Research paperFree to read2026

Data Centre Model for Transient Stability Analysis of Power Systems

IET Generation, Transmission & Distribution (Institution of Engineering and Technology (IET)) · Alberto Jiménez‐Ruiz, Federico Milano

A dynamic load model that represents a data centre through a UPS, an induction-motor cooling load and a pulsing AI load, demonstrated on the Irish transmission system with real data.

On this page

Overview

Transmission system operators are increasingly concerned about the effect of data centres on system dynamics. The paper starts from a real event: a fault caused a 204 MW drop in data-centre demand, producing a rate of change of frequency of 0.12 Hz/s and a peak of 50.22 Hz on the all-island Irish system. The generic load models used in transient stability studies do not represent this behaviour, and the work aims to fill that gap.

The proposed model has three defining features. The first is the UPS logic between server load and grid, which separates the load during a fault and reconnects it afterwards. The second is the cooling load, represented as an induction motor because they are widespread in compressors and pumps; cooling accounts for about 30% of the total consumption of standalone data centres. The third is the cyclic, pulsing load pattern produced by AI training.

The UPS disconnection logic monitors frequency and voltage; typical margins are 0.2 to 0.3 Hz for frequency and 10% of nominal voltage. Reconnection schemes covered are instant, delayed (typically 10 to 50 seconds), disturbance counting (typically three disturbances in a minute) and manual. In the case study, with a 10-second reconnection delay and a large facility (about 420 MW total), reconnection drives frequency below 49.7 Hz and disconnects the facility again, a behaviour called flapping.

The paper states that data-centre modelling for power-system analysis is at an early stage. Future work covers long-term behaviour and control strategies that change consumption gradually. The text used here is the preprint version of the same work as the published journal article.

Key points

  1. Real event: a fault dropped 204 MW of data-centre demand, with a rate of change of frequency of 0.12 Hz/s and a peak frequency of 50.22 Hz.
  2. Three core features: a UPS interface, a cooling load modelled as an induction motor, and a pulsing AI load.
  3. Cooling accounts for about 30% of the total power consumption of standalone data centres.
  4. The server load model reflects that CPU and GPU power scales with switching frequency and the square of voltage, with the operating system raising frequency gradually.
  5. Typical UPS disconnection thresholds are 0.2 to 0.3 Hz in frequency and 10% of nominal in voltage.
  6. Reconnection schemes: instant, delayed (10 to 50 s), disturbance counting (typically three disturbances in a minute) and manual (for example the DRUPS topology).
  7. Flapping risk rises with facility size and falls as grid loading rises; in the case study a 30-second reconnection delay prevents it, but the required delay cannot be known in advance.
  8. Of 104 data centres on the island of Ireland, 86 are in the Dublin metropolitan area; the share is 800 MW of a 7 GW peak and is expected to reach 1.6 GW (about 30% of demand) by 2030.

Using it in design

  • In grid-connection studies, define the data centre by its UPS disconnection and reconnection behaviour rather than as a generic load.
  • Write the UPS disconnection thresholds (frequency and voltage window) and reconnection delay into the specification and compare them with the operator's frequency limits.
  • When several large facilities share an area, design staged or coordinated reconnection timing to assess flapping risk.
  • Treat cooling motors as induction motors, including their transient current and power draw after reconnection.
  • Enter the cyclic bursts of the AI load, with their duration and period, into the model from operating data.

Who should read it

System engineers running grid-connection studies, dynamic simulation teams, and electrical designers setting UPS disconnection logic.

Document contents

  1. Introduction (motivation, literature review, contributions)
  2. Data Center Classification (constant, batched and AI load patterns)
  3. Datacenter Internal Structure (servers, cooling, back-up generator, UPS, UPS disconnection and reconnection logic)
  4. Case Study (fault near a DC, flapping, batched and AI loads, periodic transients, detailed reconnection)
  5. Conclusions

Publication details

Authors
Alberto Jiménez‐Ruiz; Federico Milano
Publisher
IET Generation, Transmission & Distribution (Institution of Engineering and Technology (IET))
Year
2026
Document language
English
Source type
Scientific
Access
Free to read
Licence
CC BY-NC-ND 4.0: share unaltered with attribution for noncommercial purposes
Original licence note

Publisher-deposited Crossref licence metadata: http://creativecommons.org/licenses/by-nc-nd/4.0/ (OpenAlex: cc-by-nc-nd); landing page blocks automated fetch, abstract read via Crossref/OpenAlex. Non-commercial licence: link/cite only in a commercial product.

Citation

Alberto Jiménez‐Ruiz; Federico Milano (2026). Data Centre Model for Transient Stability Analysis of Power Systems. IET Generation, Transmission & Distribution (Institution of Engineering and Technology (IET)). https://doi.org/10.1049/gtd2.70381

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.