Technical guideFree to read2016

Increasing Branch Circuit Reliability for Computer Rooms

Mersen · Peter Walsh

A 2016 technical note from Mersen (Selective Coordination Note 3, TT-SC3, by Peter Walsh) arguing that a short circuit on one branch must be cleared in under 20 ms (1.2 cycles at 60 Hz) so that it does not collapse the voltage of neighbouring IT loads. A current-limiting fuse clears in about 1/4 cycle; small breakers take 1 to 2 cycles and larger ones more than 4.

On this page

Overview

The four-page note concentrates on branch circuits, which hold the last overcurrent protective device in the distribution chain, and ties two topics together: collapse of the voltage wave and selective coordination. Its starting point is the ITI (CBEMA) curve. According to the curve, IT loads tolerate voltage below 70% of nominal for up to 20 ms, after which equipment function can be interrupted. When a high fault current on one branch loads the supply transformer, the voltage on every branch fed from that transformer falls together.

The author separates overloads from short circuits. During an overload the faulted circuit does not disturb the voltage of the others while it waits to be disconnected, and a properly selected breaker is sufficient. In a short circuit the response time of the protective device is decisive and should be under 20 ms. Small breakers typically clear in 1 to 2 cycles and larger ones in more than 4 cycles, whereas a fuse working in its current-limiting range opens in 1/4 cycle. A fuse therefore disturbs adjacent loads less under a high overcurrent.

For the effect of breakers standing for years without tripping, the note cites a 2008 NETA field survey. In tests on about 340,000 items, most of which had not been serviced within five years, more than 22% of breakers had an issue causing out-of-specification results and an average of 10.5% did not function at all. Suspected causes are dust, dried lubricant and corrosion; on retest, the second and later trips were often within published values. A fuse's short-circuit mechanism is solid material and does not rely on mechanical linkages.

The coordination section refers to the NEC definition and to Article 708 on critical operations power systems. Selectivity between molded case breakers depends on the magnitude of the fault current, while fuses need only a simple minimum ratio such as 2:1, independent of magnitude. The note introduces the Mersen Fused Coordination Panelboard, which combines the strengths of both: each branch pole has a breaker and a fuse in tandem. The breaker trips, and can be reset, from slight overloads up to 200%; the fuse opens in current-limiting mode on a short circuit.

The document is a manufacturer's technical note and recommends its own panel product; the comparison is framed for 60 Hz systems and North American practice (NEC, molded case breakers). Its numerical claims rest on other Mersen notes cited by the author and on the NETA survey, with no independent experiment. The criterion it sets out is clear all the same: branch protection should be assessed not only for selectivity but also for whether the fault clearing time fits the voltage tolerance of the IT load.

Key points

  1. Per the ITI (CBEMA) curve, voltage below 70% is tolerated for up to 20 ms, equal to 1.2 cycles at 60 Hz.
  2. Typical clearing times: 1 to 2 cycles for small breakers, more than 4 cycles for larger breakers, 1/4 cycle for a fuse in its current-limiting range.
  3. NETA 2008 survey: 340,000 items tested; more than 22% of breakers gave out-of-specification results and an average of 10.5% did not function at all.
  4. A minimum 2:1 ampere-rating ratio between fuses provides selective coordination at all fault current levels.
  5. Current-limiting fuses of 30 A or less typically coordinate selectively with an upstream 200 A molded case circuit breaker.
  6. In the hybrid panel the breaker trips and resets for overloads up to 200%; the fuse opens only on short circuits and high overcurrents.
  7. The panel's breakers range from 15 A to 100 A in 1, 2 or 3 poles, and only three fuse ratings are needed for short-circuit protection.
  8. The fuseholder is mechanically interlocked with the breaker so that it cannot be opened with power on.

Using it in design

  • Read the total clearing time of the branch protective device at maximum fault current from the manufacturer's curve and compare it with the 20 ms limit.
  • For racks fed from the same transformer or PDU, use the short-circuit calculation to check whether a branch fault pulls bus voltage below 70%.
  • Verify breaker-to-breaker selectivity over the full range of fault current with selectivity tables; where it cannot be achieved, consider current-limiting fuses or a fuse and breaker combination.
  • In fused schemes keep at least a 2:1 ampere-rating ratio between successive levels.
  • Add periodic trip testing of breakers to the maintenance plan, allowing for the fact that mechanisms left unoperated for years may be slow on the first trip.

Who should read it

Electrical engineers designing final distribution in data halls (PDUs, RPPs, branch panelboards) and those carrying out protection coordination and selectivity studies.

Document contents

  1. Introduction
  2. Voltage Collapse
  3. Selective Coordination
  4. Mersen Fused Coordination Panelboard
  5. References

Publication details

Authors
Peter Walsh
Publisher
Mersen
Year
2016
Document number
TT-SC3-001
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public manufacturer source inspected. No document-specific redistribution permission established; metadata and original brief summaries only. Local downloads are research evidence, not a redistribution package.

Citation

Peter Walsh (2016). Increasing Branch Circuit Reliability for Computer Rooms. Mersen. TT-SC3-001. https://www.mersen.com/sites/default/files/files_imported_ep/TT-SC3-Branch-Circuit-Reliability-for-Computer-Rooms.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.