Saving options in data centres and server rooms 2021 and 2025 (Besparingsopties in datacentra en serverruimten)

Original title Besparingsopties in datacentra en serverruimten 2021 en 2025

RVO / Certios B.V.

A 12 October 2020 LEAP report by Dr. D.H. Harryvan (Certios) for RVO surveys data-centre technologies at TRL 6 or higher that could join Dutch recognised measures lists (EML), including UPS efficiency at low load.

On this page

Overview

The report was prepared under the Innovation Track of the Low Energy Acceleration Program (LEAP) run by the Netherlands Enterprise Agency (RVO) for the Ministry of Economic Affairs and Climate Policy. Its question is which technologies not yet on the Recognised Measures List (EML) for commercial data centres and computer rooms could be added in the 2023 or 2027 update. For each technology it describes layer, saving potential, technology readiness level (TRL), implementation complexity, relevant market parties and the split between EML and sustainable management and maintenance (DBO).

The first chapter introduces the ICT service (servers, virtual machines, containers, virtual networks and storage) and facility infrastructure (power, air cooling, cold-plate liquid cooling, immersion cooling, heat rejection, air separation, heat reuse, adsorption and absorption chillers, thermal storage). Its closing table lists only technologies at TRL 6 or higher: workload management, virtualisation, server power management, network optimisation, storage modernisation, modular UPS, using the ASHRAE allowable temperature range, phase-change cold storage, direct liquid and immersion cooling, heat reuse at edge data centres, UPS grid balancing and load shedding.

Sample numbers in the table: the LEAP pilot showed 10 to 20% of energy can be saved using 'balanced' and 'power save' modes; workload management and virtualisation describe tens of percent savings by moving low-load servers onto a shared platform; 15,000 rpm disks draw about 10 to 20 W while SSDs draw under 5 W; actual UPS load is often below 30% because of redundancy and oversizing, where efficiency is markedly worse, and it can be several percentage points better at higher load. In the ASHRAE range, recommended intake is 18 to 27 and allowable 15 to 35 degrees C.

Later chapters cover the existing EML, the headings of the EU Code of Conduct (utilisation and planning, resilience, IT equipment selection, service deployment, cooling, direct liquid cooling and heat reuse) and proposed EML changes. Recommendations include placing efficiency and temperature-tolerance requirements for IT equipment directly on the end user and dealing with edge data centres, which will multiply with 5G, have connections far below 100 kW and risk falling outside the authority's view. Citing IDC, it says more than half of new data-centre infrastructure by 2023 will be at edge locations. The report is written in Dutch.

Key points

  1. The report is dated 12 October 2020, prepared for RVO under LEAP; author Dr. D.H. Harryvan (Certios B.V.).
  2. All listed technologies are at least TRL 6 and are candidates for the 2023 or 2027 EML update.
  3. Per the LEAP pilot, server power management in 'balanced' and 'power save' modes can cut energy by 10 to 20%.
  4. Virtualising low-load servers onto a shared platform can reduce energy by tens of percent.
  5. 15,000 rpm disks draw about 10 to 20 W; SSDs draw under 5 W and are faster.
  6. Actual UPS load is often below 30% because of redundancy and oversizing, where efficiency is markedly lower; modular UPS fits capacity to real demand.
  7. In the ASHRAE range, recommended intake is 18 to 27 degrees C and allowable 15 to 35; using the full range can avoid compression cooling wholly or partly.
  8. Phase-change cold storage, direct liquid and immersion cooling, UPS grid balancing and load shedding are other options assessed.
  9. The report recommends placing IT equipment requirements on end users and monitoring energy at edge data centres.

Using it in design

  • When sizing UPS, check the real load profile (including below 30%) and efficiency at low load; consider modular UPS to grow capacity with demand.
  • In cooling design, examine ASHRAE recommended and allowable intake ranges and the possibility of running summer conditions without compression cooling.
  • Evaluate direct liquid or immersion cooling and heat reuse at concept stage for high-density racks.
  • Add proximity to heat demand to site selection criteria for waste heat, especially for small edge centres.
  • Assess use of UPS batteries for grid balancing and load shedding in contract and control design.
  • Treat IT-side virtualisation and power-management measures as a separate saving line in the facility capacity plan.

Who should read it

Designers, policy staff and consultants in the Netherlands following data-centre measures lists and looking for candidate technologies.

Document contents

  1. Terms of reference
  2. Data centre technology (ICT service, facility infrastructure, heat rejection, air separation, heat reuse, overview of new technology)
  3. Existing EML
  4. European Code of Conduct
  5. Changes to the EML
  6. Recommendations

Publication details

Authors
RVO / Certios B.V.
Publisher
RVO / Certios B.V.
Year
Year not stated
Document number
PO15620027, V7 final
Document language
Dutch
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official PDF downloaded and extracted. Title horizon years and URL folder are not used to invent a publication date; year remains unknown. Open classification is not treated as a redistribution licence.

Citation

RVO / Certios B.V. Besparingsopties in datacentra en serverruimten 2021 en 2025. RVO / Certios B.V.. PO15620027, V7 final. https://www.rvo.nl/sites/default/files/2021/06/besparingsopties-in-datacentra-en-serverruimten-2021-en-2025.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.