Powercom VANGUARD VGD is a 6-20 kVA single-phase online double-conversion tower UPS: 0.7 output power factor, input power factor above 0.97, ECO mode efficiency above 94% and 0 ms transfer.

On this page

Overview

The catalogue states that Powercom's VGD family spans 700 VA to 20 kVA; the specification table covers the VGD-6000, 8000, 10K, 12K, 15K and 20K. All are single-phase tower, high-frequency double-conversion units with true sine output. Ratings are 6000 VA / 4200 W, 8000 VA / 5600 W, 10 kVA / 7000 W, 12 kVA / 8400 W, 15 kVA / 10.5 kW and 20 kVA / 14 kW, so the rated output power factor is 0.7.

Input is 208/220/230/240 V AC with a load-dependent window from 120-276 V AC (below 25% load) to 180-276 V AC (100% load). Input power factor is above 0.97 and cold start is supported. Output is ±2% voltage, 50/60 Hz ±0.25 Hz, 0 ms transfer, crest factor 3:1 and THD 3% on linear load (and 5%). Overload in line mode is 110-125% for 60 s and 125-150% for 10 s; in battery mode above 110% for 10 s. At 208 V output, capacity derates to 90%.

The battery uses 12 V 7 Ah or 9 Ah blocks, 20 on the 6000-10K models and 2x20 on the 12K-20K models, with a typical recharge of 4 hours to 90%. Features include ECO mode, free-run frequency stability, generator mode, battery remaining time display, multi-language LCD, EPO, USB/RS232 with optional SNMP and UPSMON PRO software. An external battery module is optional; sizes run from 257x590x570 mm (86 kg) to 342x760x905 mm (207 kg), with isolation-transformer versions at 123-273.5 kg.

Key points

  1. Six models: VGD-6000 (4200 W), 8000 (5600 W), 10K (7000 W), 12K (8400 W), 15K (10.5 kW), 20K (14 kW); output power factor 0.7.
  2. Single-phase, tower, double conversion, pure sine; 0 ms transfer.
  3. Input power factor above 0.97; input window 120-276 to 180-276 V AC by load.
  4. ECO mode efficiency above 94%; output voltage ±2%; capacity is 90% at 208 V output.
  5. Overload: line mode 110-125% for 60 s, 125-150% for 10 s; battery mode above 110% for 10 s.
  6. Battery: 12 V 7 Ah or 9 Ah, 20 units (2x20 for 12K-20K); recharge to 90% in 4 hours.
  7. Size and weight: 257x590x570 mm, 86 kg to 342x760x905 mm, 207 kg; transformer versions 123-273.5 kg.
  8. Communication: LCD, RS232, USB B, optional SNMP; UPSMON PRO; EPO.

Using it in design

  • With a 0.7 output power factor, compare real kW capacity (for example 14 kW for 20 kVA) against the kW load list, not kVA.
  • Carry the weight of the large single-phase unit (86-273.5 kg) into floor loading and layout.
  • Verify that generator mode and the wide input window suit generator-fed installations.
  • For the required autonomy, consider the external battery module option and the 4-hour recharge to 90%.
  • Include the 90% capacity derating at 208 V output in the load calculation.

Who should read it

Designers and integrators selecting mid-range single-phase online UPS.

Document contents

  1. Main Feature
  2. Specification (configuration, input, output, protection, battery, communication, physical)

Publication details

Authors
Powercom
Publisher
Powercom
Year
Year not stated
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document-specific redistribution permission was established. Bibliographic reference only.

Citation

Powercom POWERCOM VGD-6000–20K catalogue, revision 20240322, p.2. Powercom. https://www.upspowercom.com/pcm-img/UPS-VGD/Catalog2.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.