FirstPower Industrial Battery Products Manual: Edition 2015-01, printed p.25

FirstPower

FirstPower Technology's (Shenzhen) sealed lead-acid industrial battery manual, edition 2015-01, lists on printed page 25 the high-rate HR series for UPS duty: 6 V and 12 V blocks from 4.5 Ah to 200 Ah, with 15-minute ratings from 19 W to 710 W per cell.

On this page

Overview

The document is the 40-page product manual covering the full sealed lead-acid range of FirstPower, a Chinese manufacturer founded in 1993. After the company and quality sections it explains the features, general characteristics and capacity selection of VRLA (AGM) batteries, followed by tables for the standard FP, LFP and CFP types and the deep-cycle, long-life, high-rate discharge and high-temperature series. Gel, OPzV, OPzS, motorcycle and traction batteries have their own sections. The manual closes with terminal types and handling precautions.

For data-centre work the most relevant part is the high-rate discharge (HR) series table on printed page 25. For each model it gives nominal voltage, power at the 15-minute rate in watts per cell, nominal capacity in Ah, internal resistance, dimensions, terminal type and weight. The 15-minute power and the Ah capacity are separate columns and are not derived from one another. The series starts with the 6 V FP645HR (19 W per cell, 4.5 Ah) and ends with the 12 V LFP12200HR (710 W per cell, 200 Ah, 65 kg). Designed float service life at 20 °C is 5 years for the FP type and 10 years for the LFP type.

The general characteristics section uses curves to explain discharge, charging, life and storage behaviour. The final discharge voltage depends on current: 1.75 V per cell up to 0.1 CA, down to 1.30 V above 1.1 CA. Capacity measured outside 20 to 25 °C is corrected with a temperature coefficient of 0.006 for 20-hour and 10-hour tests and 0.01 for 3-hour and 1-hour tests. Constant-voltage charging is the recommended method; constant-current charging is not recommended for VRLA. The recharged capacity should be at least 1.02 to 1.05 times the capacity discharged.

The handling precautions bear directly on installation design: batteries are never charged in a sealed container, a gap of more than 10 mm is kept between them for ventilation where possible, and old and new units or different types and brands are not mixed. Charging takes place between 0 and 45 °C, storage temperature must stay between -20 and 50 °C, and stored batteries are recharged at least every 6 months. Open-circuit self-discharge is under 2% per month at 20 to 25 °C. The table gives a single 15-minute power point; other durations need the constant-power tables in the individual model sheets.

Key points

  1. The HR series consists of 6 V and 12 V blocks; the table runs from 4.5 Ah (FP645HR, FP1245HR) to 200 Ah (LFP12200HR, LFP6200HR).
  2. 15-minute ratings are in watts per cell: FP1270HR 31 W (7 Ah), FP1290HR 34 W (9 Ah), LFP1265HR 240 W (65 Ah), LFP12100HR 390 W (100 Ah), LFP12200HR 710 W (200 Ah).
  3. Internal resistance falls as capacity rises: FP1270HR 20 mΩ, LFP12100HR 3.5 mΩ, LFP12200HR 2.8 mΩ.
  4. Weight examples: FP1270HR 2.45 kg, LFP12100HR 32.5 kg, LFP12200HR 65 kg.
  5. Designed float service life for the HR series at 20 °C is 5 years for the FP type and 10 years for the LFP type.
  6. Final discharge voltage per cell: 1.75 V up to 0.1 CA; 1.70 V at 0.11 to 0.17 CA; 1.67 V at 0.18 to 0.25 CA; 1.60 V at 0.26 to 1 CA; 1.30 V above 1.1 CA.
  7. Self-discharge is under 2% per month at 20 to 25 °C; stored batteries are recharged at least every 6 months.
  8. Charging temperature 0 to 45 °C, storage temperature -20 to 50 °C; a ventilation gap of more than 10 mm between batteries where possible.
  9. Recharge capacity is at least 1.02 to 1.05 times the discharged capacity; a full charge in float service takes slightly more than 24 hours.

Using it in design

  • For short-duration UPS battery sizing, use the 15-minute W per cell figure: divide the required DC power by the number of cells in the string and compare with the model value; do not use the Ah column for this.
  • For autonomy times other than 15 minutes, request the constant-power discharge table for the model; do not scale from the single point.
  • Split the battery life assumption by type: FP-type HR blocks have a 5-year design life and LFP-type 10 years, both at 20 °C; set the battery room temperature accordingly.
  • In the battery cabinet layout, allow more than 10 mm between blocks and carry the block weights (65 kg for 200 Ah) into the rack and floor loading calculation.
  • Choose the end-of-discharge voltage by discharge current; for high-rate UPS discharges the 1.60 V or 1.30 V per cell limit must agree with the UPS low-DC-voltage setting.
  • Add the 6-month refresh charge to the storage and commissioning plan.

Who should read it

Electrical engineers sizing UPS battery strings, procurement teams comparing battery suppliers, and battery room operators.

Document contents

  1. Company Profile
  2. Company Construction
  3. Quality Control
  4. Researching and Development
  5. Company History
  6. VRLA (AGM) Battery: Features, Applications, General Characteristics, Battery Capacity Selection
  7. Standard Battery Series: FP Type, LFP Type, CFP Type
  8. Deep Cycle Battery Series
  9. Long Life Battery Series
  10. High Rate Discharge Battery Series
  11. High Temperature Battery Series
  12. Gel Battery (Gelled Electrolyte)
  13. CFPV & LFPV (OPzV) Battery
  14. CFPS & LFPS (OPzS) Battery
  15. Motorcycle Battery
  16. Traction Battery
  17. Battery Terminals and Position
  18. Handling Precautions

Publication details

Authors
FirstPower
Publisher
FirstPower
Year
2015
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document-specific redistribution permission was established. Bibliographic reference only. Original publisher HTTP URL retained as a bibliographic link. Its HTTPS counterpart could not be verified on 2026-11-16; no content was downloaded or redistributed.

Citation

FirstPower (2015). FirstPower Industrial Battery Products Manual: Edition 2015-01, printed p.25. FirstPower. http://efirstpower.com/download/FirstPower%20Product_Manual_201501.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace