Data Center Projects: Standardized Process

Schneider Electric · Neil Rasmussen, Suzanne Niles

Schneider Electric WP 140 proposes a standardized, configurable process for data centre physical-infrastructure build and upgrade projects, separating the system being built from the process that creates it.

On this page

Overview

The process has four sequential phases: Prepare, Design, Acquire and Implement. Prepare and Design form the PLAN portion; Acquire and Implement form the BUILD portion. Each phase is made of steps with an owner, a task list, and defined inputs and outputs, and each ends in a milestone: commit to project, purchase order submitted, equipment delivered, and project complete.

What turns an upgrade into a 'project' is a change in power or cooling architecture, the introduction of risk, a need for planning and coordination, or a need to shut down equipment. Three asynchronous activities can be triggered at any point: project change management, product defect correction and process defect correction. Engineered-to-order projects add steps for custom solution design, factory acceptance test and commissioning, which is whole-system testing after installation.

Every step has an owner, a task list (work instructions plus a checklist), inputs that are outputs of earlier steps, and outputs needed downstream. This creates a pull-based flow in which every output feeds a downstream step. The Start-up step comprises five tasks: verify correct assembly, verify operating mode, third-party device configuration, basic software configuration and basic operator training.

The paper stresses explicit responsibility assignment. A responsibility checklist assigns every process step to the user, the primary equipment vendor or a third party, or marks it not needed. The text makes no quantitative performance claim; its value is in writing down in advance who owns each step and where each output goes.

Key points

  1. Four phases: Prepare and Design form PLAN; Acquire and Implement form BUILD.
  2. Milestones: commit to project, purchase order submitted, equipment delivered, project complete.
  3. A change in power or cooling architecture, risk, need for planning/coordination or equipment shutdown elevates an upgrade to a 'project'.
  4. Three asynchronous activities: project change management, product defect correction, process defect correction.
  5. Engineered-to-order projects add custom solution design, factory acceptance test and commissioning.
  6. Start-up has five tasks: verify assembly, verify operating mode, third-party device configuration, basic software configuration, basic operator training.
  7. Every step has an owner, task list, inputs from earlier outputs and outputs for downstream steps.
  8. A responsibility checklist assigns each step to user, primary vendor, third party or not needed.

Using it in design

  • Plan project phases, steps and milestones-Prepare, Design, Acquire and Implement-and assign each deliverable an owner and a dependent next step.
  • Prepare a responsibility matrix for the customer, vendor and third party, marking unnecessary tasks explicitly; confirm every required step has an owner before milestone approval.
  • Auto-insert factory acceptance test and commissioning tasks when the design contains engineered-to-order equipment.
  • Keep a change log and defect register available at every phase and export a start-up checklist from the design's equipment list.

Who should read it

Project managers running data centre builds and teams defining a design workflow.

Publication details

Authors
Neil Rasmussen; Suzanne Niles
Publisher
Schneider Electric
Year
2011
Document number
WP 140
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document

Citation

Neil Rasmussen; Suzanne Niles (2011). Data Center Projects: Standardized Process. Schneider Electric. WP 140. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_DBOY-6KVM82_EN

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.