Avtron's September 2021 white paper surveys load-bank use in data centres across four applications (commissioning, expansion, maintenance, equipment replacement) for generators, UPS, HVAC, PDUs and bus systems.

On this page

Overview

The paper surveys how load banks are used in testing and maintaining data-centre power and cooling systems. It notes that downtime commonly costs hundreds of thousands of dollars per hour, risks SLA penalties, and that power availability underpins service continuity. Four primary applications are listed: commissioning, expansion, maintenance and periodic testing, and equipment replacement.

In commissioning, backup diesel generators, UPS, HVAC, electrical bus and distribution cabling, PDUs and remote power panels are tested; because full facility load is not available during construction, load banks simulate design conditions. Resistive load banks placed where heat loads will sit verify cooling capacity and balance airflow, and networking load banks gives common control and data collection. In expansion, evidence of power and cooling performance for new racks can be reported to colocation customers.

By equipment: generator testing verifies the voltage regulator, governor, cooling, fuel and control systems and avoids diesel wet stacking from insufficient load, using resistive or resistive-inductive banks. UPS testing discharges the batteries to manufacturer specification and evaluates inverter performance. Substation tests cover capacity, relays and meters; PDUs (100-300 kVA) are tested with portable castor-mounted banks; bus systems are tested at feeds and tap-offs. Load type must match the load character; motor loads call for inductive banks.

Key points

  1. Four applications: commissioning, expansion, maintenance and periodic testing, equipment replacement.
  2. Downtime can commonly cost hundreds of thousands of dollars per hour.
  3. Systems tested: backup generators, UPS, HVAC, substation, PDUs, remote power panels and bus systems.
  4. Generators use resistive and resistive-inductive banks; applying load avoids diesel wet stacking.
  5. UPS testing typically uses resistive permanent load banks, with batteries discharged per manufacturer specification.
  6. For HVAC, portable resistive load banks emulate heat output and can create hot spots.
  7. PDUs are often 100-300 kVA and are tested with portable castor-mounted load banks.
  8. Networked load banks run from one controller and automate data collection and reporting.

Using it in design

  • In the commissioning plan, define load-bank connection points and load types (resistive or inductive) for generator, UPS, HVAC, PDU, RPP and bus.
  • Write a test plan that places resistive load banks at future heat-load locations to verify design conditions without full IT load.
  • Put generator testing into the periodic maintenance programme and set a minimum load condition that avoids wet-stacking risk.
  • Add load testing after expansion and equipment replacement to the acceptance procedure.
  • Specify networked load-bank control that collects test data automatically and compiles reports.

Who should read it

Data-centre commissioning and maintenance engineers, generator and UPS test planners and colocation operators.

Document contents

  1. Background Information
  2. Load Bank Use in Data Centers: Commissioning, Expansion, Maintenance and Periodic Testing, Equipment Replacement
  3. Types of Load Banks for Data Center Systems
  4. Backup Diesel Generators
  5. HVAC Systems
  6. UPS Systems
  7. Substation
  8. Power Distribution Units
  9. Remote Power Panels
  10. Bus Tracks
  11. Summary

Publication details

Authors
Avtron Power Solutions
Publisher
Avtron Power Solutions
Year
2021
Document number
Revision: September 2021
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public manufacturer source inspected. No redistribution permission established. Metadata and original brief summaries only; local files are research evidence, not a redistribution package.

Citation

Avtron Power Solutions (2021). Load Bank Use in Data Centers. Avtron Power Solutions. Revision: September 2021. https://avtronpower.com/wp-content/uploads/2022/10/Load-Bank-Use-in-Data-Centers-2022-r2.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.