FAQ on Data Centre Requirements under the Energy Efficiency Act (EnEfG)
Original title FAQ zu Anforderungen an Rechenzentren aus dem Energieeffizienzgesetz (EnEfG)
BMWK / BAFA
The German Federal Ministry for Economic Affairs and BAFA FAQ of 11 June 2024 interprets EnEfG data-centre duties: reporting by 31 March, a management system by 1 July 2025, and certification from 1 MW in 2026.
On this page
Overview
The document helps with practical implementation of the data-centre requirements of Germany's Energy Efficiency Act (EnEfG). The answers reflect the legal views of the Federal Office for Economic Affairs and Export Control (BAFA) and the Federal Ministry for Economic Affairs and Climate Action after joint discussion. It is a question-and-answer paper of seven pages, in German.
Three points stand out in the scope definitions. First, the threshold quantity, the non-redundant electrical nominal connected load, covers the nominal power of IT and all building services needed for operation; it is normally set by the maximum power in the contract with the grid operator, or, if none exists, by the sum of non-redundant breakers on the low-voltage main distribution. Second, each independent building counts as a separate data centre; extensions and campus buildings are usually assessed separately. Third, an operator cannot report several data centres in aggregate.
Deadlines and duties are as follows: information is published and sent to the Federal Government every year by 31 March for the previous calendar year. Extended dates apply for 2024 and 2025: 15 August 2024 for 500 kW and above, and 1 July 2025 for 300 to under 500 kW. An energy or environmental management system (ISO 50001:2018 or EMAS) must be in place by 1 July 2025; from 1 January 2026, validation or certification is mandatory for centres of 1 MW and above and for publicly owned centres of 300 kW and above.
The paper also explains that the renewable-electricity requirement can be met with certificates or a PPA, that renewable electricity generated on site counts, that federal funding such as EEW and BEW supports liquid cooling and heat reuse, and that data are reported only to the national register. It is an interpretation and does not replace the legally binding statute.
Key points
- The non-redundant nominal connected load, the scope threshold, includes IT and all necessary building services; it is set by the contractual maximum power or the sum of non-redundant breakers on the low-voltage main distribution.
- IT nominal connected load is the maximum design power of the UPS supplying the whitespace.
- Each independent building is a separate data centre; extensions and campus buildings are usually assessed separately; several centres cannot be reported in aggregate.
- Reporting is due by 31 March each year for the prior year; first-period deadlines are 15 August 2024 for 500 kW and above and 1 July 2025 for 300-500 kW.
- An energy (ISO 50001:2018) or environmental (EMAS) management system must be implemented by 1 July 2025.
- From 1 January 2026 the management system must be validated or certified for centres of 1 MW and above and for publicly owned centres of 300 kW and above.
- The renewable-electricity requirement can be met by certificates, a PPA or EU green electricity certificates, and on-site renewable generation counts.
- About 145.4 TWh of guarantees of origin were cancelled for 2021; the energy volume covered by section 11 is taken as about 12 TWh.
- EEW funding supports liquid-cooled IT and infrastructure such as pumps, heat exchangers, piping and dry coolers; BEW supports new heat networks with at least 75% renewable and waste heat and a maximum flow temperature of 95 °C.
Using it in design
- Calculate the site's non-redundant nominal connected load at the start of design and document which of the 300 kW, 500 kW and 1 MW thresholds (reporting, management system, certification) it exceeds.
- Record the UPS rating as the IT nominal connected load and keep the list of non-redundant breakers on the low-voltage main distribution current; these two values underpin the reported data.
- If several buildings are planned on one campus, allow for each being a separate data centre needing its own monitoring and reporting.
- Include sub-metered energy monitoring, an ISO 50001-compatible management system and the annual data-collection process in the design before commissioning.
- For heat reuse or liquid-cooling investments, check EEW and BEW funding conditions (for example a maximum flow temperature of 95 °C in the heat network) in pre-feasibility.
Who should read it
Engineers designing or operating data centres in Germany, compliance officers, and consultants answering questions on EnEfG scope, deadlines and reporting.
Document contents
- Non-redundant electrical nominal connected load and how to determine it
- Definition of a data centre (structure, campus, out-of-scope facilities)
- Definition of whitespace and aggregated reporting
- Publication of information, deadlines and 2024-2025 transition dates
- Proof of renewable electricity (certificates, PPA, own generation)
- Energy and environmental management system, certification duty
- Company account and organisation certificate
- Funding programmes (EEW, BEW)
- Guide to data points and EU legislation
- Definition of customer and IT nominal power
- Availability of 100% renewable electricity for 2027
Publication details
- Authors
- BMWK / BAFA
- Publisher
- BMWK / BAFA
- Year
- 2024
- Document number
- Status: 11 June 2024
- Document language
- German
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public publisher text inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only.
Citation
BMWK / BAFA (2024). FAQ zu Anforderungen an Rechenzentren aus dem Energieeffizienzgesetz (EnEfG). BMWK / BAFA. Status: 11 June 2024. https://www.bundeswirtschaftsministerium.de/RZReg/Downloads/faq-anforderungen-rechenzentren-im-enefg.pdf?__blob=publicationFile&v=1
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.