Regulatory

Browse sources on regulation and public policy relevant to data centre projects. Verify the current text, effective date and applicability to your project with the responsible official source.

Key numbers

Values hold under the conditions stated in each source. Read the cited page before using one in your project.

QuantityValueConditionSource
Reporting threshold (installed IT power)at least 500 kWEU EED Art. 12(1)European Parliament and Council of the European Union, 2023 · p. 49
Start date of annual reporting15 May 2024Repeated every year afterEuropean Parliament and Council of the European Union, 2023 · p. 49
PUE limit of class A in the EU ratingA <= 1.15Class G is above 1.9European Commission, 2026 · p. 2
Waste heat obligation threshold (total rated energy input)above 1 MWUnless shown technically or economically infeasibleEuropean Parliament and Council of the European Union, 2023 · p. 62
Germany EnEfG: renewable electricity share100% from 1 Jan 202750% from 1 Jan 2024; balance-sheet basisBundesamt fuer Justiz (gesetze-im-internet.de), 2023 · Section 11(5)
Fine for not filing a verified GHG report on timeTRY 500,000-5,000,000Doubled for ETS installationsTürkiye Büyük Millet Meclisi, 2025 · Madde 14(1)(a)-(b) and footnote

Design checklist

  1. Calculate WUE at the start of design (total water input / IT energy) and use the 0.4 m3/MWh target as a constraint in cooling technology choice. (European Commission, 2026)
  2. Align the PUE target of new designs with the proposed MPS: design PUE below 1.3 and operational PUE below 1.4 in the first three years; for existing sites plan the path to below 1.5 by 2030. (European Commission, DG ENER (AIT, Borderstep Institute, EY), 2025)
  3. At 1 MW or more of installed IT power use the latest EU Code of Conduct best practices as a design checklist. (European Parliament and Council of the European Union, 2023)
  4. In the grid-connection study, support firm and non-firm (curtailable, phased, dynamic-limit) options and size the BESS or genset capacity needed to ride through curtailment hours. (International Energy Agency, 2026)
  5. Evaluate data-centre waste heat use in district heating or neighbouring facilities as its own siting criterion. (U.S. Department of Energy / Federal Register, 2025)

Start with these sources

Related standards and regulations

Calculators and product

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

All documents in this topic

1–24 / 216

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.