M&V Guidelines: Measurement and Verification for Performance-Based Contracts Version 5.0: Data Center Addendum Version 1.0
U.S. Department of Energy, FEMP · Kim Traber, Steve Greenberg et al.
A 2025 U.S. DOE FEMP addendum explaining how to measure and verify data-centre savings in performance-based energy contracts, adding nine data-centre-specific measures.
On this page
Overview
The document is an addendum to FEMP's September 2024 M&V Guidelines 5.0, written by authors from Traber Engineers, LBNL, PNNL and NREL. It repeats the parent document's section headings and adds content only where data centres need it. Its basis is the data-centre efficiency language in the 2007 Energy Independence and Security Act and the Energy Act of 2020.
The opening sections characterise data centres by continuous operation, constant cooling, high energy intensity, UPS and generator redundancy, and hot/cold aisle separation. Items to add to the risk matrix include whether IT load is measured or stipulated, who is responsible for equipment performance, and PUE and uptime requirements.
Data-centre notes are given for the four M&V options. For Option A, manufacturer data may describe a single standard operating point and must be corrected to actual conditions. For Option B, continuous EMCS measurement at 15, 30 or 60 minute intervals is suggested. Option C is described as more applicable in data centres because operation is homogeneous and sub-systems are usually metered. For Option D, air-side modelling can mislead and an experienced data-centre modeller should be consulted.
Section 6 gives measure-by-measure guidance: EMCS control points and sensor placement, air management, networked CRAC/CRAH controls, VAV conversion, heat recovery, air-side and water-side economisers, humidity control, cooling towers, motors and variable-speed pumping, battery and thermal energy storage, efficient IT equipment and efficient UPS. Each measure comes with a table of parameters, periods and sampling.
Key points
- The addendum attaches to M&V Guidelines 5.0 and adds nine new data-centre measures.
- Sampling for most parameters is 90% confidence with 10% precision or 80% confidence with 20% precision (90/10 or 80/20).
- Option B: continuous EMCS measurement every 15, 30 or 60 minutes; monthly or quarterly trend review catches issues earlier.
- Option C is treated as more practical in data centres than in occupied buildings because of homogeneous operation and sub-metering.
- Manufacturer curves may refer to one condition (for example a specific chilled water and condenser water temperature) and need correction.
- Air-side economisers can run more hours than in occupied spaces because the typical maximum at the rack face is 80 °F.
- Option A suits the efficient UPS measure; efficiency is output power over input power.
- UPS routes: a more efficient unit, a switching UPS with eco-mode, modular UPS, and shutting down unneeded modules while keeping redundancy.
Using it in design
- For an energy savings contract, decide at design stage which EMCS points are logged continuously (IT power, IT inlet temperature and humidity, cooling capacity) to support baseline and guarantee.
- In the risk matrix, state whether IT load is measured or stipulated, and record PUE and uptime commitments.
- When using manufacturer curves, check the water temperatures and load factor they assume and correct to actual operation.
- Before trusting air-side simulation, have an experienced data-centre modeller check the inputs.
- In UPS replacement, evaluate eco-mode, modular staging and module shutdown without reducing the redundancy level.
- For cooling tower and economiser measures, carry the temperature, flow and power parameters from the measurement tables into the metering point list.
Who should read it
Engineers, ESCOs and public agencies running data-centre efficiency projects under performance-based contracts.
Document contents
- Introduction
- Overview of M&V
- Risk and Responsibility in M&V
- Detailed M&V Methods
- Selecting an M&V Approach
- Guidance for Specific ECMs
- Glossary
- References
Publication details
- Authors
- Kim Traber; Steve Greenberg; Philip E. Coleman; Ian Hoffman; Dale Sartor; Christine E. Walker; Philip Voss; Shankar Earni
- Publisher
- U.S. Department of Energy, FEMP
- Year
- 2025
- Document number
- DOE/FEMP-0037, August 2025
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
No document-specific redistribution permission was established. Bibliographic reference only.
Citation
Kim Traber; Steve Greenberg; Philip E. Coleman; Ian Hoffman; Dale Sartor; Christine E. Walker; Philip Voss; Shankar Earni (2025). M&V Guidelines: Measurement and Verification for Performance-Based Contracts Version 5.0: Data Center Addendum Version 1.0. U.S. Department of Energy, FEMP. DOE/FEMP-0037, August 2025. https://www.energy.gov/sites/default/files/2025-09/femp_mv_5_0_data-center-addendum_092025.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.