Guidance on the UPS ENERGY STAR Test Method (December 12, 2013)
U.S. Department of Energy / U.S. EPA (ENERGY STAR) · Bryan Berringer
A one-page US DOE letter answering stakeholder questions on the 2013 ENERGY STAR UPS test method. It clarifies default settings, three-phase versus single-phase input, dc-output test voltage, the steady-state check at 0% load and the measurement period.
U.S. public domain: U.S. Government work; free to reuse
On this page
Overview
The document is a letter from the DOE test-method lead for the ENERGY STAR UPS programme. EPA and DOE published the final UPS test method on 10 May; stakeholders then sent further questions, and DOE decided to add guidance. The text was last updated on 12 December 2013.
A table covers five topics. As a general rule, any setting the test method does not explicitly address stays in its as-shipped (default) configuration. UPSs that accept both three-phase and single-phase input are tested on three-phase power. If a dc-output UPS cannot run at the test voltage given in Table 2, the highest normal operating voltage it supports is used instead.
The steady-state check applies only to the stability of conversion efficiency under active loads, so it is not needed at 0% load; the UPS must nevertheless be thermally stabilised for 125% of the manufacturer-specified time before the power measurement. Measurement may run longer than 15 minutes, in which case the actual period replaces t in Equation 1 for PAVG. DOE data indicate that longer durations do not alter the average efficiency.
Key points
- Settings not covered by the test method remain in as-shipped default configuration.
- UPSs supporting both three-phase and single-phase input are tested on three-phase power.
- A dc-output UPS that cannot run at the Table 2 voltage is tested at its highest normal operating voltage.
- No steady-state check at 0% load, but stabilisation still lasts 125% of the manufacturer time.
- Measurement longer than 15 minutes is allowed; the actual period is used for t in Equation 1.
- DOE data show durations over 15 minutes do not change average efficiency.
Using it in design
- When ingesting vendor UPS efficiency figures, record the input configuration (three-phase) and whether the values follow ENERGY STAR or IEC 62040-3 methods.
- Treat mode settings that are not specified as factory default in the loss model.
- Label the 0% load (no-load loss) point as a value taken after thermal stabilisation only.
Who should read it
Electrical design engineers who use UPS efficiency data in catalogues or loss models, and test laboratories.
Document contents
- General: default settings
- Section 3.B: three-phase and single-phase input power
- Section 3.D: dc-output voltage for test
- Section 5.B: steady-state check at 0% load
- Section 5.C.2: measurement period
Related standards
- IEC 62040-3
- ENERGY STAR UPS Test Method
Read the document
energystar-ups-test-method-guidance-2013.pdf
U.S. public domain: U.S. Government work; free to reuse
The document is provided unaltered because its licence permits redistribution.
Publication details
- Authors
- Bryan Berringer
- Publisher
- U.S. Department of Energy / U.S. EPA (ENERGY STAR)
- Year
- 2013
- Document language
- English
- Source type
- Government / public
- Access
- Open licence (downloadable)
- Licence
- U.S. public domain: U.S. Government work; free to reuse
- Licence evidence
- www.copyright.gov
Original licence note
Letter from the DOE test-method lead for the ENERGY STAR UPS program, published by EPA/DOE on energystar.gov; U.S. government work (17 U.S.C. 105).
Citation
Bryan Berringer (2013). Guidance on the UPS ENERGY STAR Test Method (December 12, 2013). U.S. Department of Energy / U.S. EPA (ENERGY STAR). https://www.energystar.gov/sites/default/files/asset/document/Guidance%20on%20the%20UPS%20ENERY%20STAR%20Test%20Method_Dec2013_0.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.