Data-centre Energy Efficiency: New Measures Effective April 2026

Original title Data-centre energy efficiency: new measures effective April 2026

Japan Agency for Natural Resources and Energy (METI)

Japan Agency for Natural Resources and Energy (METI): the existing benchmark objective is PUE of 1.4 or less by FY2030, and new facilities established from FY2029 are expected to reach PUE of 1.3 or less from the fiscal year after two years of operation.

On this page

Overview

The official explanation from Japan's Agency for Natural Resources and Energy describes the expanded data-centre reporting and efficiency framework. It includes operator categories and a phased target for new facilities. It separates the existing benchmark objective from the new construction requirement: the existing benchmark is PUE of at most 1.4 by FY2030, while new facilities established from FY2029 are expected to meet PUE of at most 1.3 from the fiscal year after two years of operation.

The expansion adds hosting and cloud tenant operators to the housing and owner categories. The measures apply from April 2026. For operators planning new facilities and reporting obligations, the source settles which PUE thresholds apply from which dates and to which groups of facilities.

Key points

  1. Existing benchmark objective: PUE of 1.4 or less by FY2030.
  2. New facilities established from FY2029 are expected to meet PUE of 1.3 or less from the fiscal year after two years of operation.
  3. The framework covers hosting and cloud tenant operators in addition to housing and owner categories.
  4. The new measures apply from April 2026.
  5. The existing benchmark objective and the new construction requirement are separate provisions.

Using it in design

  • For facilities commissioned in Japan after FY2029, treat PUE of 1.3 or less as a design criterion based on measurement after the second year of operation.
  • For existing facilities, make PUE of 1.4 or less for FY2030 the reference of the efficiency improvement plan.
  • For organisations acting as tenant or cloud operators, check by operator category whether the reporting obligation applies.
  • Settle PUE measurement points and the reporting method at design stage.

Who should read it

Teams designing and operating data centres in Japan, tenant operators and energy compliance advisers.

Publication details

Authors
Japan Agency for Natural Resources and Energy (METI)
Publisher
Japan Agency for Natural Resources and Energy (METI)
Year
2026
Document language
Japanese
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official Japanese explanatory article dated 20 May 2026, correction note 4 June 2026. Linked detailed guideline PDF was inaccessible; this entry summarizes the opened article only.

Citation

Japan Agency for Natural Resources and Energy (METI) (2026). Data-centre energy efficiency: new measures effective April 2026. Japan Agency for Natural Resources and Energy (METI). https://www.enecho.meti.go.jp/about/special/johoteikyo/data_center2026.html

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.