Netherlands Enterprise Agency (RVO)

Dutch RVO guidance: data centres with at least 500 kW installed IT power report their energy efficiency every year (16 March to 15 May in 2026); 36% of EU data centres, or 770 sites, took part.

On this page

Overview

The RVO page describes the reporting and publication duty arising from the European Energy Efficiency Directive (EED, Article 12). The owner or manager of a data centre with installed IT power of at least 500 kilowatts must report its energy efficiency each year, and the organisation carrying out the environmentally burdensome activity files the report. The 2026 reporting window was 16 March to 15 May. Installed IT power is the sum of nominal power of the IT equipment (networks, servers, storage) in the data centre's computer room; equipment in public, common and office spaces, single servers, single racks and wifi points are excluded.

Three data-centre types (enterprise, colocation and co-hosting) fall under the same obligation and answer the same questions. Only centres performing solely defence or disaster-response tasks are exempt; centres partly used for these tasks must still report and publish. Each answer can be marked commercially confidential and is then not published, but the interest in confidentiality must be shown to outweigh the interest in openness. Published data are in the Excel file on the page.

The European Commission commissioned an assessment based on data reported in 2024. 36% of EU data centres, 770 sites, took part; it examined energy efficiency, water-use efficiency, energy reuse factor and renewable energy factor. The report says data quality and completeness can improve and proposes making the reporting system clearer, more reliable and easier to use. Since early 2026 an EU dashboard shows aggregated data. RVO supervises and enforces, and provides a degree-day calculator for cooling.

Key points

  1. The threshold is installed IT power of at least 500 kW; scope is the nominal power of IT equipment in the computer room.
  2. The 2026 reporting window was 16 March to 15 May.
  3. Enterprise, colocation and co-hosting types fall under the same obligation.
  4. Only centres performing solely defence or disaster-response tasks are exempt; partial use gives no exemption.
  5. Answers can be marked commercially confidential, which requires showing that confidentiality outweighs openness.
  6. 36% of EU data centres took part in reporting: 770 sites.
  7. The Commission report examined energy efficiency, water-use efficiency, energy reuse and renewable energy factors and finds data quality needs to improve.
  8. Since early 2026 an EU dashboard shows aggregated data; RVO's degree-day calculator is used for cooling days in the report.

Using it in design

  • For a Dutch facility, set scope by installed nominal IT power (500 kW) and computer-room equipment only.
  • Define metering points for energy, water, reuse and renewable factors in the design.
  • Document the reference temperature and climate data used in the cooling degree-day calculation for the report.
  • Prepare in advance the justification for answers to be marked commercially confidential.
  • Write the reporting window (16 March to 15 May) into the operations calendar.

Who should read it

Owners and managers of data centres in the Netherlands, design teams and compliance managers handling EU reporting duties.

Document contents

  1. Which data centres are covered
  2. Installed IT power
  3. Equipment not part of the report
  4. Three data-centre types
  5. Exemption
  6. Publication duty
  7. EU results and dashboard
  8. Supervision and enforcement
  9. Why report
  10. Laws and regulations
  11. Degree-day calculator

Publication details

Authors
Netherlands Enterprise Agency (RVO)
Publisher
Netherlands Enterprise Agency (RVO)
Year
Year not stated
Document language
Dutch
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public publisher text inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only.

Citation

Netherlands Enterprise Agency (RVO) Rapportageplicht energie-efficiëntie datacentra. Netherlands Enterprise Agency (RVO). https://www.rvo.nl/onderwerpen/energiebesparingsplicht/eed-auditplicht/rapportageplicht-datacentra

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current