Technical guideFree to readYear not stated

BPC Energy Static Transfer Switches (50-800 A)

Original title BPC Energy Static Transfer Switches: Technical Specification

BPC Energy

BPC Energy static transfer switches: automatic or manual transfer between two AC sources, under 4 ms for synchronous sources, 50-800 A, bringing 2N architecture to single-fed loads.

On this page

Overview

The product page presents BPC Energy's automatic static transfer switches (STS). The device transfers automatically or manually between two AC power supplies; the page gives a transfer time of less than a quarter of a cycle. Installing an STS achieves 2N architecture and lets single-fed loads always be supplied by the best source. Switching is automatic when the incoming supply leaves a user-defined window, or manual when an operator forces it from the mimic panel or a remote connection.

Features: selectable preferred source and transfer method, break-before-make transfer, under 5 ms between synchronised sources (the technical row gives under 4 ms for synchronous and under 10 ms for non-synchronous sources), a switched-neutral option that keeps the sources isolated, and adjustable delay (non-synchronous). Ratings are 50, 100, 150, 200, 250, 300, 400, 600 and 800 A.

Overload capability is 0-100% continuous, 101-150% for 1 min, 151-200% for 10 s and over 200% for 250 ms. Protections are output overload and short circuit, over-temperature, backfeed and SCR fault; programmable relay outputs (dry contacts) are provided. The page notes better maintainability of switchboards in 2N distribution and protection against source interruptions or distribution-line failures.

Key points

  1. The STS transfers automatically or manually between two independent AC sources.
  2. Transfer time: <4 ms for synchronous and <10 ms for non-synchronous sources; under a quarter cycle per the page text.
  3. Ratings: 50, 100, 150, 200, 250, 300, 400, 600, 800 A.
  4. Overload: 100% continuous, 101-150% 1 min, 151-200% 10 s, >200% 250 ms.
  5. Protections: output overload and short circuit, over-temperature, backfeed, SCR fault.
  6. Switched-neutral option keeps the sources isolated.
  7. Programmable dry-contact relay outputs; mimic panel and remote control.

Using it in design

  • Feed single-corded loads from two independent UPS lines through an STS in a 2N architecture.
  • If sources are not synchronised, compare the up to 10 ms transfer with load tolerance.
  • Where neutral isolation between sources is needed, write the switched-neutral option into the specification.
  • Choose STS current from the load and the short-time overload curve up to 200%.

Who should read it

Data-centre electrical engineers designing 2N power distribution and critical-load transfer.

Document contents

  1. Static transfer switches
  2. Features
  3. Technical specification
  4. Accreditations and certifications

Publication details

Authors
BPC Energy
Publisher
BPC Energy
Year
Year not stated
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document-specific redistribution permission was established. Bibliographic reference only.

Citation

BPC Energy BPC Energy Static Transfer Switches: Technical Specification. BPC Energy. https://www.bpc-ups.com/products/switches-regulators/static-transfer-switches

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.