Speed to Power: Solutions for Accelerating Large Load Connections

Lawrence Berkeley National Laboratory · Fredrich Kahrl, Natalie Mims Frick

LBNL report reviewing the bottlenecks in connecting data centres and other large loads to the grid and organising more than 40 potential solutions into functional areas.

On this page

Overview

This report from Lawrence Berkeley National Laboratory (LBNL), written by Fredrich Kahrl and Natalie Mims Frick, was published in 2026. The study reviews documents and literature on the bottlenecks in connecting data centres and other large loads.

The report identifies more than 40 potential solutions to speed connections and groups them into functional areas: load forecasting, interconnection, resource planning and procurement, markets and operations, and cost allocation and ratemaking. Flexible interconnection options include staggered connections and static and dynamic flexible interconnection (Solution Area S6). Bring-your-own-generation (BYOG) and pay-for-transmission incentives are also among the solutions (S4.3).

The report is a review of documents and literature; it does not rank each solution's cost or impact quantitatively. The information in this record comes from the abstract and the solution table. As it addresses mainly the US grid structure, transfer to different regulatory environments such as Turkey needs care.

Key points

  1. More than 40 potential solutions to speed large load connections are identified.
  2. Solutions are grouped into load forecasting, interconnection, resource planning and procurement, markets and operations, and cost allocation/ratemaking.
  3. Flexible interconnection options include staggered connections and static and dynamic flexible interconnection (S6).
  4. BYOG and pay-for-transmission incentives are among the solutions (S4.3).
  5. The report is based on a review of documents and literature.
  6. Authors are Fredrich Kahrl and Natalie Mims Frick; published 2026.

Using it in design

  • Add interconnection strategy options (staged or phased energisation, flexible or curtailable service, BYOG) to the campus power plan.
  • Define phase-by-phase MW ramp inputs in the planning tools.
  • Manage connection schedule risk with a checklist of which solutions to discuss with the grid operator.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Review your power design in SoSo CAD

Inspect supply paths, equipment loads and UPS failure scenarios in one model.

Request a demo
Single-line diagram in the SoSo CAD power and capacity workspace

Who should read it

Investors planning large load connections, campus power planners and engineers following grid interconnection policy.

Publication details

Authors
Fredrich Kahrl; Natalie Mims Frick
Publisher
Lawrence Berkeley National Laboratory
Year
2026
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document
Original licence note

LBNL (contractor-operated DOE laboratory) resource; not US-Gov public domain. Cited only.

Citation

Fredrich Kahrl; Natalie Mims Frick (2026). Speed to Power: Solutions for Accelerating Large Load Connections. Lawrence Berkeley National Laboratory. https://eta-publications.lbl.gov/sites/default/files/2026-06/lbnl_large_loads_speed_to_power_final_1.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.