Prefabricated White Space Module Time Study: Lessons from a High-Density Liquid-Cooled Deployment

Schneider Electric · Wendy Torell, Melissa Rodriguez et al.

Schneider Electric WP 238 uses a site time study with a colocation operator to show how much less field labour a factory-built prefabricated IT pod needs than a traditional stick-built fit-out.

On this page

Overview

The study compares the same kind of high-density liquid-cooled white space built two ways: traditional stick-built installation, and a factory-built pod that integrates structural frame, busway, TCS piping, containment and cable shelving. The pod covers about 1,000 ft2 (93 m2), up to 42 rack positions and 1.2 MW of IT load, averaging about 29 kW per rack. The time study was carried out with a colocation operator.

Measured on-site installation took 75.5 hours per pod traditionally against 15 hours prefabricated, an 80% reduction. The traditional breakdown was TCS piping 37 hours, busway 13 hours, cable shelving 5 hours and pod/containment assembly 17.25 hours. The prefabricated approach removes the first three from the site entirely. In total, 60.5 hours of field work per pod move into the factory, which is the entire gap between the two methods, and 50 of those hours come from piping and busway.

The paper also reports a learning curve: earlier pods took 18 hours on site against 15 hours for later ones, a 17% improvement. The authors recall that a prior Schneider analysis found about 30% lower TCO for prefabricated deployments and argue that prefabrication shortens time-to-compute for AI capacity. The limit is that the result rests on hour measurements from a single deployment, and the cost comparison is the cited earlier analysis rather than a measurement here. It is still directly usable for schedule planning because it shows exactly which work items disappear from the site.

Key points

  1. On-site installation per pod: 75.5 h traditional versus 15 h prefabricated (80% reduction).
  2. Pod scope: about 1,000 ft2 (93 m2), up to 42 rack positions, 1.2 MW IT, about 29 kW per rack average.
  3. Traditional breakdown: TCS piping 37 h, busway 13 h, cable shelving 5 h, pod/containment assembly 17.25 h.
  4. Prefabrication removes piping, busway and shelving installation from the site.
  5. Learning curve: earlier pods 18 h on site versus 15 h later, a 17% improvement.
  6. A prior Schneider analysis is cited for about 30% lower TCO for prefabricated deployments.

Using it in design

  • Offer a 'prefabricated IT pod' option in the white-space designer, with catalog defaults 1.2 MW, 42 racks, 93 m2.
  • In the schedule estimator use about 15 h of on-site labour per pod for prefab versus 75.5 h for stick-built.
  • Show the TCS manifold, busway and shelving as one assembly in the BOM.
  • In multi-pod rollouts, reflect the roughly 17% learning gain between early and later pods in the schedule.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Check cooling capacity alongside your design

Review zone heat loads, available capacity and the capacity balance after the largest unit is lost in SoSo CAD.

Request a demo
Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Who should read it

Colocation operators, project managers and white-space designers who need high-density liquid-cooled capacity commissioned quickly.

Related standards

  • ASHRAE TC9.9 Liquid Cooling Guidelines
  • OCP Open Rack

Publication details

Authors
Wendy Torell; Melissa Rodriguez; Eric Williams
Publisher
Schneider Electric
Year
2026
Document number
WP 238
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Wendy Torell; Melissa Rodriguez; Eric Williams (2026). Prefabricated White Space Module Time Study: Lessons from a High-Density Liquid-Cooled Deployment. Schneider Electric. WP 238. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_WP238_EN

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.