Loadbank Testing and Commissioning for New Data Centres

Aggreko

Aggreko's white paper describes commissioning a new data centre in five levels, from factory acceptance to integrated systems testing, and recommends repeating loadbank testing at least annually.

On this page

Overview

The white paper is the first in Aggreko's data-centre content series. Its premise is that comprehensive testing of critical infrastructure in a new data centre cannot be compromised. Test scope runs from incoming MV distribution (20 kV switchgear) to rack-level power, covering transformers, UPS, standby generation, cooling towers, chillers and in-hall DX and CRAC units.

It defines five commissioning levels: factory acceptance, site acceptance, pre-functional testing, individual system testing and integrated systems testing (IST). At factory stage, resistive and reactive loadbanks prove generators and UPS at full load at leading and lagging power factors. At level 4, UPS modules, generators, PDUs and busbar systems undergo load burn-in and thermal imaging.

At level 5, power, cooling and IT infrastructure are tested at full load as one integrated whole, verifying response to varying loads, staged equipment failures and utility problems. Loadbanks can be free-standing units sized for halls with or without containment, or rack-mounted loads for precise testing where the server will sit. The paper names loadbank testing at initial commissioning and at least once a year afterwards as best practice.

The document is a white paper from an equipment-rental supplier: it outlines method and gives no detailed test criteria or acceptance values. Benefits listed are less unplanned downtime, lower lifecycle cost, safety, benchmarking data and standardisation; citing Uptime Institute, it states that over 70% of outages stem from human error rather than design faults.

Key points

  1. Commissioning has five levels: factory acceptance, site acceptance, pre-functional, individual system and integrated systems testing.
  2. Scope runs from 20 kV switchgear to rack-level AC or DC power distribution, and from generators to in-hall CRAC/DX units.
  3. Factory testing uses resistive and reactive loadbanks to prove generators and UPS at full load at leading and lagging power factors.
  4. Reactive load allows synchronisation of backup systems to be tested.
  5. Integrated systems testing covers varying loads, staged equipment failures and utility problems.
  6. Loadbank testing is recommended at initial commissioning and at least annually thereafter.
  7. Considering testing during design review reduces later changes to wiring, piping and sequencing.
  8. Citing Uptime Institute, over 70% of data-centre outages are caused by human error.

Using it in design

  • Require factory acceptance testing of UPS and generators at full load and at leading and lagging power factor in the specification.
  • Provide loadbank connection points (generator output, UPS output, PDU) in the design, with reserved access and cable routes.
  • Decide the per-hall heat-load strategy (free-standing or rack-mounted loads) and containment status for IST early.
  • Write staged-failure and utility-loss scenarios into the integrated test programme.
  • Add annual loadbank testing to the operations maintenance plan.

Who should read it

Commissioning engineers, project managers and owner representatives on new data-centre builds.

Document contents

  1. Testing times for data centres
  2. A best practice approach to testing and commissioning
  3. 5 levels of commissioning
  4. The outcomes of effective testing and commissioning
  5. Setting the standard

Publication details

Authors
Aggreko
Publisher
Aggreko
Year
Year not stated
Document number
Aggreko Data Centres Content Series #1
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public manufacturer document or page inspected. No document-specific redistribution permission established; retain metadata and original short summaries only.

Citation

Aggreko Loadbank Testing and Commissioning for New Data Centres. Aggreko. Aggreko Data Centres Content Series #1. https://bynder.aggreko.com/m/34acbfd3f0f96433/original/AGK5006-1_loadbank-and-commissioning-for-data-centres_whitepaper_global_Apr2020-pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.