Hosting Capacity Assessment of Data Centers with Voltage Ride-Through Capability in Power Systems
arXiv · Pengyu Ren, Wei Sun et al.
A preprint showing how the internal power-conditioning chain of a data centre, during a grid fault, limits the total capacity that can be connected and how that capacity is spread across buses.
On this page
Overview
The study treats large data centres as concentrated, power-electronic loads. If a facility disconnects abruptly or transfers to on-site backup during a voltage disturbance, a large demand leaves the system at once and can create a system-level stability problem. Interconnection feasibility therefore depends not only on thermal and voltage limits but on whether internal systems can keep IT service running while limiting customer-initiated load loss.
The proposed framework couples transmission-level fault simulation with an internal data-centre model. Python-based dynamic simulations produce point-of-interconnection (POI) voltage trajectories under selected network faults; these drive an internal model covering IT and cooling load dynamics, the DC link, UPS response and converter apparent-power limits. The result is embedded in a linear hosting optimization with 8760-hour constraints.
The numerical study uses the IEEE 118-bus system with four candidate data-centre buses (21, 75, 106, 108) and three wind plants. Without internal ride-through constraints the four buses can host 391.82 MW. With a current-limited grid-following (GFL) response and a converter rating ratio of 1.0, this falls to 107.32 MW. Steady-state planning alone can therefore overestimate feasible capacity considerably.
In scope, the model relies on reduced-order response models and is a preprint. The authors note that the linear affine screen is not a formal global lower bound outside the sampled domain. Even so, the results show with concrete numbers that UPS or battery converter headroom is a design variable directly tied to connectable capacity.
Key points
- Without internal ride-through constraints the IEEE 118-bus case hosts 391.82 MW across four buses (bus 21: 31.44 MW; 75: 153.87 MW; 106: 102.41 MW; 108: 104.09 MW).
- With the current-limited GFL response at converter rating ratio β = 1.0, feasible capacity falls to 107.32 MW.
- For GFL, β = 1.15 gives 227.44 MW and β = 1.25 gives 344.90 MW; the unconstrained value is reached at β = 1.325.
- The grid-forming (GFM) response reaches the same limit at a lower β = 1.175; it gives 109.54 MW at β = 1.0 and 385.28 MW at β = 1.15.
- Bus 21 is initially excluded by the constraints and unlocks gradually as β rises; per-bus allocation is non-monotonic because the optimizer reallocates capacity among four locations under shared network constraints.
- The acceptance criterion is not that internal voltage follows the external envelope; it is that protected IT voltage stays above the serviceability threshold for a specified window, together with POI active-power loss and converter loading.
- On the hold-out set, the tightened surrogate produces no false-pass cases after residual tightening.
- The simulation workflow is ANDES-based, the optimization is solved with HiGHS, and reported points are re-checked by AC power flow and a full nonlinear dynamic check.
Using it in design
- In a grid-connection application, justify capacity by ride-through behaviour as well as steady-state loading and voltage limits.
- Check how oversizing the UPS or battery converter relative to load raises connectable capacity, using the ratio β as in this study.
- Write the converter control mode (grid-following or grid-forming) and its current limit into the specification; note that under the same fault GFM gave more ride-through margin.
- Define the DC-link hold-up energy and the minimum acceptable IT voltage as design inputs.
- When choosing among candidate locations, assess them jointly under shared network constraints rather than one by one.
Who should read it
Electrical designers planning data-centre grid connections, engineers specifying UPS and energy storage, and transmission planning teams.
Document contents
- Introduction
- Methodology
- Case Study (internal dynamic response, system configuration, hosting capacity with and without internal VRT constraints)
- Conclusion
Publication details
- Authors
- Pengyu Ren; Wei Sun; Fei Teng
- Publisher
- arXiv
- Year
- 2026
- Document number
- arXiv:2609.03030v1
- Document language
- English
- Source type
- Scientific
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
arXiv non-exclusive distribution license is linked on the record; no general commercial redistribution permission established.
Citation
Pengyu Ren; Wei Sun; Fei Teng (2026). Hosting Capacity Assessment of Data Centers with Voltage Ride-Through Capability in Power Systems. arXiv. arXiv:2609.03030v1. https://doi.org/10.48550/arXiv.2609.03030