Research paperFree to read2026

Data Center Load Reductions: Attribution, Measurement Limits, and Estimation

arXiv · Abdallah Alalem Albustami, Ahmad F. Taha et al.

A preprint (arXiv, 28 October 2026) investigating when interconnection measurements can distinguish a workload reduction from transfer to backup supply. It sets out what recording and workload data a data-centre point of interconnection needs, in terms of disturbance recorder and root-cause-analysis requirements.

On this page

Overview

The paper relays that hundreds of gigawatts of data-centre load are seeking interconnection in the United States (about 410 GW of large loads in Texas alone as of March 2026, roughly 87% of them data centres) and that incidents of data centres cutting their loads by hundreds to thousands of megawatts have been documented.

In July 2024 a transmission fault in the Eastern Interconnection was followed within seconds by a reduction of about 1,500 MW of data-centre load. NERC has issued a Level 3 essential action alert on the modelling, study, commissioning, protection and instrumentation of computational loads, and in July 2026 FERC directed NERC to file reliability standards for the integration of computational loads by 31 December 2026. NERC also asks transmission owners to install disturbance recorders at these facilities.

The problem is that a sudden load drop can have two causes: the facility's own protection can switch equipment to backup supply (UPS batteries or onsite generators), or the workload itself can drop (for example a training job pauses or servers throttle). Recorders usually observe only electrical quantities at the point of interconnection (POI), and facility event logs can show that a UPS transferred to backup but not how much grid current was lost when the workload also changed. The paper has three objectives: determine when POI voltage and current can distinguish the mechanisms, identify the additional information needed when measurements are insufficient, and develop an estimator that reconstructs the current expected with all equipment connected and estimates how much of it remains at the POI.

The main results are: in a quasi-static constant power model, protection disconnection and workload reduction produce identical POI voltage and current. In the transient, separation depends on the reduction relative to measurement noise, the clearing time, the dynamics through which workload reaches the POI and the recorder bandwidth. A response model fitted directly to measured POI voltage can learn the grid relation and mask a disconnection; reconstructing the source voltage (which requires grid impedance) removes that relation and gave smaller errors in the tests.

The estimator uses workload data, withholds results when the prediction is not valid and flags a current that is not a scaled copy of the prediction. After voltage recovery it classified every admitted event of two data-centre architectures correctly, including partial disconnections, and estimated the load lost to disconnection within 7% of the pre-event power. For a crypto-mining facility it classified one of seven loss-free events as a loss and its load estimates were off by 10 to 13%. The results rest on EMT models with a controlled Thevenin source and a known impedance; there is no field data. The requirements are: workload data must represent computational demand independently of the connection state, the recorder must retain the fast transient with enough bandwidth, and zone-level workload data remove allocation ambiguity.

Key points

  1. In a quasi-static constant power model, protection disconnection and workload reduction produce identical point-of-interconnection voltage and current.
  2. In the transient, separation depends on the reduction relative to measurement noise, clearing time, how workload reaches the POI and recorder bandwidth.
  3. The recorder must retain the fast transient with bandwidth above the workload response bandwidth; phasor-rate data are not enough during the disturbance.
  4. Power measured at facility input drops when equipment disconnects and does not represent workload; power at the UPS output keeps supplying the computing equipment during transfer to battery and is a suitable workload signal.
  5. A response model fitted directly to POI voltage can learn the grid relation and mask a disconnection; reconstructing the source voltage with grid impedance gives smaller errors.
  6. The estimator classified every admitted event of two data-centre architectures correctly (including partial disconnections) and estimated the load lost to disconnection within 7% of pre-event power.
  7. For the crypto-mining facility it classified one of seven loss-free events as a loss; load estimates were off by 10 to 13%.
  8. A validated grid impedance is needed, and calibration records must cover the voltage and workload range of the event; ride-through records do not reach the sag depths at which a facility trips.
  9. The results rest on EMT models and a controlled Thevenin source; there is no field data.

Using it in design

  • Install a disturbance recorder at the data-centre point of interconnection in line with the NERC Level 3 alert and require its bandwidth to retain the fast transient; phasor-rate data alone is not enough for root-cause analysis.
  • Define the workload signal monitoring point from UPS output power rather than facility input power, and time-synchronise it with the POI record; where possible add separate zone-level (UPS or feeder) workload measurement.
  • Document the protection zones of UPS, feeders and load, and the transfer-to-backup thresholds (voltage and time), in a form that can be shared with the grid operator for root-cause analysis.
  • In the grid connection, make provision for grid impedance (short-circuit power) and calibration records that cover the voltage and workload range; plan for the fact that ride-through records will not cover the sag depths at which the facility trips.
  • Integrate event logs and workload data into the grid reporting process so that workload changes (a paused training job, throttling) can be separated from transfer to backup in load-reduction events.

Who should read it

Data-centre grid-connection and protection engineers, transmission planners and disturbance analysts, and UPS and monitoring-system designers.

Document contents

  1. Introduction (data-centre load growth, NERC and FERC actions, related work, contributions)
  2. Facility Model and the Attribution Problem (facility and grid model, all-connected response and participation)
  3. What terminal measurements identify
  4. Estimator using workload data and its extensions
  5. Data requirements for attribution
  6. Validation on PSCAD models (three facilities, complete and partial disconnections)
  7. Conclusion

Publication details

Authors
Abdallah Alalem Albustami; Ahmad F. Taha; Mohammad Alwahdanee; Zuhaib Shakeel Muhammad
Publisher
arXiv
Year
2026
Document number
arXiv:2610.38216v1
Document language
English
Source type
Scientific
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

arXiv page license link is the non-exclusive distribution grant to arXiv, not a general reuse license. Full PDF read; no redistribution permission inferred.

Citation

Abdallah Alalem Albustami; Ahmad F. Taha; Mohammad Alwahdanee; Zuhaib Shakeel Muhammad (2026). Data Center Load Reductions: Attribution, Measurement Limits, and Estimation. arXiv. arXiv:2610.38216v1. https://doi.org/10.48550/arXiv.2610.38216

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.