Version 2.0 (31 October 2022) of the Bangladesh National Digital Architecture hardware specifications lists device requirements for servers, networks and UPS, plus an 11-item DCIM function list (EMS.DCIM.001-011).

On this page

Overview

The document is version 2.0 of the Hardware Specification Standards published on the Bangladesh National Digital Architecture (BNDA) portal, dated 31 October 2022. It contains requirement tables with standard IDs for device classes used in public procurement: blade, database and general-purpose rack servers, storage, SAN, core, aggregation and access switches, firewalls, UPS, the enterprise management system (EMS) and end-user devices.

Each requirement carries a standard ID (for example BS.REQ.001, EMS.DCIM.003) and is classified as mandatory or recommended. A buying agency can therefore build a tender by referring to item numbers. The DCIM section consists of eleven recommended items.

The DCIM items ask for the following: site management tools for power and energy (kW, kWh), electrical parameters (A, V, kVA, PF, Hz), temperature, humidity, air flow and leak monitoring; customisable thresholds and notification; a power view from service entrance to cabinet with a real single-line diagram; PUE measured at three levels (L1 UPS output, L2 PDU output, L3 IT device); inventory with physical location and power, cooling, weight and space capacity; change planning; interfaces to infrastructure components; alarm capture; an OEM model library; search; and sustainability reporting.

The document is a procurement specification template, not a design guide; it defines no environmental conditions or redundancy goals. Its value lies in listing DCIM functions as concrete, testable statements and providing a common reference for device classes.

Key points

  1. Version 2.0 is dated 31 October 2022; requirements are classed as mandatory or recommended.
  2. The DCIM section has 11 items, EMS.DCIM.001 to EMS.DCIM.011, all recommended.
  3. Site monitoring: power and energy (kW, kWh), electrical parameters (A, V, kVA, PF, Hz), temperature, humidity, air flow, leak detection.
  4. The power view runs from service entrance to cabinet; a real single-line diagram and device-level metering are required; server power is measured by IPMI/SNMP polling, not estimated.
  5. PUE is measured at three levels: L1 UPS output, L2 PDU output, L3 IT device level (The Green Grid recommendation); DCiE is also tracked.
  6. Inventory auto-discovers SNMP-enabled devices and shows location and used/available power, cooling, weight and space capacity.
  7. Change planning compares proposed changes with capacity planning so power, cooling and space shortfalls cannot occur.
  8. The OEM model library is updated quarterly; sustainability reporting covers carbon footprint and device ageing analysis.
  9. The small UPS items ask for example for 1 kVA capacity, 230 V +/-1% pure sine output, 50 Hz and a crest factor of at least 3:1.

Using it in design

  • Compare your DCIM specification with items EMS.DCIM.001-011 to find gaps.
  • Provide metering in the design at L1 (UPS output), L2 (PDU output) and L3 (IT device) for PUE.
  • Write a DCIM interface and alarm list for service entrance, UPS, generator, ATS, PDU and CRAC components on the power path.
  • Tie change planning to the capacity system so power, cooling and space are checked before new equipment is added.
  • Use the standard-ID item structure as a model for measurable, traceable requirements in your own specification template.

Who should read it

IT managers writing public procurement specifications, design engineers writing DCIM specifications and suppliers in the Bangladesh market.

Document contents

  1. Servers: blade, database rack, general-purpose rack, blade chassis
  2. Storage: unified, SAN, tape library
  3. Network: SAN, core, aggregation, access switches
  4. Enterprise Management System: general, event, network, server, reporting, service level, helpdesk
  5. Data Center Infrastructure Management (DCIM)
  6. Application, database and traffic performance management, asset management
  7. Security: firewall, WAF, NGFW, IPS
  8. End-user devices, UPS and printers

Publication details

Authors
Bangladesh Computer Council, Bangladesh National Digital Architecture
Publisher
Bangladesh Computer Council, Bangladesh National Digital Architecture
Year
2022
Document number
BNDA Hardware Specification Standards v2.0
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public official source inspected. No document-specific commercial redistribution permission established. Metadata and original brief summaries only; local evidence is not a redistribution package.

Citation

Bangladesh Computer Council, Bangladesh National Digital Architecture (2022). BNDA Hardware Specification Standards, Version 2.0: DCIM requirements. Bangladesh Computer Council, Bangladesh National Digital Architecture. BNDA Hardware Specification Standards v2.0. https://bnda.gov.bd/standards/standard-single.jsp?standard=OA%3D%3D

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Redundancy scenarios in SoSo CAD

Compare normal operation with equipment failures and see served loads and capacity shortfalls in the same view.

Normal operation and failure scenario comparison in SoSo CAD

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.