The handbook stresses that busbar success depends on correct handling, proper installation and commissioning according to the design. Its handling section covers forklift unloading, strap rather than steel rope, holding long modules at both ends with two ropes, timber spacers every 1.5 m when stacked, and no more than 5 modules stacked horizontally. Incoming pallets are checked against the packing list for count, size and current rating.

Joint materials are stored between 5 and 25 C away from direct sunlight. Type C hardener is used at ambient 5-15 C and type B at 15-35 C; out-of-date resin is not used, and the mix is stirred at least 5 minutes until homogeneous. Joint moulds can be removed after 3 hours at 25 C, 4 hours at 15 C and 6 hours at 5 C, with 8-24 hours for full cure.

Installation starts from one point, preferably the panel, and ends with the last module. No joint is cast before a megger (insulation resistance) test shows infinite resistance. In the horizontal procedure the central joint bolt is tightened with a torque wrench to 83 Nm (M12). After horizontal casting, insulation-resistance testing is not allowed for at least 24 hours, which affects the commissioning sequence.

Site tests cover the joint resistance test (maximum 15 microohm) and the line insulation resistance test; report forms for connection resistance and insulation resistance are appended. Tests use calibrated instruments only, terminals and transformers are disconnected or protected, and the system is earthed and discharged after each test. Forms go to the manufacturer, and the quality approval form is needed for warranty cover.

The design section gives rating steps and busbar codes (aluminium CRA 630-5000 A, copper CRC 800-6300 A). The catalogue ducts are IP68, and use outside the standard phase arrangement is not the manufacturer's responsibility.

Key points

  1. Joint materials are stored at 5-25 C; type C hardener at ambient 5-15 C, type B at 15-35 C.
  2. Moulds can be removed after 3 h at 25 C, 4 h at 15 C, 6 h at 5 C; cure and full hardening take 8-24 hours.
  3. The horizontal joint central bolt is tightened to 83 Nm (M12; 60 lbft) with a torque wrench.
  4. Every joint is checked with a megger test before casting; no casting without infinite resistance.
  5. After horizontal casting, no insulation-resistance test for at least 24 hours.
  6. The maximum permitted value in the joint resistance test is 15 microohm.
  7. Spacers every 1.5 m when stacking and no more than 5 modules stacked horizontally.
  8. The mix is stirred at least 5 minutes and poured to the top of the mould without waiting.
  9. Busbar ducts are IP68; CRA aluminium 630-5000 A, CRC copper 800-6300 A.

Using it in design

  • Add resin cure and the 24-hour wait to the commissioning schedule; ambient temperature determines the times.
  • Include joint resistance (maximum 15 microohm), connection resistance and line insulation resistance tests and their report forms in the site test plan.
  • Write the disconnection and reconnection of terminals, MCCBs and transformers around testing into the work sequence.
  • In high-rise vertical shafts, measure at every floor and check on site that joints do not coincide with floor crossings.
  • Add storage temperature (5-25 C) and shelf-life checks to site logistics.

Who should read it

Site electrical engineers, test teams and project managers installing and commissioning cast resin busbar.

Document contents

  1. Introduction
  2. Unloading, handling and storage / joint area information
  3. Handling and hanging
  4. Design and engineering
  5. Vertical and horizontal cast resin applications
  6. Hanging elements
  7. Equipment used
  8. Horizontal installation and resin application
  9. Vertical installation and resin application
  10. Preparing the joint resin
  11. Electrical tests on site
  12. Connection resistance and line insulation resistance test reports
  13. General product features

Publication details

Authors
EAE Elektrik
Publisher
EAE Elektrik
Year
2023
Document number
CR El Kitabı TR Rev 04 / 23.11.2023
Document language
Turkish
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Üreticinin herkese açık kaynağı okundu. Açık erişim yeniden dağıtım izni değildir; tam metin kütüphaneye alınmaz. Revizyon son sayfada doğrulandı. Farklı sayfalarda kürlenme/kalıp sökme süreleri farklı olduğundan tek bir genel kürlenme süresi türetilmedi.

Citation

EAE Elektrik (2023). E-Line CR El Kitabı. EAE Elektrik. CR El Kitabı TR Rev 04 / 23.11.2023. https://www.eae.com.tr/storage/el-kitaplari/busbar-sistemleri/cr-el-kitabi.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.