Technical guideFree to read2026

EAE E-Line KX Busbar Systems Manual (Rev 12)

Original title E-Line KX El Kitabı

EAE Elektrik

The Turkish-language manual from EAE covering transport, storage, installation, joint assembly, energising and maintenance of E-Line KX busbar systems (Rev 12, 19.10.2026).

On this page

Overview

The manual stresses that a busbar system's success depends on correct handling, proper installation and commissioning to the design. Installation, operation and maintenance must be done only by qualified personnel and on de-energised equipment. Liquid contact is treated as a serious risk: an unfinished busbar installation is unprotected against water; a kerb of at least 100 mm must surround all floor openings through which vertical runs pass, and water paths such as rain, fire sprinklers and drips must be closed. For transport and storage it recommends forklifts, slings, stacking of at most 3 pallets and dry, clean, constant-temperature indoor storage.

Pre-installation acceptance steps: every product gets a 100% insulation test after production, but because of possible damage in transport and storage, an insulation-resistance test of at least 1000 V AC is recommended before installation. It is done between phases, phase and neutral, and neutral and earth, and values must not be below 1 MΩ. After installation the values must not be below 1 MΩ per 30 metres, and energising before the test passes is not recommended. 4-conductor system modules must not be fitted to a 5-conductor system, nor 5-conductor modules to a 4-conductor system. No oil or chemicals may be applied to joints or tap-off boxes.

Joint assembly is detailed for bolt-on and plug-in types: M12 joint nuts are tightened first to 20 Nm and then, in the same sequence, to 83 Nm (60 lbft); on a single-path busbar 83 Nm is applied directly, and nut-protection covers are tightened to 20 Nm. Vertical distribution needs a project-specific design for the building. Water resistance times are 3 minutes of pressurised water for IP55 and IP65 and 30 minutes of immersion for IP67. Joint contact resistance is measured with a four-wire calibrated instrument applying at least 10 A DC, repeated at least twice; the difference among L1, L2, L3 and N in the same joint must not exceed 10 µΩ, PE contact resistance must not exceed 100 mΩ, and maximum joint contact resistance is 25 µΩ.

Key points

  1. All products receive a 100% insulation test after production; an insulation-resistance test of at least 1000 V AC is recommended before installation, with values not below 1 MΩ.
  2. The post-installation insulation test must not fall below 1 MΩ per 30 metres; energising before it passes is not recommended.
  3. A kerb of at least 100 mm is required around all floor openings through which vertical busbar runs pass.
  4. Joint nuts are tightened in two stages: 20 Nm first, then 83 Nm (60 lbft); nut-protection covers 20 Nm.
  5. Joint contact resistance is measured with a four-wire instrument applying at least 10 A DC and repeated at least twice.
  6. The L1, L2, L3 and N resistance difference in the same joint must not exceed 10 µΩ; PE contact resistance must not exceed 100 mΩ; maximum joint contact resistance is 25 µΩ.
  7. Water resistance: IP55 and IP65 3 minutes of pressurised water, IP67 30 minutes of immersion.
  8. 4-conductor and 5-conductor modules are not mixed; pallets are stacked at most 3 high.
  9. Caps are fitted to open joint points of unfinished installations; no oil or chemicals on joints or tap-off boxes.

Using it in design

  • Coordinate the busbar route with mechanical, heating and fire-suppression services and confirm that no water path crosses the busbar run.
  • Add the 100 mm kerb detail around floor openings of vertical runs to the architectural design.
  • Add the pre-installation insulation-resistance test (at least 1000 V AC) and joint torque records to the work programme; write the 1 MΩ and 1 MΩ per 30 metres limits as acceptance criteria.
  • In the commissioning checklist, define joint contact resistance measurement (maximum 25 µΩ, phase difference 10 µΩ, PE 100 mΩ) and phase-sequence check.
  • Choose the IP class by the water risk of the installation environment (IP55, IP65 or IP67) and protect open joint points after installation.
  • Fix the choice of 4-conductor or 5-conductor system at design stage; changing it on site is not possible.

Who should read it

Electrical engineers installing busbar power distribution in data centres and facilities, installation and commissioning teams, and site inspectors.

Document contents

  1. Introduction
  2. General
  3. Transport and storage
  4. Points to note before starting installation
  5. Joint structure and general view
  6. Spacer and offset dimensioning
  7. Bolt-on and plug-in busbar joint assembly
  8. Points to note after installation
  9. Points to note in a vertical distribution project
  10. Plug-in and bolt-on busbar tap-off boxes
  11. Feeder box installation (B10, B11)
  12. Energising and before energising
  13. Energising the equipment
  14. Maintenance

Publication details

Authors
EAE Elektrik
Publisher
EAE Elektrik
Year
2026
Document number
KX El Kitabı / Tr. / Rev 12 / 19.10.2026
Document language
Turkish
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Üreticinin herkese açık kaynağı okundu. Açık erişim yeniden dağıtım izni değildir; tam metin kütüphaneye alınmaz. Revizyon tarihi son sayfada doğrulandı; bu tork diğer busbar ailelerine genellenemez.

Citation

EAE Elektrik (2026). E-Line KX El Kitabı. EAE Elektrik. KX El Kitabı / Tr. / Rev 12 / 19.10.2026. https://www.eae.com.tr/storage/el-kitaplari/busbar-sistemleri/kx-el-kitabi.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.