What You Need to Know About Arc Flash
Eaton · Adam Reeves, David G. Loucks
An introductory paper on arc-flash hazards and mitigation in commercial and industrial electrical systems, data centres included.
On this page
Overview
The paper frames the hazard through incident energy, the NFPA 70E / IEEE 1584 framework and labelling. NFPA 70E 130.5(G) requires the incident energy analysis to be updated at least every 5 years. The arc-flash boundary is where incident energy equals 1.2 cal/cm2, and labels are required on equipment over 50 V that may be accessed energised. Single-phase-to-ground faults are 7.8 (junctions) to 73 (cable) times more likely than three-phase faults (IEEE 493-2007), but IEEE 1584-2002 gives no method for them.
Mitigation is grouped into reducing available fault current (open tie during maintenance, smaller or higher-impedance transformers, high-resistance grounding, current-limiting devices), shortening clearing time (zone-selective interlocking, bus differential, maintenance-mode settings, arc-quenching switchgear), remote operation, predictive maintenance and redirecting blast energy. Opening the tie between dual feeds during maintenance roughly halves available fault current.
Eaton recommends separate line-side and load-side calculations for the main breaker, because line-side-only values can exceed 40 cal/cm2 and wrongly bar energised work. Main breakers can take up to 4 cycles (67 ms) to clear, while arc-quenching switchgear contains an arc in under 4 ms.
NEC prohibits high-resistance grounding on systems serving line-to-neutral loads such as most servers, which limits HRG to motor-only portions.
Key points
- NFPA 70E 130.5(G): the incident energy analysis must be updated at least every 5 years.
- Single-phase-to-ground faults are 7.8 (junctions) to 73 (cable) times more likely than three-phase faults (IEEE 493-2007); IEEE 1584-2002 gives no method.
- The arc-flash boundary is where incident energy equals 1.2 cal/cm2; labels are required on equipment over 50 V accessed energised.
- Eaton recommends separate line-side and load-side calculations for the main breaker; line-side-only values can exceed 40 cal/cm2 and wrongly bar energised work.
- Opening the tie between dual feeds during maintenance roughly halves available fault current.
- NEC prohibits HRG on systems serving line-to-neutral loads such as most servers; HRG is limited to motor-only portions.
- Main breakers can take up to 4 cycles (67 ms) to clear; arc-quenching switchgear contains an arc in under 4 ms.
Using it in design
- Add arc-flash attributes per switchboard (available fault current, clearing time, maintenance-mode/ZSI availability, working distance) and compute incident energy per IEEE 1584 for line and load side.
- Warn when incident energy exceeds 40 cal/cm2 or when breakers above the threshold ratings lack energy-reducing maintenance switching.
- Prevent HRG selection on boards feeding line-to-neutral IT loads.
- Flag closed-tie (double-ended) maintenance scenarios and generate label data.
Who should read it
Electrical engineers designing boards and maintenance procedures, and operational safety managers.
Related standards
- NFPA 70E
- IEEE 1584
- IEEE 493
- NEC 240.87
- OSHA 29 CFR 1910.269
Publication details
- Authors
- Adam Reeves; David G. Loucks
- Publisher
- Eaton
- Year
- 2018
- Document number
- WP083033EN
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Citation
Adam Reeves; David G. Loucks (2018). What You Need to Know About Arc Flash. Eaton. WP083033EN. https://web.archive.org/web/20220120090611/https://www.eaton.com/content/dam/eaton/company/news-insights/arc-flash-safety/what-you-need-to-know-about-arc-flash-wp083033en.pdf