User manual for the ENTES RGP three-phase reactive power control relay: 9 or 12 steps with per-phase compensation, automatic wiring and step detection at commissioning, and alarm and warning tables.

On this page

Overview

The manual describes ENTES's new-generation RGP series reactive power control relay. Through 9 or 12 steps (with 9+SVC and 12+SVC options) the relay controls the three phases separately and brings each phase's cos φ towards the user-set target, preventing the facility from entering the reactive-penalty zone. The unit has three-phase voltage inputs, current inputs, an RS-485 communication port, an alarm output and a fan output.

The commissioning section proceeds step by step. On power-up the language selection, tutorial mode and automatic setup screens appear, asking for region, time, date, CT primary and secondary, nominal frequency, target cos φ and reference step. The device first runs automatic wiring detection, correcting phase-sequence and CT polarity errors by switching the three-phase capacitor on the reference step in and out. It then runs step detection to learn each step's power and connection type. Non-linear and suddenly changing loads such as thyristor or triac controlled loads, frequency converters and UPS can defeat the automatic correction; those loads should be switched off temporarily and the procedure repeated.

The alarm and warning structure is broad. It defines 7-day inductive and capacitive ratio alarms and warnings, step capacity loss, contactor life and switching-count alarms, insufficient capacitor or reactor power, and voltage, THDV, THDI and cabinet-temperature alarms. For voltage, THDV, THDI and temperature, enabling the step protection option makes the device switch off all steps to protect the capacitors. A smiley display mode and LED colours (red alarm, yellow warning, blue generator on) show the state.

The manual also covers the measurement menus (voltage, current, frequency, harmonics, energy and daily/monthly compensation data), the Modbus setting, the compliance standards and measurement ranges. It gives a 144 × 144 mm housing, -20/+70 °C operating temperature and IP 54 on the front panel.

Key points

  1. 9 and 12 steps, with 9+SVC and 12+SVC options; each phase is controlled separately.
  2. A three-phase capacitor must be connected to the reference step; the device does not work without a three-phase-to-neutral connection.
  3. Automatic wiring detection corrects phase sequence and CT polarity errors; phase currents must be non-zero for it to work.
  4. Thyristor/triac controlled, frequency-converter and UPS-type loads can defeat automatic correction; switch them off temporarily and repeat.
  5. Alarm postpone-time options are 1, 8, 24 and 72 hours.
  6. On voltage, THDV, THDI and temperature alarms, with step protection on, all steps are switched off.
  7. Measurement ranges: phase-neutral 10-400 Vac, phase-phase 10-690 Vac, frequency 47-63 Hz, current input 0.005-6 A, harmonics 2nd-31st.
  8. Housing 144 × 144 mm, panel cut-out 138 × 138 mm, operating temperature -20/+70 °C, front IP 54.

Using it in design

  • In the compensation panel, connect the relay CT with the correct phase-neutral pairing and place a three-phase capacitor on the reference step.
  • Commission under low-harmonic conditions, or switch off drive and UPS loads temporarily, so their harmonic effect does not disturb the automatic setup.
  • Set voltage, THDV and THDI alarm limits and the step protection option to match the capacitor and reactor class.
  • Link the contactor life and switching count warnings to the maintenance plan.
  • Carry RS-485 Modbus communication into the building management and monitoring system.

Who should read it

Electrical engineers and technicians designing, commissioning and operating reactive power compensation panels.

Document contents

  1. Introduction: general features, product family, operating conditions
  2. LED indicator, display and front panel
  3. Key functions
  4. Connection diagram
  5. Commissioning the RGP device
  6. Using the device and menus: settings, alarms, time, system, reset
  7. COS φ and compensation menus
  8. Power, energy, measurement and harmonic menus
  9. Messages
  10. Maintenance, warranty and compliance
  11. Appendices: mechanical and environmental conditions, measurement, capacitor calculation table

Publication details

Authors
ENTES
Publisher
ENTES
Year
Year not stated
Document number
RGP Serisi
Document language
Turkish
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public source opened on the access date. No open redistribution licence established; metadata and original short summaries only. PDF text-layer character mapping is corrupt. Pages 2–4, 17, 26, 32 and 33 were rasterized and OCR processed; pages 17 and 32 were visually verified for the two facts. PDF creation metadata is not treated as publication year. Contents-page numbering differs from the actual section page positions; locators use the visible printed pages.

Citation

ENTES RGP Serisi 3 Fazlı Reaktif Güç Kontrol Rölesi: Kullanım Kılavuzu. ENTES. RGP Serisi. https://entes.com.tr/uploads/files/1733815959-tr_rgp_serisi.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.