Licensing in Low-Voltage Type-Tested Switchgear Assemblies
Original title Alçak Gerilim Tip Testli Pano Sistemlerinde Lisanslama
ETMD
An article by the Electrical Engineers Association (ETMD) dated 19 December 2023 that explains the responsibilities of the original manufacturer and the final manufacturer (assembler) under IEC 61439-1/2 and how they should be verified, with PanelMaster project-based licensing as an example.
On this page
Overview
The article says the move from IEC 60439-1 to 61439-1/2 created a false perception, and that although the standard clearly requires design verification rules, large gaps remain in practice. A type-tested assembly is defined as one whose type tests were done and certified to 61439-1/2 and which was assembled in strict compliance with the design verification rules. Two key definitions of the standard are given: the original manufacturer is the organisation that designs and verifies the assembly; the final manufacturer (panel builder) is the organisation that assembles the verified design in strict compliance with the original manufacturer's rules and takes responsibility.
For checking the original manufacturer, the article lists what must be proved with certificates: IEC 61439-1/2 compliance, IEC 60068 seismic qualification and IEC 61641 internal arc tests if required, accreditation of the test laboratory, and all type tests in clauses 10.2 to 10.13 of 61439-1 (strength of materials, degree of protection, clearances and creepage, protection against electric shock, incorporation of switching devices, internal circuits, terminals for external conductors, dielectric properties, temperature rise, short-circuit withstand, EMC and mechanical operation).
It also points to practical constraints: every breaker model to be used in the project must have been included in the type test within the assembly; tests must have been made with switchgear at rated current (for example if tests were at 4000 A, a 5000 or 6300 A breaker cannot be used); and the brand of switchgear tested must equal the brand used in the project. For the final manufacturer, it requires a signed and stamped authorisation from the original manufacturer, possession of the design verification and application catalogues, a CE declaration of conformity, and licensing after the original manufacturer checks compliance.
The last section describes PanelMaster-specific project-based licensing: the final manufacturer must be a PanelMaster partner or obtain project-based authorisation from EAE Elektroteknik; after application an on-site inspection team checks documents against panel labels, takes measurements, photographs each panel compartment and completes a form; if no non-conformity is found a licence badge is issued, and panels without a badge are not considered licensed. This process is one manufacturer's practice and must not be used as a general legal or standards provision for all switchgear systems.
Key points
- Type-tested assembly: type tested and certified to IEC 61439-1/2 and assembled in strict compliance with design verification rules.
- The original manufacturer designs and verifies; the final manufacturer (panel builder) assembles in compliance with the original manufacturer's rules and takes responsibility.
- The original manufacturer must prove by certificate: IEC 61439-1/2 compliance, IEC 60068 seismic and IEC 61641 internal arc tests if required, laboratory accreditation, and the 61439-1 clause 10.2-10.13 type tests.
- Every breaker model and current class used in the project must be included in the type test; example: if tests were at 4000 A, a 5000 or 6300 A breaker cannot be used in that assembly.
- The brand of switchgear used in the test must equal the brand used in the project.
- The original manufacturer must give the final manufacturer technical catalogues describing assembly conditions and design rules.
- The final manufacturer proves responsibility with a signed authorisation, catalogues, a CE declaration and checking and licensing by the original manufacturer.
- In the PanelMaster example, a licence is issued after on-site inspection, document-label matching, measurements and a photographed check form, with a badge; a panel without a badge is not counted as licensed.
Using it in design
- When specifying type-tested switchgear, define the original and final manufacturers separately and ask both for responsibility documents (certificates, authorisation, catalogue, CE declaration).
- Match the breaker model, current class and brand in the panel's type test certificate line by line to project equipment, and verify that no breaker above the tested current is used.
- If seismic or internal arc is required, write the IEC 60068 and IEC 61641 tests and laboratory accreditation as separate specification clauses.
- Treat manufacturer-specific processes such as licensing and document checks (for example the PanelMaster badge) as that manufacturer's quality evidence, not as a design requirement.
- At handover, add the match between documents and labels on the panel to commissioning acceptance criteria.
Who should read it
Electrical engineers who specify, buy and accept low-voltage switchgear assemblies.
Document contents
- Definitions: type-tested assembly, original manufacturer, final manufacturer
- Checking the original manufacturer's responsibilities
- Responsibilities of the final manufacturer (panel builder)
- PanelMaster-specific project-based licensing
Related standards
- IEC 61439-1
- IEC 61439-2
Publication details
- Authors
- ETMD
- Publisher
- ETMD
- Year
- 2023
- Document language
- Turkish
- Source type
- Industry body
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
No document-specific redistribution permission was established. Bibliographic reference only.
Citation
ETMD (2023). Alçak Gerilim Tip Testli Pano Sistemlerinde Lisanslama. ETMD. https://www.etmd.org.tr/alcak-gerilim-tip-testli-pano-sistemlerinde-lisanslama/
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.