Techno-Economic Analysis of the Applicability of Trigeneration Systems in Data Centers
Original title Veri Merkezlerinde Trijenerasyon Sistemlerinin Uygulanabilirliğinin Teknoekonomik Analizi
Gazi Üniversitesi · Rıdvan Hatiboğlu
A September 2021 Gazi University master's thesis: replacing an existing data centre's DX cooling with 1.2, 1.56 or 2 MWe trigeneration gives a 2-2.5 year payback and 12,400-16,330 t/year lower CO2.
On this page
Overview
The thesis is a 115-page work by Rıdvan Hatiboğlu at the Gazi University Graduate School of Natural and Applied Sciences, supervised by Assoc. Prof. M. Zeki Yılmazoğlu. It notes that data centres, driven by cryptocurrency, the pandemic and cloud use, now have higher energy intensity than many building types, and that white space cooling is a large share of operating cost. The first chapters cover data centre and telecom facility reference documents, air and liquid cooled systems, energy efficiency assessment and the basics of cogeneration and trigeneration.
The analysis chapter derives a load profile from the energy consumption data of an operating data centre and examines trigeneration in place of the existing DX coil cooling: waste heat from the prime mover (an internal combustion gas engine) produces chilled water through thermally activated (absorption) cooling. Trigeneration is said to need continuous full-load operation for best efficiency, which a data centre's steady load suits. Three engine capacities are selected from the load profile: 2,000, 1,560 and 1,200 kWe.
The economic analysis covers fuel consumption, monthly operating hours, electricity unit cost, maintenance and operation cost, internal consumption, net present value (NPV), internal rate of return (IRR) and payback. The abstract gives a payback of 2-2.5 years for the capacities and an average annual CO2 reduction of 12,400-16,330 tonnes. The conclusion compares the three capacities over 24 years of investment and operating cost: the 2,000 kWe system has the highest monthly profit rate, but initial investment and heavy maintenance over 24 years put it at a disadvantage; the 1.2 MW plant suits NPV and IRR.
The work evaluates, techno-economically, an alternative energy infrastructure for data centres where grid plus generator is the classic choice. Results depend on the studied data centre's load profile and on fuel and electricity prices; the thesis stresses that system selection must follow detailed analysis for the data centre capacity.
Key points
- Three trigeneration capacities are compared: 2,000 kWe, 1,560 kWe and 1,200 kWe gas engine systems.
- Payback for the different capacities is calculated as 2-2.5 years.
- Average annual CO2 reduction is calculated as 12,400-16,330 tonnes.
- The 2,000 kWe system gives the best monthly profit rate but is disadvantaged by initial investment and 24-year operating cost including heavy maintenance.
- The 1.2 MW trigeneration plant is found suitable on NPV and IRR.
- Trigeneration should run at continuous full load for best efficiency; a data centre's steady load fits this.
- Engine waste heat drives absorption cooling in place of the existing DX coil system.
- The thesis finds that system selection needs detailed analysis for the data centre capacity.
Using it in design
- For a data centre considering trigeneration, first derive the real load profile (monthly electrical and cooling load) and select engine capacity from it.
- Compare several engine capacities on 20-24 year NPV, IRR and payback; the largest system does not always win.
- Include heavy maintenance periods and the backup grid connection (Tier III/IV redundancy) in the investment calculation.
- For an absorption chiller driven by waste heat, check condenser tower capacity and chilled water temperature requirement.
- Run sensitivity analysis on fuel and electricity price scenarios; results here depend on the prices used.
Who should read it
Engineers planning data centre energy and cooling infrastructure, managers doing investment analysis and academics studying trigeneration.
Document contents
- Introduction
- Data centres and telecommunication facilities (air cooled systems, liquid cooled system, energy efficiency assessment)
- Cogeneration and trigeneration systems (efficiency, capacity determination, prime mover selection, thermally activated cooling, maintenance costs)
- Analyses (data centre load profile, trigeneration economic analysis, NPV, IRR, payback)
- Conclusion
- Evaluation and recommendations
Publication details
- Authors
- Rıdvan Hatiboğlu
- Publisher
- Gazi Üniversitesi
- Year
- 2021
- Document number
- Yüksek lisans tezi, Makina Mühendisliği, Eylül 2021
- Document language
- Turkish
- Source type
- Scientific
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official publisher or university publicly accessible text; no open redistribution licence established. Only the author’s case-study scope is summarised. ASHRAE-derived background, secondary Tier descriptions and inconsistent 20/24-year horizon statements are not adopted.
Citation
Rıdvan Hatiboğlu (2021). Veri Merkezlerinde Trijenerasyon Sistemlerinin Uygulanabilirliğinin Teknoekonomik Analizi. Gazi Üniversitesi. Yüksek lisans tezi, Makina Mühendisliği, Eylül 2021. https://avesis.gazi.edu.tr/advisingtheses/showdocument/ae88fd7f-34ae-45eb-a7b6-cb3230af1ca4
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.