Busbar Installation Guide (Busbar Montaj Kılavuzu)

Original title Busbar Montaj Kılavuzu

Gersan Elektrik

A one-page guide from Gersan Elektrik that sets out busbar trunking installation in ten steps: hanger points are marked 1.5 to 2 metres apart, busbar lengths are stacked at most 5 to 6 rows high, and SYK tap-off boxes are fitted with the handle in the off position.

On this page

Overview

The guide is a short site installation instruction for Gersan busbar trunking systems. It divides the work into two stages: preparing the route and installing the busbar. The introduction notes that the system is made up of standard and special lengths, joint parts and elbows, which allows it to be installed and commissioned quickly regardless of how far the building work has progressed. The document is in Turkish and applies to the manufacturer's own products and hanger components.

The first steps concern protection of the material. Busbar components stay in factory packaging until installation begins and are transported to site in that packaging. Stacking is limited to 5 to 6 rows, with cardboard or wooden spacers between rows. Route preparation consists of marking, drilling and fitting the hangers. Hanger points are marked 1.5 to 2 metres apart, taking care that hangers do not coincide with the tap-off points on the busbar. The manufacturer's own hanger components are used in the support system.

The second stage is lifting, hanging and tightening the busbar. The ceiling that carries the run must be able to bear the load; openings for wall penetrations are prepared in advance, and the position of the neutral conductor is observed during assembly. Because the busbar is fully enclosed, no lower limit is set for the hanging height. In the final step, lengths are joined to each other and to the feeder boxes through joint components. Expansion units are used to accommodate thermal and mechanical movement.

The last four steps describe fitting SYK tap-off boxes. The box is held at an angle with both hands, inserted into the tap-off window, pushed fully home and fixed with screws; the box handle must be in the off position throughout. Cables enter the box through glands and are terminated with lugs; the glands also retain the cable. Protective conductors are connected to the earthing bar of the box. After the cover is closed, the box is energised only when the handle is turned to the on position. The guide contains no tightening torques or current ratings.

Key points

  1. Installation has two stages: route preparation (marking, drilling, hanger fitting) and hanging and joining the busbar.
  2. Material stays in factory packaging until installation and is transported packaged.
  3. Busbar lengths are stacked at most 5...6 rows high, with cardboard or spacers between rows.
  4. Hanger points are marked 1.5...2 metres apart and kept clear of tap-off points.
  5. The manufacturer's own hanger components are used; the ceiling must be able to carry the load.
  6. Expansion units provide thermal and mechanical flexibility.
  7. An SYK tap-off box is inserted at an angle with its handle off and fixed with screws.
  8. Cables are connected to the tap-off box with glands and lugs; the protective conductor goes to the box earthing bar.
  9. The tap-off box enters service once the cover is closed and the handle is turned on.

Using it in design

  • Draw the hanger plan at 1.5...2 metre spacing and shift hanger positions against the rack layout so they do not clash with tap-off box points.
  • Include the weight of the busbar run and tap-off boxes in the ceiling or support-steel load calculation.
  • Enter wall penetration openings in the architectural and structural drawings before installation.
  • Leave access clearance at tap-off positions so the box can be inserted at an angle and the handle operated.
  • Define the 5...6 row stacking limit and a covered, dry storage area in the site logistics plan.
  • Add the protective-conductor connection to the earthing bar of every tap-off box to the commissioning checklist.

Who should read it

Site crews installing busbar trunking, site managers, and electrical engineers designing busbar routes and support details.

Document contents

  1. Giriş: hattın hazırlanması ve montaj
  2. Ambalaj, nakliye ve istifleme (1-3)
  3. Askı sistemi ve hattın hazırlanması (4)
  4. Busbarın asılması ve birleştirilmesi (5-6)
  5. SYK tipi çıkış kutularının montajı ve bağlantısı (7-10)

Publication details

Authors
Gersan Elektrik
Publisher
Gersan Elektrik
Year
Year not stated
Document language
Turkish
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public source inspected. No document-specific redistribution permission established; metadata and original brief summaries only. Local downloads are research evidence, not a redistribution package.

Citation

Gersan Elektrik Busbar Montaj Kılavuzu. Gersan Elektrik. https://gersan.com.tr/wp-content/uploads/2025/06/busbar_genel_montaj_klavuzu.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.