Technical guideFree to read2021

BEAM Plus Existing Data Centres V1.0 (Hong Kong, 2021)

Original title BEAM Plus Existing Data Centres, Version 1.0

BEAM Society Limited

The BEAM Society's 2021 manual defines a voluntary green-building assessment for existing data centres in Hong Kong; operating PUE of 2.0 earns 1 credit, 1.6 earns 8, with 1 more bonus at 1.5 and 2 at ≤1.4.

On this page

Overview

The manual is the BEAM Plus tool covering the operation and maintenance of existing data centres. It defines prerequisites and credits in the categories Management (MAN), Integrated Design and Construction Management (IDCM), Sustainable Site (SS), Materials and Waste (MW), Energy Use (EU), Water Use (WU), Health and Wellbeing (HWB) and Innovations and Additions (IA). For each credit it gives the objective, extent of application, assessment method and submittals. It takes into account Hong Kong's local climate and the limited space in most existing data centres, and encourages adopting advances such as aisle containment.

Grading has four levels. Under the comprehensive scheme (one-step or step-wise) all prerequisites must be met, together with a total score percentage and a minimum percentage for MAN and EU: Platinum needs total ≥75% and MAN/EU 70%, Gold ≥65% and 60%, Silver ≥55% and 50%, Bronze ≥40% and 40%. Under the selective (single category) scheme Platinum needs ≥70%, Gold ≥60%, Silver ≥50% and Bronze ≥40%. At most 10 innovation (IA) credits can be submitted.

The energy prerequisite is an energy audit report completed within the past five years under Hong Kong's Buildings Energy Efficiency Ordinance (Cap 610) and endorsed by a Registered Energy Assessor (REA). The metering and monitoring credit gives one point each for sub-metering, BMS logging and PUE monitoring with total facility and IT power at PDU outputs. The PUE benchmarking credit awards 1, 2, 4, 6 and 8 credits for operating PUE of 2.0, 1.9, 1.8, 1.7 and 1.6, with 1 bonus credit at 1.5 and 2 at ≤1.4; the PUE for the past 12 months is submitted as evidence.

The air management credit gives one point each for a total supply-and-return airflow efficiency of 0.9 kW/(m3/s) in data halls and for supply air temperature of at least 24 °C. The energy analysis credit defines points for one-year and over-three-year data records, EUI and PUE (Level 2) calculation, an energy audit report and a carbon audit. The manual is a certification criteria and submittal list, not a design guide; some credit heads are marked not applicable to existing data centres.

Key points

  1. Categories: Management, Integrated Design and Construction Management, Sustainable Site, Materials and Waste, Energy Use, Water Use, Health and Wellbeing, Innovations and Additions.
  2. Comprehensive scheme grades: Platinum total ≥75% (MAN and EU ≥70%), Gold ≥65% (≥60%), Silver ≥55% (≥50%), Bronze ≥40% (≥40%).
  3. Selective (single category) scheme: Platinum ≥70%, Gold ≥60%, Silver ≥50%, Bronze ≥40%; at most 10 IA credits count.
  4. EU-00-P1 prerequisite: an REA-endorsed energy audit report under Cap 610 within the past 5 years.
  5. EU-05-01 PUE credits: PUE 2.0 = 1, 1.9 = 2, 1.8 = 4, 1.7 = 6, 1.6 = 8 credits; 1.5 = 1 bonus, ≤1.4 = 2 bonus.
  6. EU-01-04 metering and monitoring (3 credits): sub-meters (chilled water and air side, lighting), BMS logging and total facility and IT energy metering at PDU outputs for PUE.
  7. EU-03-05 air management (2 credits): total airflow efficiency 0.9 kW/(m3/s) and data hall supply air temperature ≥ 24 °C.
  8. EU-04-03 energy analysis (7 credits): at least 1 year of data, EUI calculation, 1 year of PUE (Level 2), the energy audit template and a carbon audit.
  9. EU-02-01 renewable energy: 1 credit for a rooftop solar feasibility study and 1 bonus credit if at least 0.2% of energy comes from renewables.
  10. The manual is dated 2021; EU-01-01, EU-01-02, EU-01-03 and EU-03-04 are marked not applicable to existing data centres.

Using it in design

  • If BEAM Plus is targeted for an existing facility, first prepare an REA-endorsed energy audit report within the past 5 years; it is a prerequisite.
  • For PUE measurement, set up a metering architecture that measures IT power at PDU outputs and total facility power separately; the benchmarking credit rests on the past 12 months of PUE.
  • Plan PUE steps for the target grade: 1.6 and below earns 8 credits, while 1.5 and ≤1.4 earn bonus credits; link improvement investments to these steps.
  • In data halls, measure total supply-and-return fan power and airflow to calculate the 0.9 kW/(m3/s) airflow efficiency and verify supply air at ≥ 24 °C.
  • Keep sub-meter and BMS records (chilled water and air side, cooling load, lighting) for at least one year, preferably three, to support the energy analysis credit.

Who should read it

Operators and engineers seeking a green certificate for an existing data centre in Hong Kong, and consultants reviewing BEAM Plus criteria for benchmarking.

Document contents

  1. 1 Introduction (overview, framework, summary of credit heads)
  2. 2 Management (MAN)
  3. 3 Integrated Design and Construction Management (IDCM)
  4. 4 Sustainable Site (SS)
  5. 5 Materials and Waste (MW)
  6. 6 Energy Use (EU)
  7. 7 Water Use (WU)
  8. 8 Health and Wellbeing (HWB)
  9. 9 Innovations and Additions (IA)
  10. 10 Appendices (glossary, assumptions and baselines for water consumption, space type)

Publication details

Authors
BEAM Society Limited
Publisher
BEAM Society Limited
Year
2021
Document number
Version 1.0, September 2021
Document language
English
Source type
Industry body
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Copyright 2021 BEAM Society Limited; all rights reserved. Only original certification-process provisions used; ASHRAE content excluded.

Citation

BEAM Society Limited (2021). BEAM Plus Existing Data Centres, Version 1.0. BEAM Society Limited. Version 1.0, September 2021. https://www.hkgbc.org.hk/eng/beam-plus/beam-plus-references/manuals-assessment/ManualsFiles/BEAMPlus-EDCV1-2021-EN.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.