Technical guideFree to readYear not stated

Santak Castle6-10k user manual, section 1.4, printed p.5

Original title Santak Castle6-10k user manual, section1.4, printed p.5

Eaton

The Santak Castle C6K/C10K manual covers 6 and 10 kVA (5.4 and 9 kW) online double-conversion UPS: input 120-275 V, output 220 V ±1%, THD below 2%, with an altitude derating table.

On this page

Overview

The manual presents the Santak Castle Online series as a double-conversion UPS for computer, communication and industrial control systems. The rectifier converts mains AC to DC, which charges the batteries and feeds the inverter; the inverter permanently produces a pure sine voltage. On mains failure, maintenance-free batteries feed the inverter; on inverter failure or overload the UPS transfers to bypass and returns to the inverter when the fault clears.

Section 1.4 compares five models: C6K and C10K (long body with internal batteries, 58.9 and 62.1 kg), C6KS and C10KS (short body for external batteries, 14.2 and 15.9 kg) and 3C10KS (three-phase input, 16.9 kg). Body sizes are 248 x 500 x 616 mm (C6K, C10K) and 212 x 500 x 420 mm (S models). Power is 6 kVA/5.4 kW and 10 kVA/9 kW.

Input voltage range is 120-275 Vac, frequency 40-70 Hz, power factor 0.99 (0.95 for 3C10KS) and maximum input current 32.1-56.6 A (at 176 Vac input, full load and empty battery charging). Output is 220 Vac ±1%, 50 Hz ±1%, power factor 0.9, crest factor 3:1 and THD below 2% on linear full load. On overload the UPS transfers to bypass after 10 min for 105-125% (0-30 °C) or 1 min (30-40 °C), after 30 s for 125-150% and after 0.5 s above 150%.

Battery backup at full load is 4 min for the C6K and 3 min for the C10K; charge time is 7 hours to 90%. For S models the time depends on external battery capacity. Operation is 0-40 °C, storage -25 to 55 °C, humidity 20-90%, with no derating below 1000 m; a correction factor falls from 95% at 1500 m to 67% at 5000 m. At least 50 cm of space around the unit is recommended.

Key points

  1. Models: C6K (6 kVA/5.4 kW), C10K (10 kVA/9 kW), C6KS, C10KS and 3C10KS (three-phase input).
  2. Body: C6K 248 x 500 x 616 mm 58.9 kg; C10K 62.1 kg; S models 212 x 500 x 420 mm, 14.2-16.9 kg.
  3. Input: 120-275 Vac, 40-70 Hz, power factor 0.99 (3C10KS 0.95), maximum current 32.1-56.6 A (176 Vac).
  4. Output: 220 Vac ±1%, 50 Hz ±1%, power factor 0.9, crest factor 3:1, THD < 2%.
  5. Overload: 105-125% 10 min (0-30 °C) or 1 min (30-40 °C); 125-150% 30 s; above 150% 0.5 s, then bypass.
  6. Backup at full load 4 min (C6K) and 3 min (C10K); charge 7 hours to 90%.
  7. Standards: EN 62040-2:2005, EN 62040-1:2008+A1:2013, YD/T 1095-2008.
  8. Altitude derating: 1000 m 100%, 1500 m 95%, 2000 m 91%, 3000 m 82%, 4000 m 74%, 5000 m 67%.
  9. Operation 0-40 °C, storage -25 to 55 °C, humidity 20-90%; output line recommended no longer than 10 m.

Using it in design

  • Verify the load in watts: with output power factor 0.9, the limits are 5.4 kW for the 6 kVA model and 9 kW for the 10 kVA model.
  • Size input protection and cables with the maximum input current (up to 56.6 A at 176 Vac); the wide input window (120-275 V) tolerates weak mains.
  • Compare the 3-4 minute backup of the internal-battery models with the runtime target; longer autonomy needs an external battery pack on the S model.
  • Apply the derating table above 1000 m (for example 91% of nominal load at 2000 m).
  • Leave 50 cm of ventilation space around the unit in the layout and keep the output cable under 10 m and communication cables under 3 m.

Who should read it

Electrical engineers selecting and commissioning single-phase UPS for small technical rooms and industrial control loads.

Document contents

  1. Introduction (symbols, front and rear view, product specification)
  2. Installation (cables, connection, external battery, parallel card, EPO)
  3. Control and display panel
  4. Operation
  5. Maintenance
  6. Troubleshooting

Publication details

Authors
Eaton
Publisher
Eaton
Year
Year not stated
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document-specific redistribution permission was established. Bibliographic reference only.

Citation

Eaton Santak Castle6-10k user manual, section1.4, printed p.5. Eaton. https://osscom.santak.com/Castle%206-10k%20user%20manual.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace