The JUQ1 operating instruction from JUTRION Electric describes a PC-class isolation-type dual-power automatic transfer switch with a built-in controller from 20 A to 3200 A: AC 400 V, 3 or 4 poles, a transfer time of 0.45, 0.6 or 1.2 seconds depending on frame, and a conditional short-circuit current of 50 to 120 kA.

On this page

Overview

The fifteen-page instruction is the installation and operating document for the JUQ1 series dual-power automatic transfer switch from Chinese manufacturer JUTRION Electric. The product combines the switching device and logic control in one unit and needs no external controller. It provides voltage and frequency detection with electrical and mechanical interlocking, and supports automatic, motorised remote and emergency manual operation. Its classification is PC class of the load-switch type, meaning the device does not interrupt short-circuit current but only makes and carries it. The product standard is GB/T 14048.11, which corresponds to IEC 60947-6-1.

The series covers eleven frame sizes (100, 160, 250, 400, 630, 1000, 1250, 1600, 2000, 2500, 3200) and rated currents from 20 A to 3200 A. Rated operational voltage is AC 400 V, insulation voltage is 750 V or 1000 V depending on frame, and impulse withstand voltage is 8 kV or 12 kV. Making capacity is given as 10 Ie and breaking capacity as 8 Ie. In utilisation category AC-33A the larger frames are derated: the 630 A frame is rated 400 A and the 1600 A frame 1000 A.

Short-circuit data is stepped by frame: conditional short-circuit current of 50, 70, 100 and 120 kA, and short-time withstand current of 7, 9, 13, 26 and 50 kA. Transfer time from I to II or II to I is 0.45 s, 0.6 s or 1.2 s. The switch has three stable positions (I-0-II), and a forced 0 position disconnects both supplies together for fire interlocking. The drive motor draws current only at the instant of transfer. Service life exceeds 8,000 operations. Weight rises from 7.0 kg at 20 A to 43 kg at 1600 A.

The instruction defines seven wiring methods: an economy type for 100 A and below, fully automatic, forced 0, with generator start signal, with remote manual control and with a controller. The internal control supply is 220 V taken from the normal and standby sources, and the switch operates correctly within 85-110% of rated control voltage. The manufacturer requires overvoltage protection on the incoming side and short-circuit protection on the outgoing side. The document also holds outline and mounting dimension tables for all frames.

Key points

  1. Frames: 100, 160, 250, 400, 630, 1000, 1250, 1600, 2000, 2500, 3200; rated currents 20-3200 A; 3 or 4 poles.
  2. PC class, load-switch type; standard GB/T 14048.11 (IEC 60947-6-1).
  3. Rated operational voltage AC 400 V; Ui 750 V or 1000 V; Uimp 8 kV or 12 kV.
  4. Making capacity 10 Ie, breaking capacity 8 Ie.
  5. Conditional short-circuit current 50, 70, 100 or 120 kA by frame; short-time withstand current 7, 9, 13, 26 or 50 kA.
  6. Transfer time (I to II or II to I) 0.45 s, 0.6 s or 1.2 s.
  7. Control voltage DC 24 V, 48 V, 110 V or AC 220 V; operating range 85-110% of rated control voltage.
  8. Three positions (I-0-II); the forced 0 position disconnects both supplies for fire interlocking.
  9. Service life above 8,000 operations; weight from 7.0 kg (20 A) to 43 kg (1600 A).
  10. Output K1 gives a generator start signal when the normal supply fails.

Using it in design

  • A PC-class switch does not clear fault current, so coordinate the upstream protective device with the conditional short-circuit current (50-120 kA) and the short-time withstand rating.
  • A transfer time of 0.45-1.2 seconds is an interruption for IT load; use the switch on the input side of the UPS or on mechanical loads.
  • For motor and mixed loads use the derated AC-33A current; the 630 A frame, for example, is 400 A in that category.
  • Where interlocking with the fire detection system is required, choose the forced 0 wiring method and design the volt-free or DC 24 V signal.
  • In generator systems wire the K1 start output to the generator control panel, and use the 4-pole version where the neutral has to be switched.
  • Fit overvoltage protection on the incoming side; the manufacturer requires it to protect the internal board and motor.

Who should read it

Electrical engineers designing low-voltage main distribution and generator transfer boards, and panel builders.

Document contents

  1. 1. Product Overview
  2. 2. Applicable Standards
  3. 3. Model Designation
  4. 4. Applications
  5. 5. Performance and Features
  6. 6. Switch Structure
  7. 7. Main Technical Parameters
  8. 8. Main Circuit Wiring Diagram
  9. 9. Overall and Mounting Dimensions
  10. 10. Wiring Methods
  11. 11. Terminal Operation
  12. 12. Correct Mounting Positions
  13. 13. Operating Instructions
  14. 14. Ordering Information

Publication details

Authors
JUTRION
Publisher
JUTRION
Year
Year not stated
Document language
Unverified
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

No document-specific redistribution permission was established. Bibliographic reference only.

Citation

JUTRION JUTRION JUQ1 PC-class ATS operating instruction, printed pp.2-4; manufacturer JUQ1 web frame table. JUTRION. https://jutrion.com/wp-content/uploads/2026/08/juq1-pc-class-ats-operating-instruction-english.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace