Recommended Inventory for Data Center Scope 3 GHG Emissions Reporting
Schneider Electric · Paul Lin, Robert Bunger
Paul Lin and Robert Bunger narrow the GHG Protocol's 15 Scope 3 categories to nine relevant to IT resources and propose data-centre-specific subcategories.
On this page
Overview
The paper first defines Scope 1, 2 and 3 under the GHG Protocol and ISO 14064. Scope 1 includes onsite diesel generator operation, Scope 2 covers purchased electricity, heat, steam or cooling, and Scope 3 covers all other value-chain emissions. Two accounting rules apply: scopes are mutually exclusive within one organisation, but the same emissions may be counted again by another organisation in the value chain, as when a manufacturer's emissions become the buyer's upstream Scope 3.
The motivation is CDP 2019 data: supply-chain emissions average 5.5 times an organisation's Scope 1 and 2, and SBTi requires a Scope 3 target once Scope 3 exceeds 40% of the total. The 15 WRI/WBCSD categories are cut to nine: purchased goods and services, capital goods, fuel- and energy-related activities, upstream transport, waste, business travel, employee commuting, upstream leased assets and downstream leased assets. Each is described separately for on-premise, colocation and cloud IT.
Capital goods split into IT, power, cooling and other equipment (rack, fire protection, lighting). Switchgear and transformers last 20-30 years, servers 3-5, and cradle-to-gate emissions are booked in the acquisition year rather than depreciated. Transmission and distribution losses of around 5% (US EIA) fall under Scope 3 Category 3; generator fuel's upstream emissions are Scope 3 while combustion is Scope 1. Organisations without on-premise data centres should prioritise cloud services, leased colocation space and, for providers, multi- or single-tenant data centres.
Key points
- CDP 2019: supply-chain emissions average 5.5 times Scope 1 and 2; SBTi requires a Scope 3 target if Scope 3 exceeds 40% of total emissions.
- Scope 1 includes onsite diesel generator operation, Scope 2 purchased electricity, heat, steam or cooling, Scope 3 all other value-chain emissions.
- Scopes are mutually exclusive within an organisation, yet the same emissions can be counted by different organisations (a manufacturer's emissions as the buyer's upstream Scope 3).
- The 15 categories are narrowed to nine for IT: goods and services, capital goods, fuel and energy, upstream transport, waste, business travel, commuting, upstream leased assets, downstream leased assets.
- Switchgear and transformers last 20-30 years, servers 3-5; cradle-to-gate emissions are booked in the acquisition year, not depreciated.
- T&D losses are around 5% (US EIA) under Scope 3 Category 3; generator fuel purchase is Scope 3, combustion Scope 1.
- Without on-premise data centres, prioritise cloud services (Cat. 1), leased colocation space (Cat. 8) and, for providers, multi-/single-tenant data centres (Cat. 9).
Using it in design
- Structure embodied and operational carbon outputs by the nine categories of Table 2; map bill-of-materials lines to Category 2 subcategories (IT, power, cooling, other) and building materials to Category 1 core and shell.
- Record each phase’s embodied carbon in the installation year without amortisation, and record it again on replacement; identify the source lifetimes of 20–30 years for switchgear/transformers and 3–5 years for servers.
- Split generator fuel into upstream (Scope 3 Cat. 3) and combustion (Scope 1); for grid power add a configurable ~5% T&D-loss uplift in Scope 3 Cat. 3 on top of Scope 2, and support both location-based and market-based factors.
- For colocation designs, produce per-tenant allocation outputs for Cat. 8/9 reporting.
Who should read it
Engineers and ESG leads building data-centre emissions inventories and embodied-carbon calculations.
Related standards
- GHG Protocol Corporate Value Chain (Scope 3) Standard
- ISO 14064
Publication details
- Authors
- Paul Lin; Robert Bunger
- Publisher
- Schneider Electric
- Year
- 2024
- Document number
- WP 53
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Citation
Paul Lin; Robert Bunger (2024). Recommended Inventory for Data Center Scope 3 GHG Emissions Reporting. Schneider Electric. WP 53. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_WP53_EN
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.