Ulusoy Elektrik (Eaton Ankara) oil-filled distribution transformer manual: no-load first energisation, earthing below 5 ohm, thermometer alarm 85 C and trip 90 C, inspection and oil test tables.

On this page

Overview

The manual, in Turkish, covers transport, delivery inspection, handling, storage, installation, commissioning, operation and maintenance of oil-filled distribution transformers. It treats hermetic and conservator (expansion tank) designs separately.

For installation it asks for adequate ventilation indoors, with inlet openings as low and outlet openings as high as possible. The 24-hour average air temperature should be +30 C, room temperature at most +40 C and altitude no more than 1000 m. A torque table by bolt size is given for connections; flexible connections are recommended because rigid ones can crack or leak at bushings. Earth resistance should be below 5 ohm and both earthing bushes used.

For commissioning, protection relay connections are made, thermometer alarm is recommended at 85 C and trip at 90 C, and the tap position is changed only when de-energised. First energisation is without load; the transformer is loaded once temperature, noise, oil level, gas formation and electrical values are verified. For outdoor units arcing-horn gaps are tabulated by rated voltage, for example 110 mm for 12-17.5 kV; clearances rise 1.25% per 100 m above 1000 m.

The operation section gives a periodic inspection table: for hermetic units oil level weekly, bushings monthly, terminal connections every 6 months, earthing and thermometer yearly and oil dielectric test every 2 years; for conservator units desiccant silica gel monthly and oil testing yearly. In the oil test tables breakdown voltage is at least 50 kV for new oil and 40 kV or more is acceptable in service; water below 20 ppm is acceptable and 50 ppm or more means oil replacement.

Key points

  1. First energisation is without load; load is applied once normal operating values are verified.
  2. Thermometer recommendation: alarm 85 C, trip 90 C.
  3. Earth resistance below 5 ohm; checked yearly; two earthing bushes.
  4. Standard conditions: altitude up to 1000 m, ambient at most +40 C, 24-hour average +30 C.
  5. Storage temperature -25 to +50 C (unless otherwise requested).
  6. Tap changing only when de-energised (unless an on-load tap changer is fitted).
  7. Inspections: oil level weekly, bushings monthly, terminals 6-monthly, earthing yearly, oil dielectric test every 2 years (hermetic).
  8. Oil: breakdown voltage 40 kV or more acceptable in service; water below 20 ppm acceptable, 50 ppm or more replace.
  9. The pressure relief valve must never be painted; no maintenance while energised.

Using it in design

  • Design transformer-room ventilation with low inlet, high outlet and the 40 C room temperature limit.
  • For altitude above 1000 m and ambient above +40 C, state special conditions in the order.
  • Wire protection relay and thermometer contacts (85/90 C) to the monitoring system.
  • Design earthing for below 5 ohm and include it in the annual measurement plan.
  • Prepare the maintenance calendar by hermetic versus conservator type and plan oil test intervals.
  • Add the torque table to the commissioning checklist.

Who should read it

Electrical engineers and commissioning and maintenance teams running distribution transformer installations.

Document contents

  1. Introduction
  2. Important safety information
  3. Transport
  4. Handling
  5. Storage
  6. Commissioning and use
  7. Operation and maintenance
  8. Accessories

Publication details

Authors
Ulusoy Elektrik / Eaton Ankara
Publisher
Ulusoy Elektrik / Eaton Ankara
Year
Year not stated
Document language
Turkish
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official publisher material inspected. No document-specific commercial redistribution permission established; retain metadata and original short summaries only.

Citation

Ulusoy Elektrik / Eaton Ankara Dağıtım Transformatörleri Bakım, İşletme, Devreye Alma ve Kullanma Talimatı. Ulusoy Elektrik / Eaton Ankara. https://www.ulusoyelektrik.com.tr/sites/other/ulusoyelektrik/uploads/contents/162/ccbad0fa9449cd728f057551374904a1.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.