UFGS 01 91 00.15: Building Commissioning (Change 3)

Original title UFGS 01 91 00.15: Building Commissioning, Change 3

USACE / NAVFAC / AFCEC

The US Unified Facilities Guide Specification 01 91 00.15 (USACE, NAVFAC, AFCEC; May 2023, Change 3 August 2024) defines commissioning from design through warranty visit, with a Certificate of Readiness and sampling rules.

On this page

Overview

UFGS 01 91 00.15 is the building commissioning specification under Division 01 General Requirements prepared by the US Army Corps of Engineers, NAVFAC and the Air Force Civil Engineer Center (May 2023, Change 3: August 2024; it supersedes the 2019 and 2021 versions). As a guide specification it contains bracketed options to tailor to the project, and it coordinates commissioning of the systems required by ASHRAE 90.1 and UFC 1-200-02.

The structure is as follows. Part 1 covers references, definitions, systems to be commissioned, team, schedule, phasing, submittals, the commissioning firm and specialists, the commissioning standard, sustainability third-party certification, the issues log and the Certificate of Readiness. Part 3 covers the design-phase coordination meeting (before 50 percent design) and commissioning plan, design review, construction-phase plans and site visits, inspections, tests, training plan, systems manual, maintenance and service life plan, commissioning report and warranty-phase site visit.

As commissioning standard, ASHRAE 202 applies along with the standard under which firm and specialist qualifications were approved (ACG, NEBB S1110 or ANSI/SMACNA 014); in a conflict the most stringent requirement applies, and NETA test standards can be added for electrical systems. Before tests of each system, the Quality Control Manager issues a Certificate of Readiness, submitted a bracketed period such as 30 calendar days or 20 working days before the tests, and no tests are scheduled until it is approved.

For test sampling, either 100 percent or less-than-100-percent procedures can be selected. In sampling, at least three units of each group of identical equipment are tested at random; if 10 percent of the first sample fails, a second sample of the same size is tested, and if 10 percent of the second fails, all remaining units are tested. Aborted tests are repeated and the Contracting Officer may withhold payment for lost time and re-testing.

Key points

  1. Edition: UFGS-01 91 00.15, May 2023, Change 3 August 2024; supersedes the 2019 and 2021 versions.
  2. Commissioning standard: ASHRAE 202 with ACG, NEBB S1110 or ANSI/SMACNA 014; most stringent applies; NETA can be added for electrical.
  3. The design-phase commissioning coordination meeting must occur before 50 percent design completion.
  4. The design-phase commissioning plan is submitted no later than 14 calendar days after the coordination meeting.
  5. A Certificate of Readiness is issued per system before tests; the example period is 30 calendar days or 20 working days; no testing until approved.
  6. Sampling: at least three units per group; 10 percent failure in the first sample triggers a second, and 10 percent in the second triggers testing of all remaining units.
  7. The issues log is submitted monthly and within three working days.
  8. Training plan, systems manual, maintenance and service life plan, commissioning report and warranty-phase visit are deliverables.

Using it in design

  • Structure a data-centre commissioning specification on this section: design-phase plan, design review, construction plan, tests and warranty visit.
  • Schedule the commissioning coordination meeting before 50 percent design and settle the list of systems to commission early.
  • Put a Certificate of Readiness requirement per critical system into the contract, with no testing before approval.
  • For multi-unit equipment (PDUs, CRAHs), write explicit sampling rules such as the three-unit minimum and 10 percent failure escalation.
  • List the issues log, training, systems manual and maintenance plan as mandatory handover deliverables.

Who should read it

Commissioning authorities, engineers writing public-project specifications and consultants defining data-centre commissioning scope.

Document contents

  1. Part 1 General: references, definitions, systems to be commissioned, commissioning team, project schedule, submittals, commissioning firm, commissioning standard, third-party certification, issues log, certificate of readiness
  2. Part 2 Products
  3. Part 3 Execution: design coordination meeting, design phase plan, design review, construction submittal reviews, kickoff and coordination meetings, construction phase plans, site visits, inspections, commissioning tests, training plan, systems manual, maintenance and service life plan, commissioning report, warranty phase site visit

Publication details

Authors
USACE / NAVFAC / AFCEC
Publisher
USACE / NAVFAC / AFCEC
Year
2024
Document number
UFGS 01 91 00.15; 05/23, CHG 3: 08/24
Document language
English
Source type
Industry body
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official public publisher source inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only. Local downloads are research evidence, not a redistribution package.

Citation

USACE / NAVFAC / AFCEC (2024). UFGS 01 91 00.15: Building Commissioning, Change 3. USACE / NAVFAC / AFCEC. UFGS 01 91 00.15; 05/23, CHG 3: 08/24. https://www.wbdg.org/FFC/DOD/UFGS/01%2091%2000.15.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.