Picking the Right UPS for Your Critical Applications: A White Paper on Availability
Vertiv
This 2018 Vertiv introductory guide approaches data-centre UPS selection through the disturbances each topology handles.
On this page
Overview
The guide contrasts three topologies: passive standby, line-interactive and online double conversion. Among them only online double conversion provides zero transfer time, frequency regulation, power factor correction and harmonic correction. Passive standby is considered unsuitable for three-phase applications and limited to single-phase workstation loads. Common power-quality problems are catalogued by disturbance type, showing which topology removes which. This is why the guide frames selection as matching topology to the disturbances a site must tolerate.
Design choices layered on double conversion form the second part. Double-conversion systems can exceed 96% efficiency without availability compromise. Transformer-free designs are increasingly used between 200 kW and 5 MW, with about 300 kW cited as the threshold below which their space, weight and cost advantages dominate. Capacity-on-demand modularity comes in two forms: software-keyed capacity steps (40-80 kVA, 80-120 kVA or 160-200 kVA) and row-based modular units that grow in 15 kW power cores up to 45 or 90 kW per cabinet.
Finally the eco-mode variant is covered: keeping the inverter energised costs under 1% of rated power, yields 4-4.5% savings against typical double conversion and efficiencies above 98%, and makes transfers nearly seamless. The paper dates from 2018 and its figures are vendor claims, but it works as a compact introduction that compares topology, transformer and modularity choices in one frame.
Key points
- Of the three topologies, only online double conversion provides zero transfer time, frequency regulation, power factor correction and harmonic correction.
- Passive standby is considered unsuitable for three-phase applications and limited to single-phase workstation loads.
- Double-conversion systems can exceed 96% efficiency without availability compromise.
- Transformer-free designs are increasingly used for 200 kW-5 MW; about 300 kW is cited as the threshold below which their space, weight and cost advantages dominate.
- Software-keyed capacity steps such as 40-80, 80-120 or 160-200 kVA; row-based modular units grow in 15 kW power cores up to 45 or 90 kW per cabinet.
- Keeping the inverter active in eco mode costs under 1% of rated power, yielding 4-4.5% savings and efficiencies above 98%.
Using it in design
- For UPS selection, record topology classification, transformer-based vs transformer-free, modular increment (kW) and maximum frame, and eco-mode type (passive bypass vs active inverter).
- Require double conversion for three-phase critical loads.
- When eco mode is used, report its transfer behaviour.
- Suggest right-sizing via capacity-on-demand when the initial load is well below design load.
Who should read it
Designers and decision makers choosing UPS topology and modularity for the first time.
Related standards
- IEC 62040-3
Publication details
- Authors
- Vertiv
- Publisher
- Vertiv
- Year
- 2018
- Document language
- English
- Source type
- Manufacturer
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Citation
Vertiv (2018). Picking the Right UPS for Your Critical Applications: A White Paper on Availability. Vertiv. https://www.vertiv.com/4aabcf/globalassets/documents/white-papers/white_paper_refresh_-_picking_the_right_ups_for_your_data_center-rev2_244002_0.pdf