Victaulic's July 2009 white paper: grooved mechanical couplings on chilled-water pipe install up to 10 times faster than welding in the field and reduce outage risk during maintenance and expansion.

On this page

Overview

The paper is a manufacturer white paper written by David Gibbons of Victaulic, dated 15 July 2009 (WP-05 Rev. A). It explains that rising computing density needs more efficient cooling and that in larger data centres chilled water is the most cost-effective method. Chilled water goes from the mechanical room through under-floor lines to air handlers, absorbs heat, returns to the chiller and the heat leaves through the condenser-water loop and cooling tower.

Welding, brazing and flanging on carbon steel pipe or copper tube are common, but the paper says that growing loads, frequent changes and expansion make them problematic: access is hard, design flexibility is limited, they create fire hazards and need long shutdowns for maintenance. In a grooved mechanical joint, coupling housings seat in a groove cut in the pipe end, the gasket is compressed and a triple seal forms that strengthens under pressure.

The manufacturer states that field fabrication of a grooved system is up to 10 times faster than welding and six times faster than flanged joints, and can halve project calendar days. A grooved joint acts as a union at every point: two nuts are loosened and the coupling opens, against 12 bolts on a 12-inch Class 150 flanged line. It can be installed on wet lines and reduces the need for hot-work permits and fire watch.

The paper also describes reduced transmission of vibration and noise, lower loads at equipment connections and the ability to accommodate movement in seismic zones. It is a product-oriented white paper; the comparisons are the manufacturer's statements and rest on older (2009) data.

Key points

  1. Field fabrication of a grooved system is up to 10 times faster than welding and six times faster than flanged joints.
  2. Up to a 50% reduction in project calendar days is reported.
  3. The joint has four elements: grooved pipe, gasket, coupling housings, and nuts and bolts; the triple seal strengthens with pressure.
  4. A grooved joint allows 360 degrees of rotation; flange rotation is limited to bolt-hole increments.
  5. A 12-inch Class 150 flanged joint needs 12 bolts removed; a grooved coupling needs two nuts.
  6. Grooved joints can be installed on wet lines and reduce hot-work permit and fire-watch needs.
  7. Three consecutive flexible couplings near a vibration source are said to give noise damping similar to specialty products.
  8. Citing the Uptime Institute, 2001 allowed 1.6 hours of downtime a year for Tier III and 0.4 hours for Tier IV.

Using it in design

  • In chilled-water distribution, plan mechanical grooved joints in sections where expansion and maintenance are expected, with butterfly-valve dead-end isolation points.
  • For pipe work in live halls, weigh the fire, fume and work-stoppage risks of hot work in the choice of joining method.
  • At equipment connections use flexible couplings to reduce vibration and pipe-load transfer, and check the equipment maker's allowable nozzle loads.
  • In seismic zones, set the number and position of flexible joints by differential movement analysis.
  • Do not use the maker's speed and cost claims as a comparison criterion without checking them against local labour and project schedule data.

Who should read it

Mechanical engineers choosing chilled-water pipe design and joining methods, and construction planners.

Document contents

  1. Introduction: Chilled Water Cooling and Joining Methods
  2. Grooved Pipe Joining Technology
  3. Installing a Grooved Mechanical Piping System
  4. Maintenance and Expansion of Grooved Mechanical Piping Systems
  5. Protecting Equipment Using Grooved Mechanical Piping Systems
  6. Seismic Considerations

Publication details

Authors
David Gibbons
Publisher
Victaulic
Year
2009
Document number
WP-05 Rev. A; 15 July 2009
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public manufacturer document or page inspected. No document-specific redistribution permission established; retain metadata and original short summaries only.

Citation

David Gibbons (2009). Keeping Your Cool: Grooved Technology as a Means to More Efficient Data Center Construction and Operation. Victaulic. WP-05 Rev. A; 15 July 2009. https://assets.victaulic.com/assets/uploads/literature/White%20Paper/WP-05.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cooling capacity in SoSo CAD

Check zone heat loads, installed capacity and the capacity left with the largest unit out, as part of the design.

Zone heat loads and capacity balance in the SoSo CAD cooling workspace