Data-centre investments in Türkiye: energy supply of data centres
Original title Türkiye'de Veri Merkezi Yatırımları: Veri Merkezlerinin Enerji Tedariki (Data-centre investments in Türkiye: energy supply of data centres)
Çakmak Avukatlık Bürosu · Mustafa Durakoğlu, Nazlı Başak Ayık et al.
A legal briefing of 10 February 2026 on how Turkish data centres can secure electricity: long-term power purchase agreements, unlicensed self-generation, storage and ESCO/energy performance contracts.
On this page
Overview
This legal briefing of 10 February 2026, by Mustafa Durakoğlu, Nazlı Başak Ayık and Zeynep Ayça Şenol of Çakmak Avukatlık Bürosu, examines how Turkish data centres can secure electricity: long-term power purchase agreements, on-site or remote self-generation under the Unlicensed Electricity Generation Regulation, storage, and ESCO or energy performance contracts. It also summarises the IEA's global context.
According to the global-situation section, data centres use about 1.5% of global electricity (of that, the US accounts for 45% and China 25%), and about 20% of planned data centre projects risk delay from grid constraints (IEA). PPAs are typically 10-20 years; in Türkiye price volatility pushes parties toward shorter terms.
Two models stand out in the self-generation section. Model 5(1)[c] covers renewable plants up to 5 MW; surplus is bought for 10 years at the active-energy price, but the model is too small for full data centre demand. Model 5(1)[h] allows a renewable plant at the same or a different metering point, limited to the contract power in the connection agreement, and is judged the most suitable model for data centres.
On storage, from 1 January 2026 unlicensed plants with net-metering may add storage; equipment must be standard-compliant, under warranty and produced within the last five years. The Climate Law in force since 9 July 2025 introduces an emissions trading system, raising the value of renewable electricity. As a limitation, this is a legal briefing and does not replace legal advice.
Key points
- Data centres use about 1.5% of global electricity (US 45%, China 25% of that); about 20% of planned projects risk delay from grid constraints (IEA).
- PPAs are typically 10-20 years; in Türkiye price volatility pushes parties to shorter terms.
- Model 5(1)[c]: renewable plants up to 5 MW; surplus bought for 10 years at the active-energy price, but too small for full data centre demand.
- Model 5(1)[h]: renewable plant at the same or a different metering point, limited to contract power; judged the most suitable for data centres.
- From 1 January 2026, unlicensed plants with net-metering may add storage.
- Storage equipment must be standard-compliant, under warranty and produced within the last five years.
- The Climate Law in force from 9 July 2025 introduces an emissions trading system.
Using it in design
- In the site and energy module for Turkish projects, let users model PPA versus unlicensed self-generation (5(1)[h], with the 5 MW cap for 5(1)[c]) and storage.
- Flag grid-connection capacity as a schedule risk.
- Consider the effect of the emissions trading system as a scenario in the renewable supply strategy.
Monthly newsletter · free
Keep your reading list current
Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.
SoSo CAD
Compare the cost of design decisions
Evaluate equipment costs, energy expenses and total cost of ownership (TCO) using your inputs and assumptions in SoSo CAD.
Request a demo
Who should read it
Investors, energy procurement managers and legal counsel planning data centre investments in Türkiye.
Publication details
- Authors
- Mustafa Durakoğlu; Nazlı Başak Ayık; Zeynep Ayça Şenol
- Publisher
- Çakmak Avukatlık Bürosu
- Year
- 2026
- Document language
- English
- Source type
- Expert / community
- Access
- Free to read
- Licence
- Copyright retained; citation only — the publisher’s terms apply to the original document
Citation
Mustafa Durakoğlu; Nazlı Başak Ayık; Zeynep Ayça Şenol (2026). Türkiye'de Veri Merkezi Yatırımları: Veri Merkezlerinin Enerji Tedariki (Data-centre investments in Türkiye: energy supply of data centres). Çakmak Avukatlık Bürosu. https://cakmak.av.tr/wp-content/uploads/2026/02/Veri-Merkezlerinin-Enerji-Tedariki.pdf
Events on this subject
Browse the events calendarAll content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.