Benefits and Drawbacks of Prefabricated Modules for Data Centers

Schneider Electric · Wendy Torell, Dennis Bouley et al.

This 2026 Schneider Electric white paper compares factory-built power, cooling and IT modules with conventional stick-built construction on capex, opex, schedule and risk.

On this page

Overview

The core claim is that total capital cost is roughly equal while schedule can shrink by up to 60%. The material premium for module shells and factory integration is offset by reduced site labour, design and building-shell space. Simple core-and-shell construction costs about $100-150 per ft2 ($1,076-1,614 per m2). Site plan design and engineering can be about 5% of total project expense in traditional builds, and pre-integrated subsystems can save 50% of design and engineering time.

The deployment estimate is about 34 weeks modular versus 88 weeks traditional, concept to commissioning. Table 1 gives 12 to 24 months for traditional builds, while prefabricated can be operational within 8 months or less. In the energy example, a traditional 1 MW data center in St. Louis (50% load, 6 kW/rack, raised floor, chillers with VFDs and economizers) reaches a PUE of about 1.75, while a comparable prefabricated configuration is expected at 1.4 or better, about a 20% lower electricity bill.

Drawbacks include existing building investment, long cable and pipe runs to interior IT rooms, weather and security exposure, cramped servicing, AHJ uncertainty and road transport limits; the cited US transport width limit is 11.6 ft (3.5 m), and wider loads need permits and possibly escorts. On carbon, steel and aluminum produce about half the emissions of concrete, and modules need concrete only for the support pad.

The paper is a vendor's view, its figures rest on the authors' example configurations, and advantages such as equipment-rather-than-building tax treatment depend on jurisdiction.

Key points

  1. Prefabricated deployment can be up to 60% faster at approximately the same capital cost.
  2. Schedule: about 34 weeks modular versus 88 weeks traditional.
  3. Traditional builds take 12-24 months; prefabricated can be operational in 8 months or less.
  4. Simple core-and-shell construction costs about $100-150 per ft2 ($1,076-1,614 per m2).
  5. St. Louis 1 MW example: traditional PUE about 1.75 versus 1.4 or better prefabricated (about 20% lower electricity bill).
  6. Pre-integrated subsystems can save 50% of design and engineering time.
  7. US transport width limit cited as 11.6 ft (3.5 m); wider loads need permits.
  8. Steel and aluminum produce about half the carbon of concrete.

Using it in design

  • Offer a delivery-method option per subsystem (stick-built or prefabricated), defaulting to about 88 and 34 weeks with editable phase durations.
  • In the cost model, shift cost from site labour and shell ($/m2) to an equipment premium when prefabrication is chosen, and show the roughly equal total with sensitivity.
  • Add site checks for module footprint versus pad, crane access, transport width above 3.5 m and cable/pipe length from outdoor plant modules to the indoor IT room.
  • Let factory acceptance test (FAT) credit reduce on-site Level 1-3 commissioning scope.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Bring standards pre-checks into your project

Review model-based TS EN 50600 and Tier pre-checks, missing inputs and items requiring engineering review in SoSo CAD.

Request a demo
Selected rule packs and findings in the SoSo CAD standards panel

Who should read it

Owners and project managers choosing between prefabricated and stick-built delivery.

Related standards

  • NFPA 70 (NEC)
  • UL 2755
  • ASHRAE 90.4

Publication details

Authors
Wendy Torell; Dennis Bouley; Scott Neal
Publisher
Schneider Electric
Year
2026
Document number
WP 163
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Wendy Torell; Dennis Bouley; Scott Neal (2026). Benefits and Drawbacks of Prefabricated Modules for Data Centers. Schneider Electric. WP 163. https://download.schneider-electric.com/files?p_Doc_Ref=SPD_WTOL-7NGRBS_EN

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.