Technical guideFree to read2013

Totally Integrated Power - Application Models for Power Distribution: Data Centres

Siemens · Siegbert Hopf

This 80-page Siemens planning manual from 2013 walks the whole electrical chain of a data centre, from medium voltage to sub-distribution. Its Tier IV worked example is especially useful because it puts numbers on how redundancy choices inflate installed UPS capacity and floor area.

On this page

Overview

The manual moves in sequence through planning tasks, availability concepts, MV switchgear, cast-resin transformers, standby generator sets, UPS, LV switchboards, sub-distribution and power management. Availability is defined as A = MTBF / (MTBF + MTTR) and the BSI availability classes are reproduced, which ties the redundancy decision to a measurable quantity instead of intuition. The space-planning section gives tier-dependent infrastructure space factors: Tier II versus Tier I ranges from x1.2 (n=5) to x2 (n=1), Tier III is 1.25 times Tier II, Tier IV (n+n) is 2 times Tier I, and Tier IV (n+1)+(n+1) is 2.4-4 times Tier I.

For the same IT load, the grey space therefore grows sharply as redundancy rises. In the worked example, a 2,400 kW ICT load at PUE 1.5 gives 3,600 kW total, four computer rooms of 300 m2 and roughly 2,400 m2 of total area. The (N+1)+(N+1) design installs 7,200 kVA of UPS apparent-power capacity for that load; the source notes that kVA and kW are different units, so the figure alone is not a real-power multiplier.

Swing concepts are shown to recover utilisation. It is a 2013 vendor manual: product and topology examples reflect Siemens' system approach and do not track every detail of the current Uptime Tier Standard. It still provides a calculation skeleton aligned with IEC 60364, IEC 61439, IEC 62040-3 and EN 50600, which makes it a good starting reference for early-stage sizing.

Key points

  1. Availability A = MTBF / (MTBF + MTTR).
  2. Space factors: Tier II vs I x1.2 (n=5) to x2 (n=1); Tier III vs II x1.25; Tier IV (n+n) vs I x2; Tier IV (n+1)+(n+1) vs I x2.4-4.
  3. Example: 2,400 kW ICT x PUE 1.5 = 3,600 kW total; 4 computer rooms x 300 m2; about 2,400 m2 total.
  4. The (N+1)+(N+1) example installs 7,200 kVA of UPS apparent power for 2,400 kW ICT; kVA and kW differ, so this is not a real-power multiplier.
  5. Critical (ICT) to infrastructure power split is about 2:1 (PUE about 1.5).
  6. Safety-services changeover is typically within 15 s (0.15 s for some circuits).
  7. Cast-resin transformers go up to 2,500 kVA; forced ventilation can lift a 1,000 kVA unit to about 1,300-1,500 kVA.

Using it in design

  • Use the tier factors as defaults in the early-stage area estimator: grey space = white space x factor.
  • Show installed UPS / IT load per topology as a cost KPI (N=1.0, 2N=2.0, 2(N+1)=about 3.0).
  • Build the availability calculator on A=MTBF/(MTBF+MTTR) with series and parallel composition.
  • Keep kVA and kW separate: report redundancy multipliers on real power and UPS capacity on apparent power.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.

SoSo CAD

Review your power design in SoSo CAD

Inspect supply paths, equipment loads and UPS failure scenarios in one model.

Request a demo
Single-line diagram in the SoSo CAD power and capacity workspace

Who should read it

Design engineers who need to estimate redundancy and floor area for a data centre electrical chain early.

Related standards

  • IEC 60364
  • IEC 61439
  • IEC 62040-3
  • EN 50600
  • Uptime Tier Standard: Topology
  • BSI High-Availability Compendium

Publication details

Authors
Siegbert Hopf
Publisher
Siemens
Year
2013
Document language
English
Source type
Manufacturer
Access
Free to read
Licence
Copyright retained; citation only — the publisher’s terms apply to the original document

Citation

Siegbert Hopf (2013). Totally Integrated Power - Application Models for Power Distribution: Data Centres. Siemens. https://assets.new.siemens.com/siemens/assets/api/uuid:7c0c711e32fb88aab5569489cb754c148a1f2d50/power-distribution-in-data-centres.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.