The NSW Government's August 2026 guidelines set data-centre application targets of dPUE ≤1.25 with dWUE ≤1.0 (or dPUE ≤1.3 with dWUE ≤0.44), diesel generator emission limits and a 25% grid-demand reduction for 2 hours.
On this page
Overview
The NSW Government's August 2026 Data Centre Guidelines define six principles and measurable performance measures for proponents investing in data centres in the state. The aim is a faster, more predictable assessment process while showing that energy, water and community impacts are managed. The guidelines align with the Australian Government's March 2026 expectations and will be reviewed annually.
The background section is backed by numbers: AEMO forecasts data centres rising from 5% of NSW grid energy in 2026 to 11% by 2030. Oxford Economics estimates that 6 in every 7 MW of connection requests is phantom demand, and utilities expect about 20% of applications to proceed. Recent applications show PUE between 1.15 and 1.4 (average 1.3), and 9 of 12 projects averaged a WUE of 1.0.
Principle 1 (environment and efficiency) is the most technical: dPUE/dWUE targets, 100% recycled water for water-intensive cooling or an agreed transition with the water utility, drought-capable hybrid cooling, Group 6 limits for diesel generators such as NOx at 450 mg/m³, noise, fire and explosion risk, demand data and smart meters. Principle 2 requires the ability to cut grid draw by 25% for 2 hours and cost recovery for infrastructure.
The guidelines are an assessment framework, not a regulation: compliance is shown in the Environmental Impact Statement and conditions are written into consent. The remaining principles cover water and energy supply, local infrastructure, supply chain and skills. For designers, the key value is that targets are tied to explicit climate and utilisation assumptions.
Key points
- Table 2, measure 1: dPUE ≤1.25 with dWUE ≤1.0 (potable) or ≤1.6 (non-potable); alternatively dPUE ≤1.3 with dWUE ≤0.44. Other arrangements with the water utility and offsetting initiatives are allowed.
- Designs use average annualised climate data and mature utilisation at 100% IT load; PUE is measured to ISO/IEC 30134-2:2026 and WUE to ISO/IEC 30134-9:2022.
- Evaporative, adiabatic and other open-loop cooling needs 100% recycled water or a utility agreement for the transition; interim potable use must allow reduced water use under drought restrictions through hybrid cooling.
- Diesel generator Group 6 limits: NOx 450 mg/m³, solid particles 50 mg/m³, VOC 1,140 mg/m³, CO 5,880 mg/m³ (for example with SCR). Non-urban sites away from sensitive receivers may use US EPA Tier 2 limits (NOx+NMHC 6.4 g/kWh, CO 3.5 g/kWh, PM 0.20 g/kWh).
- Fire and explosion risk covers diesel storage, Li-ion batteries and electrical work; battery systems of 30 MW and above need a Preliminary Hazard Analysis before approval and a Fire Safety Study after.
- Measure 9: ability to reduce grid-supplied demand by 25% of forecast average load for up to 2 hours, in a hierarchy of load shifting, on-site or proximate renewables and storage, and non-diesel options.
- Maximum and average water and energy demand data are provided commercial-in-confidence, and smart energy and water meters are required.
- The government commits to SEARs within 2 months and a state-side assessment of no more than 75 days; 19 SSD projects worth $50.3 billion are in the pipeline (July 2026).
Using it in design
- Compute dPUE at average annual climate and 100% IT load using site weather data, and decide early which of the 1.25 or 1.3 routes can be met together with the water target.
- Treat recycled water access or a water-utility agreement as a precondition for open-loop cooling, and size a dry or hybrid fallback for drought scenarios.
- Classify the site as urban or non-urban when selecting generators: document SCR-type abatement for Group 6 in urban sites, Tier 2 compliance in remote ones.
- For the 25% demand reduction, build pre-cooling or thermal storage, batteries and load shifting into the single-line diagram and control architecture.
- Make smart metering, demand data and fire safety study outputs standard items in the design deliverables.
Who should read it
Designers, planning consultants and investors preparing data-centre applications in NSW, and engineers comparing similar policy targets.
Document contents
- Overview and approach of the NSW Data Centre Guidelines
- Data centre investment, operation and resource use in NSW
- Speed to market and efficient planning outcomes for data centre investors
- Principles and performance measures
- Principle 1: Apply world-class environmental and efficiency standards
- Principle 2: Impose no net cost to consumers and communities
- Principle 3: Fund additional supply of water and energy
- Principle 4: Enhance local community infrastructure and amenity
- Principle 5: Invest in future industries across the supply chain
- Principle 6: Demonstrate a commitment to training and skills to support jobs
- Future actions and next steps
- Appendix A: Glossary
Publication details
- Authors
- NSW Government
- Publisher
- NSW Government
- Year
- 2026
- Document number
- August 2026
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public source inspected. Document-specific permission for commercial redistribution was not established; metadata and original short summaries only.
Citation
NSW Government (2026). NSW Data Centre Guidelines. NSW Government. August 2026. https://www.infrastructure.nsw.gov.au/media/4jlictae/id0073_nsw-data-centre_guidelines.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.