Fact sheet: Power purchase and firming agreements under the NSW Data Centre Guidelines
NSW Government
NSW Government fact sheet (September 2026) explaining the data-centre requirement of at least 40% wind, 4-hour storage of at least 25% of generation capacity and agreements of at least 10 years, with a 125 MW worked example.
On this page
Overview
The September 2026 fact sheet from the NSW Government explains Performance Measure 13 of the NSW Data Centre Guidelines. The measure expects data centres to enter power purchase agreements (PPAs) and firming agreements for additional generation assets in NSW to meet the data centre's electricity demand (MWh).
The measure's conditions are: at least a 40% wind component (MWh); storage, battery or pumped hydro, of at least 25% of generation capacity (MW) for four hours; from the fourth year of operation, contracted energy equal to the annual average demand; a term of at least ten years; and projects that have not reached final investment decision at contracting. Agreements may be portfolio-based or tied to a specific data centre, and co-location providers can show commitments through operator and major tenant agreements.
The fact sheet says a PPA can be physical supply from a co-located generator, a financial swap, or a retail contract backed by a generator; it requires both the electricity and the certificates it creates to be covered, with certificates surrendered to avoid double counting. Firming examples are shaping, tolling and cap contracts. If a project is delayed, additional time may be considered and short-term mismatch can be topped up with REGO certificates.
The wind, solar and storage components are set to deliver an average 80% correlation between new supply and data-centre demand across a year. A worked example follows a 125 MW connection with a 100 MW average load. The fact sheet does not describe the full set of supply arrangements a data centre may use.
Key points
- Performance Measure 13: at least 40% wind (MWh), 4-hour storage of at least 25% of generation capacity (MW), at least 10 years.
- Contracted energy must equal annual average demand from the start of the fourth operating year and rise as operations ramp up.
- Agreements are for new or expanded projects that have not reached final investment decision at contracting.
- A PPA must cover both electricity and certificates; certificates are surrendered to avoid double counting.
- Wind, solar and storage together target an average 80% demand-supply correlation over a year.
- Example: a 100 MW flat load needs 876,000 MWh a year; 40% of that, 350,400 MWh, comes from wind and the remaining 525,600 MWh from solar.
- The example contracts 118 MW of wind (34% capacity factor), 214 MW of solar (28%) and an 83 MW / 332 MWh battery firming agreement; total generation is 332 MW.
- With 80% wind and 20% solar, total generation is 307 MW and required storage 77 MW / 307 MWh.
- A 25 MW / 50 MWh on-site battery reduces the firming need from 83 MW / 332 MWh to 70.5 MW / 282 MWh.
Using it in design
- For a NSW project, compute annual MWh demand from average load (assuming about 80% of connection capacity) and derive the wind share (40%) and solar share from that energy.
- Convert on-site demand-flexibility battery capacity into its 4-hour equivalent to size the reduction of the firming contract.
- Because a higher wind share lowers the storage required, optimise the portfolio mix together with storage cost.
- Anchor the contract timeline to the first months after planning consent; energy and certificates must be available at the start of year four.
- For sites with a growth plan, write scaling of contracted volume and storage with demand growth into the contracts.
Who should read it
Investors developing data centres in Australia, energy procurement teams and electrical designers, and policy analysts studying similar renewable supply requirements.
Document contents
- What is Performance Measure 13?
- What is a PPA?
- What is a firming agreement?
- When must contracts be in place?
- How wind, solar and storage meet data-centre energy needs
- Worked example: PPA and firming agreements for a 125 MW data centre
Publication details
- Authors
- NSW Government
- Publisher
- NSW Government
- Year
- 2026
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Public official source inspected; no document-specific commercial redistribution permission established. Original short summaries and metadata only; downloads are local research evidence.
Citation
NSW Government (2026). Fact sheet: Power purchase and firming agreements under the NSW Data Centre Guidelines. NSW Government. https://www.infrastructure.nsw.gov.au/media/ctundwph/id0073_nsw-data-centre_guidelines-factsheet.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.