Data Centres: Key Tips for Cantons and Municipalities
Original title Rechenzentren – wichtige Tipps für Kantone und Gemeinden
EnergieSchweiz, Bundesamt für Energie
EnergieSchweiz planning guide for cantons and municipalities: Schaffhausen requires PUE+ of at most 1.20 within three years of commissioning, and up to 80% of a data centre's electricity could be reused as heat.
On this page
Overview
The guide is a web publication from the Swiss federal energy programme EnergieSchweiz for cantons and municipalities facing a data-centre project. It frames a data centre as both an opportunity and a challenge. Because public authorities often learn about projects late, it advises raising topics such as waste-heat reuse at the start and preparing legal bases before an application arrives. It also answers frequent questions collected in a webinar.
Figures set the context. Enterprise and commercial data centres use 3.6% of Swiss electricity. Consumption was 2.1 TWh in 2024, 44% commercial (colocation and cloud) and 56% enterprise, and could reach 2.5 to 3.2 TWh by 2030. Nearly 120 commercial data centres operate in the 2 to 20 MW range. Conventional facilities connect at 2 to 20 MW and AI-capable ones up to 200 MW. The largest planned site, in Volketswil, is close to 100 MW.
The guide lists the areas a municipality can influence: the electricity grid and substation needs, water (up to 1,500 m3 per GWh of IT energy depending on cooling), waste heat, backup generators and land use. Legal instruments include cantonal energy law, cantonal and regional structure plans, municipal energy planning and building law. For existing sites, target agreements, funding programmes, networking and the SDEA label stand out.
It also gives a worked example: 20 MW IT load, PUE 1.2, 40% utilisation, 84 GWh per year, 40,600 m3 per year of water and heat for 4,700 households. It stresses that waste heat is low-temperature (25 to 40 degrees C) and constant all year, so a steady heat customer or seasonal storage is needed. The guide gives no product selection or cost calculation; it supplies a planning and regulatory framework.
Key points
- Schaffhausen energy ordinance: data centres must reach PUE+ of at most 1.20 within three years of commissioning or obtain SDEA Gold certification.
- MuKEn 2025 (article 1.18): a company that does not use more than 2 GWh per year of its waste heat must offer it to third parties at production cost.
- Zurich structure plan: facilities with waste-heat potential above 5 GWh per year are identified in regional plans, which corresponds to small to medium data centres.
- Data centres use 3.6% of Swiss electricity; 2.1 TWh in 2024 (44% commercial, 56% enterprise), possibly 2.5 to 3.2 TWh by 2030.
- Technically up to 80% of a data centre's electricity can be used as waste heat; the heat is 25 to 40 degrees C and constant all year.
- Water use can reach up to 1,500 m3 per GWh of IT energy depending on the cooling system.
- Worked example: 20 MW IT, PUE 1.2, 40% utilisation, 84 GWh/yr, 40,600 m3/yr water, heat for 4,700 households (usable waste heat 47%, WUE 580 m3/GWh IT).
- Sites above 500 MWh per year fall under the large-consumer model of MuKEn; target agreements apply, but classification follows actual consumption after commissioning, so they cannot be used to demand measures at building permit.
- The SDEA label is awarded after commissioning with at least 12 months of measured data and an independent audit; the SIA 2068 information sheet (PUE and PUE+ including heat reuse) is planned for mid 2026.
Using it in design
- At site selection, run a waste-heat potential analysis early covering the nearest heat customer, existing or planned heat networks and available temperature levels.
- For designs with heat recovery, target PUE+ and SDEA Gold rather than PUE alone; in the Schaffhausen example PUE+ of 1.20 or less is required within three years of commissioning.
- Notify the grid operator early of the connection power (2 to 20 MW conventional, up to 200 MW for AI); substation needs drive the project timeline.
- When choosing the cooling technology, compute annual water demand (m3 per GWh IT) and raise it with the water supply contract and the building permit process.
- Since waste heat is constant and low-temperature, include an industrial customer with steady heat demand or seasonal storage in the concept design.
Who should read it
Designers and developers preparing data-centre projects in Switzerland, and cantonal and municipal energy and planning officials.
Document contents
- What you need to know
- What you can do (efficiency requirements, identifying potential, early cooperation, informing the public)
- Data centres in Switzerland
- What a data centre means for canton and municipality
- Planning: laying the foundations for efficient data centres
- Existing sites: raising efficiency and identifying waste-heat sources
- Experience from practice
- Frequently asked questions
Publication details
- Authors
- EnergieSchweiz, Bundesamt für Energie
- Publisher
- EnergieSchweiz, Bundesamt für Energie
- Year
- Year not stated
- Document language
- German
- Source type
- Industry body
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official public publisher source inspected. No document-specific commercial redistribution permission established; metadata and original short summaries only. Local downloads are research evidence, not a redistribution package.
Citation
EnergieSchweiz, Bundesamt für Energie Rechenzentren – wichtige Tipps für Kantone und Gemeinden. EnergieSchweiz, Bundesamt für Energie. https://www.energieschweiz.ch/gemeinden/information-gemeinden/ratgeber-rechenzentren/
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.