Energinet Analysis Assumptions 2026 (AF26): Data Centres Sector Note
Original title Analyseforudsætninger til Energinet 2026 – Datacentre
Danish Energy Agency (Energistyrelsen)
Danish Energy Agency note (October 2026): data-centre electricity demand is projected from a maturity-weighted Energinet grid-connection pipeline and a European market-share model, cutting the long-term forecast to roughly half of AF25.
On this page
Overview
The October 2026 sector note from the Danish Energy Agency (Energistyrelsen) explains the data-centre section of the Analysis Assumptions for Energinet 2026 (AF26). A data centre is defined as specialised physical infrastructure housing IT equipment such as servers, storage and network devices, with associated cooling and power systems. Capacity is counted at the start of the year, so capacity installed during a year counts from the start of the next. The note is written in Danish.
Denmark has no separate policy target for data centres and no sector-specific regulation. A June 2026 political agreement on an emergency plan for the electricity grid signals upcoming changes to grid connection rules, including possible prioritisation among grid customers, and the government has announced a data-centre strategy; neither is yet in the AF26 model. The model assumes data centres are connected only to the electricity grid, though by June 2026 more than 10 data centres had asked about terms for connecting to the gas system.
Methodologically, the short term (to 2030) rests on Energinet's electricity consumption pipeline and the long term on an econometric model by Rambøll that estimates Denmark's share of European data-centre demand. Pipeline projects above 3 MW are weighted by maturity: connected 100%, connection agreement 80%, maturing 50%, screening 10%, initial dialogue 0%. A linear transition from pipeline to model runs over 2030-2035.
Operating assumptions are a linear ramp-up of grid-connection utilisation over 10 years, a utilised share of 70% of the connection, and 8,760 full-load hours a year. The biggest change from AF25 is the use of the Rambøll model; against newer international projections (IEA, ICIS, BloombergNEF) the previous approach would have given Denmark a disproportionate share. The new method cuts long-term demand to about half of AF25.
Key points
- The sector note is part of AF26; Energistyrelsen, October 2026, in Danish.
- Denmark has no specific policy target or sector-specific regulation for data centres.
- The June 2026 grid emergency plan foresees changes to connection rules and prioritisation of grid customers; these are not yet modelled.
- In June 2026 more than 10 data centres had asked for price and terms to connect to the gas system; the model assumes grid connection only.
- The pipeline includes projects of 3 MW and above; weights: connected 100%, connection agreement 80%, maturing 50%, screening 10%, initial dialogue 0%.
- The econometric model uses electricity price, renewable share, corporate tax and transatlantic fibre access as competitiveness parameters (2021-2024 data).
- Transition: 100% pipeline before 2030; 80/20 in 2031, 60/40 in 2032, 40/60 in 2033, 20/80 in 2034; fully model growth rate from 2035.
- Grid-connection utilisation ramps linearly over 10 years; utilised share is 70% and full-load hours are 8,760.
- The new method roughly halves long-term data-centre electricity consumption compared with AF25.
Using it in design
- When preparing a Danish data-centre connection request, note that the grid operator weights projects by maturity; a project at the connection-agreement stage appears in planning at 80% weight.
- Separate requested connection capacity from actual consumption; the model assumes a utilised share of 70% and a 10-year linear ramp.
- For grid connection delay or prioritisation risk, evaluate gas-connected on-site generation early, while accounting for its evolving regulatory status.
- Compare the 8,760 full-load hour assumption used in country-level demand scenarios with your own load profile to declare grid impact accurately.
- Record upcoming regulatory changes (connection rules, data-centre strategy) in the project risk register.
Who should read it
Investors planning data-centre connections in Denmark, grid connection advisers and energy system analysts.
Document contents
- 1. Introduction to data centres
- 2. Development towards 2050
- 3. Method and assumptions (short-term capacity, long-term electricity consumption, transition, operating patterns)
- 4. Differences from AF25
Publication details
- Authors
- Danish Energy Agency (Energistyrelsen)
- Publisher
- Danish Energy Agency (Energistyrelsen)
- Year
- 2026
- Document number
- AF26 sector note, J nr. 2026-388
- Document language
- Danish
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official landing https://ens.dk/analyser-og-statistik/analyseforudsaetninger-til-energinet and linked 6-page PDF opened; PDF downloaded and extracted. No explicit reuse licence found; citation only.
Citation
Danish Energy Agency (Energistyrelsen) (2026). Analyseforudsætninger til Energinet 2026 – Datacentre. Danish Energy Agency (Energistyrelsen). AF26 sector note, J nr. 2026-388. https://ens.dk/media/8838/download
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.