Insights from EPRI's Battery Energy Storage Systems (BESS) Failure Incident Database: Analysis of Failure Root Cause

Original title Insights from EPRI's Battery Energy Storage Systems (BESS) Failure Incident Database: Analysis of Failure Root Cause (2024 White Paper)

EPRI (Electric Power Research Institute) · EPRI, Pacific Northwest National Laboratory (PNNL) et al.

An EPRI white paper of May 2024: in the 26 BESS incidents with a known root cause, integration, assembly and construction is the most common cause, balance of system and controls dominate failed elements, and the cell is the source in only 3 (11%).

On this page

Overview

The white paper uses EPRI's BESS Failure Incident Database, started in 2021 after the South Korean fires and the Surprise, Arizona incident, to classify failures on two axes: root cause (design, manufacturing, integration-assembly-construction, operation) and the element where the failure began (cell or module, controls, balance of system or BOS). At the time of writing the database held 81 incidents. Only 26 had enough information to assign a root cause and failed element; none of the 9 incidents from 2011 to 2017 could be classified, while 36% of those since 2018 had an identified root cause.

The results challenge a common assumption. Integration, assembly and construction is the most common root cause, and the large majority of those incidents involved BOS components such as DC and AC wiring, HVAC subsystems and safety elements like fire suppression. Operation is the second most common cause and in every case sat in the controls system; seven were in South Korea in 2018 and 2019. Manufacturing is assigned least, because physical evidence is lost after a fire. Of failures with a known system age, 72% occurred during construction, commissioning or the first two years of operation.

Among failed elements, BOS and controls make up the vast majority; only 3 incidents (11%) are attributed directly to cells. Clean Energy Associates factory audits likewise found nearly 50% of quality items in the BOS, with 26% of inspected units showing fire suppression defects and 18% thermal management defects. As an example, in the 2022 Elkhorn incident rainwater ingress combined with insulation-loss alarms that were not properly escalated to the operator.

Recommendations are tabulated by root cause: code compliance and site-specific hazard assessment for design; workforce training, commissioning quality checks and system-level failure analysis of interfaces for integration; supplier verification and factory acceptance testing for manufacturing; and monitoring and analytics that augment the BMS for operation. The paper notes the results are limited to public data and calls on the industry to share root cause reports.

Key points

  1. The database held 81 incidents at the time of writing; 26 could be classified for root cause and failed element.
  2. None of the 9 incidents from 2011 to 2017 could be classified; the root cause is known for 36% of those since 2018.
  3. The most common root cause is integration, assembly and construction; most such incidents involve BOS components (wiring, HVAC, fire suppression).
  4. Operation is second and always sat in the controls; seven were in South Korea in 2018 and 2019 (SOC often above 90%).
  5. Only 3 incidents (11%) are attributed directly to cells; BOS and controls are the majority of failed elements.
  6. 72% of failures with a known system age occurred during construction, commissioning or the first two years of operation.
  7. 27 of the 30 incidents in 2018 and 2019 were in South Korea, where installed BESS rose from 30 in 2013 to 947 in 2018.
  8. In Clean Energy Associates audits, BOS was about 50% of quality items, with fire suppression defects in 26% and thermal management defects in 18% of inspected units.
  9. Three of the four design failures in 2023 came from one BOS design flaw (water intrusion in an enclosure design in New York and Idaho).

Using it in design

  • In battery room and container design, check water ingress points (vents, vent shields, cable penetrations) closely and require insulation-loss alarms to be escalated to the operator and monitoring.
  • Verify integration interfaces (DC and AC wiring, cooling, suppression piping) by system-level failure analysis and document compatibility of components from different suppliers.
  • If monitoring and communications are not online during commissioning, leaks and isolation failures can cascade; prepare a site-specific hazard assessment and procedure for commissioning.
  • Keep the BMS operating windows for SOC, voltage and current restricted and add monitoring and analytics that augment the BMS for early warning.
  • In procurement, specify factory acceptance testing, supplier quality verification and compliance with the latest UL and NFPA revisions.

Who should read it

Engineers who design, integrate, commission and operate battery energy storage and UPS battery systems, and insurance and safety specialists doing risk analysis.

Document contents

  1. Introduction
  2. Methodology and the BESS Failure Incident Database
  3. Data collection and classification of failure incidents
  4. Results overview
  5. Root causes of incidents
  6. Failed element
  7. Biaxial analysis
  8. Mitigations and recommendations
  9. Looking ahead
  10. Conclusion

Related standards

  • NFPA 855
  • UL 9540A

Publication details

Authors
EPRI; Pacific Northwest National Laboratory (PNNL); TWAICE
Publisher
EPRI (Electric Power Research Institute)
Year
2024
Document number
3002030360
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

EPRI white paper, public download; EPRI copyright.

Citation

EPRI; Pacific Northwest National Laboratory (PNNL); TWAICE (2024). Insights from EPRI's Battery Energy Storage Systems (BESS) Failure Incident Database: Analysis of Failure Root Cause (2024 White Paper). EPRI (Electric Power Research Institute). 3002030360. https://restservice.epri.com/publicdownload/000000003002030360/0/Product

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.