Technical guidePDF2025

National Roadmap for Data Centres: Rapporteur's Report

Finnish Government / Prime Minister's Office · Veli-Matti Mattila

Finland's national roadmap for data centres. It examines economic value, electricity-system flexibility, environmental effects and security, and proposes measures to attract higher-value activity. It is a national reference for site selection, grid connection and heat-reuse decisions.

CC BY-SA 4.0: share with attribution under the same licence

On this page

Overview

Prepared by Veli-Matti Mattila, appointed rapporteur by Prime Minister Petteri Orpo on 18 June 2025 with a term that ended on 31 October 2025, the report assesses Finland's position and strengths in international competition for data centres and their impact on the economy, power system, environment and security. It was published in the series Publications of the Finnish Government 2025:95, in an English edition dated 4 November 2025, and is licensed CC BY-SA 4.0. Its central concept is the high-value-added data centre: one that creates investment, jobs and tax revenue, registers with a designated national authority, and contributes flexibility to power generation and grid operation during peak-price periods.

The report gives the context in numbers: Finnish data centres used about 1.6 TWh of electricity in 2024 (under 2% of national consumption), expected to rise to 5-6 TWh, or 3-4% of national consumption, by 2030. European capacity is concentrated in the FLAPD markets (Frankfurt, London, Amsterdam, Paris, Dublin), where grid connection capacity increasingly constrains growth. Finland's advantages are fast grid access (time to power), electricity prices, abundant renewable energy, efficient cooling thanks to a cool climate, strong telecom links and the ability to use waste heat in district heating.

In the power-system section the report relays Fingrid's statement that spare connection capacity exists for data centres, especially in northern, western and eastern Finland, while capacity in the south is being significantly increased. Fingrid has received about 70 GW of connection enquiries, nearly half of them for data centres, and battery storage enquiries exceed 30 GW. In 2024, 95% of Finland's electricity came from fossil-free sources. On waste heat, about ten data centres supply district heating networks, which is about 20% of centres above 1 MW, and one barrier is the lack of economically viable demand within a reasonable distance.

The measures include three immediate steps: continuing electricity tax relief for high-value-added data centres at a substantial level and for a reasonably long period, creating a fossil-free flexibility scheme to manage grid scarcity and price spikes, and introducing a registration requirement to maintain an industry-wide situational picture. Other measures cover streamlined permitting, training, information-led guidance on siting with Fingrid and municipalities that considers grid capacity, waste heat and manufacturing synergies, telecom infrastructure, environmental performance beyond EU and national requirements, and security oversight covering greenfield investments and capacity leasing.

Key points

  1. Finnish data centres used about 1.6 TWh in 2024 (under 2% of national consumption); 5-6 TWh, or 3-4%, is expected by 2030.
  2. Fingrid has received about 70 GW of connection enquiries, nearly half for data centres; battery storage enquiries exceed 30 GW.
  3. In 2024, 95% of Finland's electricity came from fossil-free sources such as nuclear, wind, hydro, solar and renewable fuels.
  4. Three immediate measures: electricity tax relief for high-value-added data centres, a fossil-free grid flexibility scheme and a registration requirement.
  5. A high-value-added data centre has three features: economic value and regulatory compliance, registration with a national authority, and flexibility contribution at peak-price periods.
  6. Principles: data centres should increase renewable generation, take part in system balancing and locate at grid-favourable sites close to generation.
  7. As much waste heat as possible should be recovered for building heating, district heating or industry.
  8. About ten data centres supply district heating, about 20% of centres above 1 MW.
  9. European capacity is concentrated in FLAPD markets; Finland's advantages are fast grid access, electricity prices, renewable energy and scalability.

Using it in design

  • For Finnish sites, verify grid connection capacity with Fingrid early; the report states spare capacity exists in the north, west and east and that southern capacity is being increased.
  • Make waste-heat output temperature and the connection route to a nearby district heating network design inputs; reasonable distance to heat demand is the economic precondition for recovery.
  • Build grid flexibility (demand-side flexibility, reserve generation capacity and storage) into the design; the report treats flexibility contribution at high-price periods as a main evaluation criterion.
  • Track how national requirements and possible regulatory changes for registration, electricity tax relief and permitting affect the project schedule.
  • Take account early of the EU Energy Efficiency Directive's waste-heat use and environmental reporting obligations in the design.

Who should read it

Developers and designers planning data-centre investment in Finland, grid-connection and site-selection teams, and policy and regulatory analysts.

Document contents

  1. Preface
  2. Mandate and implementation
  3. National objectives for data centre operations (high-value-added data centres, principles, proposals for measures)
  4. International competition for data centres
  5. Current state of data centres and economic impact (current situation and outlook, value added, employment and tax revenue, spillover effects)
  6. Data centres as part of the power system
  7. Environmental impacts of data centres
  8. Data centres and security
  9. Appendices: Common claims and facts about data centres, consultations and participants, written views submitted
  10. References

Read the document

finland-national-roadmap-data-centres-2025.pdf

PDF · 0.8 MB · English

CC BY-SA 4.0: share with attribution under the same licence

The document is provided unaltered because its licence permits redistribution.

Publication details

Authors
Veli-Matti Mattila
Publisher
Finnish Government / Prime Minister's Office
Year
2025
Document number
Publications of the Finnish Government 2025:95; ISBN 978-952-383-885-7
Document language
English
Source type
Expert / community
Access
Open licence (downloadable)
Licence
CC BY-SA 4.0: share with attribution under the same licence
Original licence note

Creative Commons Attribution-ShareAlike 4.0 International; licence verified from the licence statement in the document itself. Attribution to the authors and publisher is kept; adaptations must keep the same licence.

Citation

Veli-Matti Mattila (2025). National Roadmap for Data Centres: Rapporteur's Report. Finnish Government / Prime Minister's Office. Publications of the Finnish Government 2025:95; ISBN 978-952-383-885-7. https://julkaisut.valtioneuvosto.fi/server/api/core/bitstreams/057514dd-ba36-4fa4-b000-fce8f83e5183/content

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.