Technical guideFree to read2024

Code of Practice for Energy Efficiency of Building Services Installation, 2024 Edition (Hong Kong BEC 2024)

Original title Code of Practice for Energy Efficiency of Building Services Installation, 2024 Edition

Electrical and Mechanical Services Department, Hong Kong

The 88-page building energy code of the Hong Kong Electrical and Mechanical Services Department (EMSD); for data centre design the most relevant part is section 7: distribution losses, power quality and metering and monitoring rules.

On this page

Overview

The document is the 2024 edition of Hong Kong's code setting energy efficiency requirements for lighting, air conditioning, electrical, lift and escalator installations in buildings. It also includes a performance-based approach and definitions. For the data centre designer the most directly relevant part is the electrical installation section (section 7): distribution transformer efficiency, copper losses in main, feeder, sub-main and final circuits, motor efficiency, power quality and metering and monitoring facilities.

Distribution losses are given as numerical limits. A minimum efficiency table applies to distribution transformers not owned by the electricity supplier (98% up to 1000 kVA, 99% above). Copper loss in the main circuit between the transformer and the main incoming breaker of the LV switchboard may not exceed 0.5% of the active power transmitted; alternatively, the transformer room and main switch room are placed beside, above or below each other. Limits are 2.5% for a feeder circuit, 1.5% for a sub-main up to 100 m, 2.5% above 100 m, and 1% for a final circuit over 32 A.

The power quality section requires a design total power factor of not less than 0.85 and current total harmonic distortion (THD) within the table limits: 20% below 40 A, 15% for 40-400 A, 12% for 400-800 A, 8% for 800-2000 A and 5% above 2000 A. For three-phase 4-wire circuits at or above 400 A with single-phase loads, current unbalance may not exceed 10%. A correction device, or a connection point for one, must be provided as a reserved spare way.

The metering and monitoring rules are as follows: a main incoming circuit at or above 400 A is fitted with devices measuring voltages (phase-to-phase and phase-to-neutral), currents (three phases and neutral), total power factor, total energy (kWh), maximum demand (kVA) and total harmonic distortion. A feeder or sub-main above 200 A and below 400 A measures currents and kWh; at or above 400 A it measures the full parameter set. The chilled water plant, heated water plant, lifts, escalators and EV charging facilities are metered separately. THD measurement must reach at least the 31st harmonic, parameters are trended every 15 minutes with hourly, daily, monthly and annual data, and data must be kept for at least 36 months. The document is a building code and contains no data-centre-specific rules; its scope follows section 7.1.

Key points

  1. Main incoming circuit at or above 400 A: voltages (phase-to-phase, phase-to-neutral), currents (three phases and neutral), total power factor, kWh, maximum demand (kVA) and THD are measured.
  2. Feeder or sub-main above 200 A and below 400 A: currents (three phases and neutral) and kWh are measured; at or above 400 A the full main-circuit parameter set is measured.
  3. Parameters are trended every 15 minutes with hourly, daily, monthly and annual data; data are kept for at least 36 months.
  4. THD metering devices must measure at least up to the 31st harmonic order.
  5. The chilled water plant, heated water plant, all lifts, escalators and EV charging facilities are metered separately.
  6. Copper loss limits: main circuit 0.5% of active power, feeder 2.5%, sub-main up to 100 m 1.5% (above 100 m 2.5%), final circuit over 32 A 1%.
  7. Current THD limits: 20% below 40 A, 15% for 40-400 A, 12% for 400-800 A, 8% for 800-2000 A, 5% above 2000 A.
  8. Design total power factor not less than 0.85; current unbalance not above 10% on three-phase 4-wire circuits at or above 400 A.
  9. Minimum distribution transformer efficiency: 98% up to 1000 kVA, 99% above (tested to IEC 60076-1 at full load, harmonic-free, unity displacement power factor).

Using it in design

  • For main incoming and feeder circuits at or above 400 A, add voltage, current (including neutral), power factor, kWh, kVA maximum demand and THD to the metering point list, and write the 31st harmonic capability into the device specification.
  • Size a monitoring system that collects measurements at 15-minute intervals, produces hourly, daily, monthly and annual summaries and retains data for 36 months.
  • Plan the distance between transformer and main switchboard so that main circuit copper loss stays below 0.5%, or place the rooms adjacent.
  • Check feeder, sub-main and final circuit cross-sections against the copper loss limits (feeder 2.5%, sub-main 1.5% or 2.5%, final circuit over 32 A 1%).
  • If Hong Kong rules do not apply to your data centre, use this document as a benchmark for metering granularity; do not carry it into the project specification as a regulatory provision.

Who should read it

Engineers designing electrical distribution, metering and energy monitoring requirements, and teams delivering projects in Hong Kong.

Document contents

  1. Scope and definitions
  2. Lighting
  3. Air conditioning
  4. Electrical installation (section 7): power distribution loss, motor installation, power quality, metering and monitoring facilities
  5. Lift and escalator installation
  6. Performance-based approach

Publication details

Authors
Electrical and Mechanical Services Department, Hong Kong
Publisher
Electrical and Mechanical Services Department, Hong Kong
Year
2024
Document number
BEC 2024
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Official publisher document inspected. No document-specific commercial redistribution permission established; retain metadata and original short summaries only.

Citation

Electrical and Mechanical Services Department, Hong Kong (2024). Code of Practice for Energy Efficiency of Building Services Installation, 2024 Edition. Electrical and Mechanical Services Department, Hong Kong. BEC 2024. https://www.emsd.gov.hk/beeo/en/pee/BEC_2024_ENG.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Power design in SoSo CAD

Calculate supply paths, equipment loads and UPS failure scenarios as part of the design.

Single-line diagram in the SoSo CAD power and capacity workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.