Total Energy Model 4.0: Data Centres
Original title Total Energy Model 4.0: Data Centres: Final report
IEA 4E EDNA · Anson Wu, Fiona Brocklehurst
The IEA 4E EDNA report of May 2025 presents a bottom-up data-centre energy model built on CPU sales and SERT measurements; its unconstrained base case gives 2,510 TWh in 2030, a figure it judges unrealistic.
On this page
Overview
The report was written by Anson Wu and Fiona Brocklehurst of Hansheng Ltd and Ballarat Consulting for the EDNA platform of the IEA 4E TCP. The Total Energy Model 4.0 (TEM) forecasts data-centre energy not by extrapolating equipment sales or data traffic but through computational capacity and efficiency metrics. Its main inputs are CPU sales data and Server Efficiency Rating Tool (SERT) performance measurements.
The model segments the market by data-centre type (traditional, cloud, hyperscale, AI) and workload (general compute, AI) across five global regions. The calculation has four stages: total computational capacity from CPU sales, server energy from utilisation and efficiency, storage and network energy as a proportion of server energy, and finally infrastructure energy through PUE.
On the policy side the model can assess minimum efficiency standards and labels, utilisation improvements, PUE targets, moving traditional data centres to cloud and hyperscale, and changes in server lifetime. In the results, non-AI compute energy roughly triples by 2034, with most of the growth in hyperscale facilities, and infrastructure energy remains a significant share outside AI.
The report is explicit about limits. Because AI capacity is grown by simple trend extrapolation and no power, chip or capital constraints are applied, energy is dominated by AI after 2030. Comparison with Andrae (2020), Goldman Sachs (2024), SemiAnalysis (2024) and LBNL (2024), together with a sensitivity analysis, shows that the model's medium-term values are unrealistically high.
Key points
- TEM 4.0 is a bottom-up hybrid model that converts CPU sales and SERT results into computational capacity and efficiency metrics.
- Market segments: traditional, cloud, hyperscale and AI; five global regions.
- Data centres account for roughly 1-2% of global electricity use, and 2030 estimates differ by more than an order of magnitude between studies.
- Non-AI compute energy is relatively stable over 2015-2020 and roughly triples by 2034, mostly in hyperscale.
- After 2030 energy is entirely AI-driven; the model does not include power, budget or chip-supply constraints.
- Comparison (TWh, base case, 2023 and 2030): Andrae 375 and 974; Goldman Sachs 425 and 1,150; SemiAnalysis 450 and 1,500; TEM 4 323 and 2,510.
- 2030 ranges: Goldman Sachs 820-1,400 TWh, SemiAnalysis 500-2,250 TWh.
- North America consumes the most electricity, followed by Europe and Asia; South America and the Middle East and Africa are very low.
- PUE is used as the most widely available infrastructure efficiency metric, but may carry reporting bias in favour of efficient facilities.
Using it in design
- In capacity planning, build low and high scenarios for AI load that include power and chip-supply constraints rather than a single trend extrapolation.
- For non-AI compute, model the effect of server efficiency and utilisation gains separately from PUE targets that reduce infrastructure energy.
- Keep the server lifetime assumption, especially for AI hardware, as an explicit parameter; the report shows it strongly affects installed base and energy.
- When using external national or regional demand forecasts, check whether the method is constrained or unconstrained, and treat unconstrained forecasts as upper bounds.
- When using PUE data for benchmarking, allow for reporting bias and verify against site measurement.
Who should read it
Energy policy analysts, planners producing data-centre demand forecasts and engineers assessing server and infrastructure efficiency scenarios.
Document contents
- Executive Summary
- Introduction
- Methodology (market segmentation, computational capacity, AI computational capacity, energy consumption, infrastructure energy)
- Policy modelling
- Results
- Comparisons with other projections
- Sensitivity analysis
- Conclusions
- Annex A: PUE data sources
- Annex B: Model dashboard
Publication details
- Authors
- Anson Wu; Fiona Brocklehurst
- Publisher
- IEA 4E EDNA
- Year
- 2025
- Document number
- Final report, 31 May 2025
- Document language
- English
- Source type
- Government / public
- Access
- Free to read
- Licence
- Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note
Official publisher document inspected. No document-specific commercial redistribution permission established; retain metadata and original short summaries only.
Citation
Anson Wu; Fiona Brocklehurst (2025). Total Energy Model 4.0: Data Centres: Final report. IEA 4E EDNA. Final report, 31 May 2025. https://iea-4e.org/wp-content/uploads/2025/05/TEM-4-Report-Draft-v0-15-FINAL.pdf
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.