Research paperFree to read2026

A systematic analysis of data center water use, methodological divergence, and policy implications

Environmental Research Communications (IOP Publishing) · Julia A. Davis, Landon T. Marston et al.

A 2026 paper by Davis, Marston and Shafiee-Jood analysing 100 data-centre water estimates from 33 sources: indirect (Scope 2) water is about 2-12 times direct use, and a nine-element reporting standard is proposed.

On this page

Overview

Published estimates of data-centre water use vary by several orders of magnitude, which creates interpretive problems for policymakers, utilities and the public. The paper examines how methodological choices relate to this divergence. It compiles 100 estimates from 33 sources, including academic studies, government reports, corporate disclosures and industry analyses, and classifies each across seven analytical dimensions such as system boundary, water metric, operational assumptions and temporal basis.

The results show that divergence is structured rather than arbitrary. Within the same sources, indirect electricity-related water use (Scope 2) is about 2-12 times larger than direct on-site use (Scope 1). The choice between consumption and withdrawal can produce differences from modest to extreme, while cooling technology assumptions and facility composition add variability even in normalised metrics. Growth scenario assumptions widen the gap between historical and projected values.

The authors conclude that aggregated and modelled estimates are not directly comparable without accounting for methodological choices. They propose a minimum reporting standard of nine disclosure elements: system boundary, water metric, electricity attribution, cooling technology, operational efficiency definition, spatial scale, temporal resolution, growth scenario basis and data provenance. The aim is that estimates can be matched to the decisions they inform, such as benchmarking, utility planning and permitting.

Key points

  1. 100 estimates from 33 sources were compiled and classified on seven analytical dimensions.
  2. Published data-centre water estimates vary by several orders of magnitude.
  3. Within the same sources, indirect electricity-related water (Scope 2) is about 2-12 times direct use (Scope 1).
  4. The consumption versus withdrawal distinction can create differences from modest to extreme.
  5. Cooling technology assumptions and facility composition add variability even in normalised metrics.
  6. Growth scenario assumptions widen the gap between historical and projected values.
  7. The proposed minimum standard has nine elements: system boundary, water metric, electricity attribution, cooling technology, efficiency definition, spatial scale, temporal resolution, growth scenario basis and data provenance.

Using it in design

  • When reporting a data centre's water figure, state the system boundary (Scope 1 or 2) and the metric (consumption or withdrawal).
  • Before comparing WUE or water estimates from different sources, check that the methodological dimensions match.
  • In the demand file for the utility, document cooling technology, spatial and temporal scale and data source against the nine-element list.
  • If benchmarking, utility planning and permitting need different numbers, produce each with the method suited to its purpose.

Who should read it

Engineers and analysts working on data-centre water reporting, sustainability measurement and utility planning.

Related standards

  • ISO/IEC 30134-9 (WUE)

Publication details

Authors
Julia A. Davis; Landon T. Marston; Majid Shafiee-Jood
Publisher
Environmental Research Communications (IOP Publishing)
Year
2026
Document language
English
Source type
Scientific
Access
Free to read
Licence
CC BY 4.0: share with attribution
Original licence note

Licence CC-BY-4.0 stated on publisher landing page (fetched 2026-11-16); matches Crossref licence metadata. Round 1 ingestion retains bibliographic metadata only; no local full text is redistributed.

Citation

Julia A. Davis; Landon T. Marston; Majid Shafiee-Jood (2026). A systematic analysis of data center water use, methodological divergence, and policy implications. Environmental Research Communications (IOP Publishing). https://doi.org/10.1088/2515-7620/aebc1a

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cooling capacity in SoSo CAD

Check zone heat loads, installed capacity and the capacity left with the largest unit out, as part of the design.

Zone heat loads and capacity balance in the SoSo CAD cooling workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.