Recommendation ITU-T L.1308 (12/2025): Guidelines for the implementation of low-carbon data centres to climate change mitigation and adaptation

International Telecommunication Union (ITU-T) · ITU-T Study Group 5

ITU-T Recommendation L.1308 (December 2025) advises new low-carbon data centres to target an annual PUE of 1.3 in cool and 1.4 in warm climates, with a 75% renewable energy factor.

On this page

Overview

L.1308 is an ITU-T Recommendation that gives guidance for six data-centre lifecycle stages: site selection, design, procurement, construction, operation, and decommissioning and recycling. It was approved on 14 December 2025 and is in force. Its purpose is to tie data centres' contribution to climate mitigation to measurable targets by cutting energy use and dependence on fossil fuels.

The core of the text is seven requirement areas: energy efficiency, renewable energy, water conservation, waste-heat reuse, lifecycle greenhouse gas emissions, the CUE ratio and the circular economy. Each is tied to an ISO/IEC 30134 indicator: PUE, renewable energy factor (REF), WUE, energy reuse factor (ERF) and CUE. Operators are advised to review these regularly and, where useful, to commission a third-party gap analysis against the targets.

The numeric targets are anchored in industry averages. The text cites the Uptime Institute 2024 average PUE of 1.56 and suggests an annual PUE of 1.3 for new facilities running at full capacity in cool climates and 1.4 in warm climates. It recommends a 75% REF or hourly carbon-free energy, and a 100% waste diversion rate for retired equipment. Lifecycle emissions are the sum of construction, operation and demolition; site selection, design and procurement emissions are left out of the calculation.

The design clauses go down to engineering decisions: separating cold and hot air, free cooling, zoned air conditioning by load density, liquid cooling for high-density cabinets, low-GWP refrigerants, distribution close to the load centre, high-frequency modular UPS and high-density backup power in place of lead-acid. The text is guidance, not a binding standard, and its targets are recommendations.

Key points

  1. Six lifecycle stages are covered: site selection, design, procurement, construction, operation, and decommissioning and recycling.
  2. The 2024 industry average PUE is cited as 1.56; the suggested annual PUE target at full load for new low-carbon facilities is 1.3 in cool climates and 1.4 in warm climates.
  3. A renewable energy factor (REF) of 75% or hourly carbon-free energy is recommended, sourced from on-site generation, direct purchase from nearby plants or green power trading.
  4. For water, lower-consumption cooling technology plus reclaimed water and rainwater are recommended to reduce WUE.
  5. For waste heat, ERF is reported; the reuse plan, including district heating connection, should cover technical feasibility, cost, and supply and demand matching. Heat users are sought typically within a few kilometres.
  6. Lifecycle emissions are E_total = E_construction + E_operation + E_demolition, and may include Scope 1, 2 and optional Scope 3 emissions.
  7. CUE = E / P_IT (P_IT in MWh); in the short term it should sit well below the local grid average, and for net zero it should trend to 0.
  8. All e-waste and waste batteries should be reused, remanufactured or recycled, for a waste diversion rate of 100%.
  9. Low IT utilisation pushes electrical and cooling plant into an inefficient range, and scattered cabinet placement brings extra UPS and pump load online. Server utilisation is tracked with ISO/IEC 30134-5.

Using it in design

  • Add PUE (1.3 or 1.4), REF (75%), CUE, WUE and ERF to the early-design target table, and define each measurement boundary according to the ISO/IEC 30134 series.
  • Add renewable energy access, natural cooling sources, grid capacity that does not affect residential and hospital supply, and heat users within a few kilometres to the site-selection criteria.
  • Put cold and hot aisle separation, floor sealing and free-cooling potential in the airflow checklist, and define separate zones and control strategies for halls with different power densities.
  • Write liquid cooling for high-density cabinets, zero-ODP and low-GWP refrigerant criteria and super-bypass or intelligent on-line UPS evaluation into the specification.
  • For operation, prepare a cabinet placement plan aligned with design power density and a list of metering points for energy, water, waste and waste heat.

Who should read it

Data-centre designers, operators and decision makers who set sustainability targets and write low-carbon project specifications.

Document contents

  1. Scope
  2. Definitions
  3. Basic requirements for low-carbon data centre (energy efficiency, renewable energy, water conservation, reuse of waste heat, lifecycle GHG emissions, CUE, circular economy)
  4. Guidelines for implementation: site selection, design, procurement, construction, operation, decommissioning and recycling stages

Related standards

  • ISO/IEC 30134-2
  • ISO/IEC 30134-3
  • ISO/IEC 30134-6
  • ISO/IEC 30134-9

Publication details

Authors
ITU-T Study Group 5
Publisher
International Telecommunication Union (ITU-T)
Year
2025
Document number
ITU-T L.1308 (12/2025)
Document language
English
Source type
Expert / community
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

(c) ITU 2026, all rights reserved; PDF is freely downloadable from ITU.

Citation

ITU-T Study Group 5 (2025). Recommendation ITU-T L.1308 (12/2025): Guidelines for the implementation of low-carbon data centres to climate change mitigation and adaptation. International Telecommunication Union (ITU-T). ITU-T L.1308 (12/2025). https://www.itu.int/rec/T-REC-L.1308-202512-I

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Cost studies in SoSo CAD

Calculate equipment cost, energy cost and total cost of ownership (TCO) from the design’s quantities and your own price assumptions.

CAPEX and TCO estimates in the SoSo CAD cost workspace

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.