Technical guideFree to read2025

Fiber Optic-Backbone, Metro and Last Mile Infrastructure Standard

ICT Authority Kenya

Kenya ICT Authority standard ICTA.2.2.004:2025 sets 1500 mm trench depth, maintenance-chamber and cable specifications, fibre attenuation limits, and acceptance testing with bidirectional OTDR and splice loss of at most 0.1 dB.

On this page

Overview

The standard aims to close the gap in standards for territorial ICT connectivity that the Kenya National Digital Masterplan 2022-2032 identifies. Scope is the minimum requirements for planning, design, deployment, operation, maintenance and management of backbone, metro and last-mile fibre optic cable, applying to entities planning, designing and operating fibre infrastructure within Kenya. Requirements cover ducts, maintenance chambers, hand holes, way leaves, poles, fibre cables, markings, aerial cable, the design process, the fibre test process and civil works. The cover states the second edition while document control states the third.

Civil and duct requirements are numeric. Trenches are excavated to 1500 mm depth in all soils, with bottom and top width of at least 300 mm; in soft or unstable soils a 150 mm compacted bedding layer mixed with 5 to 8% cement or lime is laid. Backfill is compacted in 150-200 mm layers. Unstable soils use a concrete envelope at 1:2:4 (cement:sand:gravel), water-cement ratio 0.45 to 0.60 and at least seven days of curing. Maintenance chambers are at least 1600 x 1300 x 1600 mm with a cover load rating of at least 135 kN and a digital lock that the NOC can monitor. Markers are placed at intervals of at most 500 m in rural terrain.

Fibre specifications: attenuation of at most 0.36 dB/km at 1310 nm and 0.23 dB/km at 1550 nm, tensile strength of at least 1,500 N short term and 600 N long term, and crush resistance of 2,000 N/10 cm. Cables are laid in ducts at least 1500 mm deep. The test process follows ITU-T G.650.3: OTDR testing, insertion loss (IL), optical return loss (ORL), continuity and polarity, and end-face inspection. The sequence is pre-test inspection, continuity, OTDR from both ends, insertion loss with a light source and power meter, and recorded results for each fibre core.

Acceptance criteria unless otherwise specified: splice loss at most 0.1 dB per splice, connector loss at most 0.3 dB, total link loss per the design budget, and ORL at least 35 dB for most access links. Handover reports include OTDR traces (PDF and SOR), insertion loss and ORL data, end-face images, test equipment serial numbers and calibration certificates, and tester name and certification; non-compliant fibres are repaired and retested, and the Authority may audit at random.

Key points

  1. Scope: planning, design, deployment, operation and maintenance of backbone, metro and last-mile fibre in Kenya.
  2. Trench 1500 mm deep, bottom and top width at least 300 mm; 150 mm stabilised bedding in soft soil; backfill in 150-200 mm layers.
  3. Unstable soil: 1:2:4 concrete envelope, water-cement ratio 0.45-0.60, at least seven days curing.
  4. Maintenance chamber at least 1600 x 1300 x 1600 mm, cover load rating at least 135 kN, digital lock monitored from the NOC.
  5. Fibre attenuation at most 0.36 dB/km (1310 nm) and 0.23 dB/km (1550 nm); tensile strength at least 1,500 N short term, 600 N long term.
  6. Cable ducts at least 1500 mm deep; markers at most every 500 m in rural terrain and at every chamber, crossing and customer termination.
  7. Tests follow ITU-T G.650.3: OTDR from both ends, insertion loss with light source and power meter, ORL, continuity and polarity, end-face inspection.
  8. Acceptance: splice loss at most 0.1 dB, connector loss at most 0.3 dB, ORL at least 35 dB for most access links.
  9. Handover report: OTDR traces (PDF and SOR), IL and ORL data, end-face images, equipment IDs and calibration certificates, tester certification.

Using it in design

  • When planning data-centre entry routes, use this standard's 1500 mm trench depth and chamber size (1600 x 1300 x 1600 mm) as reference and apply them on two independent routes.
  • Compute the fibre link budget with 0.36 dB/km (1310 nm) and 0.23 dB/km (1550 nm) attenuation, 0.1 dB per splice and 0.3 dB per connector.
  • In the handover specification require bidirectional OTDR, IL and ORL (at least 35 dB), end-face images, calibration certificates and tester certification.
  • Connect chamber digital locks to NOC monitoring and put the marker spacing (500 m in rural areas) in the route document.
  • Archive reported results per fibre core and retest after repair or change following commissioning.
  • Because the cover states the second edition and document control the third, confirm with the ICT Authority which edition to cite and record it.

Who should read it

Engineers planning, building and commissioning fibre infrastructure in Kenya, data-centre connectivity designers and public infrastructure auditors.

Document contents

  1. Introduction, scope, application, normative references, definitions, abbreviations, sub-domains
  2. Requirements: ducts
  3. Maintenance chambers
  4. Hand holes
  5. Way leaves
  6. Poles
  7. Fiber cables
  8. Markings
  9. Aerial cable
  10. Design process
  11. Fiber test process
  12. Civil works
  13. Annexes: duct physical and technical requirements, trench and concrete specifications

Publication details

Authors
ICT Authority Kenya
Publisher
ICT Authority Kenya
Year
2025
Document number
ICTA.2.2.004:2025
Document language
English
Source type
Government / public
Access
Free to read
Licence
Copyright retained; citation only: the publisher’s terms apply to the original document
Original licence note

Public official source inspected; no document-specific commercial redistribution permission established. Original short summaries and metadata only; downloads are local research evidence. PDF p. 2 expressly reserves ICTA copyright and reproduction rights.

Citation

ICT Authority Kenya (2025). Fiber Optic-Backbone, Metro and Last Mile Infrastructure Standard. ICT Authority Kenya. ICTA.2.2.004:2025. https://cms.icta.go.ke/sites/default/files/2025-11/Fiber%20Standard%202025.pdf

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Standards pre-assessment in SoSo CAD

Run TS EN 50600 and Tier pre-checks on the model, with missing inputs and items for engineering review listed separately.

Selected rule packs and findings in the SoSo CAD standards panel

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.