Best Practices for Large Load Interconnections: A North American Perspective on Data Centers
CIGRE US National Committee, 2025 Grid of the Future Symposium (arXiv preprint) · Rafi Zahedi, Amin Zamani et al.
A review of published large-load interconnection guidance from AEP, Dominion, ERCOT, Ameren (MISO), PG&E, Southern Company and SPP, organised into eight categories: load management, power quality, voltage and frequency ride-through, post-disturbance recovery, protection, communications/control, and study/modelling.
CC0 1.0: public domain dedication; free to reuse
On this page
Overview
Large loads are expanding rapidly across North America, led by data centres, cryptocurrency mining, hydrogen production facilities and heavy-duty charging stations. Data centres draw particular attention as AI deployment drives unprecedented capacity growth; their scale, duty cycles and converter-dominated interfaces introduce new challenges for transmission interconnections regarding disturbance behaviour, steady-state performance and operational visibility. In July 2024 a 230 kV fault in the Eastern Interconnection tripped 1,500 MW of data-centre load; between late 2023 and early 2025 ERCOT and the Eastern Interconnection recorded 25 crypto-mining load losses of 100-400 MW each.
The authors extract explicit numeric limits at the point of interconnection and compare them. Large-load thresholds differ: Dominion ≥50 MW for power-electronic loads, ERCOT ≥75 MW per site with a 25 MW substation visibility threshold, Southern ≥50 MW above 40 kV, SPP >10 MW at 69 kV or >50 MW at higher voltage. Southern Company is the only entity in this review with a numeric ramp cap, ≤20 MW/min under normal operation. Power quality: Dominion ≤3% instantaneous voltage fluctuation at the POI; Ameren uses IEEE 519 and IEEE 1453; PG&E Rule 2 limits THD ≤5% and ~10% imbalance.
SPP's VRT curve is 0.90-1.10 pu continuous with short-duration tolerance down to ~0.50 pu for ~0.15 s; Dominion requires ride-through of several reclosing shots of ~50-70 ms with undervoltage pickup near 85%. SPP FRT example: continuous 58.8-61.2 Hz, extended tolerance for 299 s outside that band, trip permissible above ~61.8 Hz or below ~57.0 Hz. ERCOT is the only entity with a numeric recovery target: ≥90% of pre-disturbance load restored within 1 second once V_POI ≥ 0.9 pu (proposal). Only SPP and ERCOT publish explicit POI-based VRT envelopes; load FRT is mostly tied to UFLS schemes.
The finding is that protection and power-quality rules are fairly mature and converge on IEEE 519/1453, whereas ride-through envelopes, ramp limits, recovery targets and even the definition of a 'large load' vary widely; the authors argue for harmonised VRT/FRT envelopes and telemetry similar to European practice. Limits: a review of seven entities' published guidance; rules are evolving fast, and it is a preprint.
Key points
- In July 2024 a 230 kV fault in the Eastern Interconnection tripped 1,500 MW of data-centre load; between late 2023 and early 2025 ERCOT and the Eastern Interconnection recorded 25 crypto-mining load losses of 100-400 MW each.
- Large-load thresholds differ: Dominion ≥50 MW for power-electronic loads, ERCOT ≥75 MW per site (25 MW substation visibility threshold), Southern ≥50 MW above 40 kV, SPP >10 MW at 69 kV or >50 MW at higher voltage.
- Southern Company is the only entity in this review with a numeric ramp cap: ≤20 MW/min under normal operation.
- Power quality: Dominion ≤3% instantaneous voltage fluctuation at the POI; Ameren IEEE 519 and IEEE 1453; PG&E Rule 2 THD ≤5% and ~10% imbalance.
- SPP's VRT curve: 0.90-1.10 pu continuous with short-duration tolerance down to ~0.50 pu for ~0.15 s; Dominion requires ride-through of several reclosing shots of ~50-70 ms with undervoltage pickup near 85%.
- SPP FRT example: continuous 58.8-61.2 Hz, extended tolerance for 299 s outside that band, trip permissible above ~61.8 Hz or below ~57.0 Hz.
- ERCOT is the only entity with a numeric recovery target: ≥90% of pre-disturbance load restored within 1 second once V_POI ≥ 0.9 pu (proposal).
- Only SPP and ERCOT publish explicit POI-based VRT envelopes; load FRT is mostly tied to UFLS schemes.
Using it in design
- In a large-load interconnection application, verify the relevant entity's large-load threshold (10-75 MW) and ramp limit (Southern ≤20 MW/min) early; definitions differ widely between entities.
- Check data-centre ride-through design against the VRT envelopes at the point of connection (SPP: 0.90-1.10 pu continuous, ~0.50 pu for ~0.15 s; Dominion: several ~50-70 ms reclosing shots) and FRT bands.
- Design for power quality at the point of connection to IEEE 519 and IEEE 1453, and plan permanent power-quality metering and telemetry.
- Add the target ERCOT proposes for post-disturbance recovery (≥90% within 1 second) to UPS and load-reconnection logic.
Who should read it
Grid engineers and designers preparing large data-centre load interconnection applications and comparing entities' technical requirements.
Document contents
- 1. Introduction
- 2. USA Large Load Technical Interconnection Requirements
- 3. European Experience and Vision
- 4. Conclusion
Related standards
- IEEE 519
- IEEE 1453
- IEEE 2800-2022
- IEEE 1668-2017
- NERC PRC-029-1
- ITI (CBEMA) curve
Read the document
large-load-interconnection-best-practices-2026.pdf
CC0 1.0: public domain dedication; free to reuse
The document is provided unaltered because its licence permits redistribution.
Publication details
- Authors
- Rafi Zahedi; Amin Zamani; Rahul Anilkumar
- Publisher
- CIGRE US National Committee, 2025 Grid of the Future Symposium (arXiv preprint)
- Year
- 2025
- Document number
- arXiv:2601.12686
- Document language
- English
- Source type
- Scientific
- Access
- Open licence (downloadable)
- Licence
- CC0 1.0: public domain dedication; free to reuse
- Licence evidence
- arxiv.org
Original licence note
arXiv record licence is http://creativecommons.org/publicdomain/zero/1.0/ (CC0, checked via arXiv OAI-PMH)
Citation
Rafi Zahedi; Amin Zamani; Rahul Anilkumar (2025). Best Practices for Large Load Interconnections: A North American Perspective on Data Centers. CIGRE US National Committee, 2025 Grid of the Future Symposium (arXiv preprint). arXiv:2601.12686. https://doi.org/10.48550/arXiv.2601.12686
All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.